CITY COUNCIL STAFF REPORT
DATE: March 7, 2007 CONSENT
SUBJECT: Gensler Change Order No.3 — Additional Structural Services — Airport
Hold-room
FROM: David H. Ready, City Manager
BY: City Manager
SUMMARY
This action would provide approval of a Change Order to the Gensler architectural
design contract to add structural design services for the Airport Hold-room project in the
amount of$12,000.
RECOMMENDATION:
Recommend that City Council adopt Minute Order No. approving Change Order
No. 3 to Agreement No. A4382 (Amendment No. 11) with Gensler adding structural
design services for the Regional Jet Hold-room project to the design contract for an
amount not to exceed $12,000, subject to approval of the Federal Aviation
Administration.
STAFF ANALYSIS:
Gensler is the architectural firm that designed the Regional Jet Hold-room and the
Security Check Point Expansion projects. The original contract included design as well
as construction administration services from the architect and all the design consultants.
Both projects were budget to run concurrent over a ten month period. The projects
were split apart for budget purposes and the first project, Security Check Point, ran well
beyond the original budgeted time. These delays and changes were beyond the control
of the design consultants and they quickly exhausted the budget that was allocated for
construction administration. Of particular concern has been the structural consultant
who has continued to provide services despite the fact that funding has run out. The
Hold-room project is in a critical period where the help of the structural designer is
ITEM NO.J�—
City Council Staff Report
March 7, 2007 - Page 2
Gensler Change Order
of $12,000; see attached proposal letter. Staff recommends approval of the attached
Minute Order to approve the contract increase
FISCAL IMPACT:
The design work contemplated in the Change Order is eligible under AIP 38 for
reimbursement and is budgeted in account 415-6600-56063.
4I"
1
Allen F. Smoot, AirpoN Construction Administrator
David H. Ready, City If
Attachments:
1. Minute Order
2. Change Order
MINUTE ORDER NO.
APPROVING CHANGE ORDER NO. 3 TO
AGREEMENT NO. A4382 (AMENDMENT NO, 11)
WITH GENSLER, ADDING STRUCTURAL, DESIGN
SERVICES FOR TIIE REGIONAL JET HOLD-ROOM
PROJECT TO TIIE DESIGN CONTRACT FOR AN
AMOUNT NOT TO EXCEED $12,000, SUBJECT TO
APPROVAL OF THE FEDERAL AVIATION
ADMINISTRATION.
I, James Thompson, City Clerk of the City of Palm. Springs, hereby certify that this
Minute Order approving Change Order No. to Agreement No. A4382 (Amendment No.
ll) with Gensler, adding structural design services for the Regional Jet Hold-room
project to the design contract for an amount not to exceed $12,000, subject to the
approval of the Federal Aviation Administration was adopted by the City Council of the
City of Palm Springs, California in a meeting tbereof held on the 7"'day of March, 2007.
James Thompson, City Clerk
CITY OF PALM SPRINGS
Expand Terminal/Expand Hold-room- Checkpoint Phase III (Part 2)
CHANGE ORDER
To: Gensler Date. March 7, 2007
2500 Broadway Suite 300 Project No. CP05-010
Santa Monica, Ca 90404 Project Name: Design Terminal Hold-room (Part 2)
Change Order No.03
AIP 38
Attn: Andy Cohen, FAIA Contract No.A4382(Amend No. 11)
Description of Change:
This Change Order is for Structural Engineering Extra Services related to the airport Hold-room project. Specifically
for continued Construction Administration Services,signage foundation and retaining wall foundation design work.
Summary of Cost/Time
Original Contract Price $ 828,795.08
Total of all Previous Change Orders $ 158,160.00
Total of this Change Order $ 12,000.00
Total Contract Price $ 998,955.08
This Change Order Wreases)�.�e� (unchanged) the contract time by 0 working days.
I have received a copy of this Change Order Construction Administrator
and the above AGREED PRICES are acceptable Approval: Date:
to the contractor.
By:
Aviation Department Approval:
Title:
Approved by. Date,
Date: Airport Construction Administrator
City Approval
Date:
City Clerk
Date:
City Manager
Distribution:
Original Conformed Copies Conformed- File Copy
City Clerk (1)
Contractor (1) Procurement& Contracting (1)
FAA (1) Finance (1)
Airport File (1)
Page 1 of I
February 12,2007 Arehirecrure, Design es Planning Worldwide Gensler
Mr.Allen Smoot
Palm Springs International Airport
3400 E.Tahquitz Canyon Way,Suite OFC
Palm Springs,California 92262-6966
SubjectTalm Springs International Airport Security Expansion,
Structural Engineering Extra Services Request
05.0201.022
Dear Allen:
Gensler is requesting Extra Services on behalf of Brandow Johnston for structural engineering
items related to the hold Room D project(Phase Il of Amendment 11)at Pahn Springs
International Airport.The request is divided into the following categories:
1) Continued Construction Administration Services. This is to allow Brandow Johnston to
provide continuing services during the construction administration phase.Included in this
service will be 2 site visits to observe the progress of construction(16 hours)and responses to
current and future requests for information(39 hours)-
2)Signage foundation.This is for the design of a structural footing to support the freestanding
signage that will be located between the Checkpoint and Hold Room A.
3).Detaining wall.Brandow Johnston will provide the structural design of the retaining wall to
be located between the Check Point and the Hold Room-The wall will be designed to retain a
maximum of 4 1/2'of earth.
Fee: This service will be billed on an hourly basis using the established hourly rates for this
contract.
Item Hrs Fee
1)Continued Construction Adnninistration services 55 S10,170
3 Sign footing design 6 $950
4 Retainin Wall design 3 S380
Total Labor Fee $11,500
Reimbursable Expenses $500
Total Fee and Reimbursable $12,000
Please gii c me a call if you have any questions-
Sincerely,
Keith Thompson
Principal SWI Broadway
airc 300
KAT/Sun Santa Monica CaliFOrnla 90404
M:\05,0201.022\Documcnmiion\I General\IC\LT070212 ES.dvc Tcl:;io.449. 5600
- - Fax:310-449. 5850