Loading...
HomeMy WebLinkAbout8/1/2001 - STAFF REPORTS (8) DATE: August 1, 2001 TO: City Council FROM: Director of Public Works/City Engineer CONSTRUCTION CHANGE ORDER NO. 1 TO E. L. YEAGER CONSTRUCTION COMPANY RECOMMENDATION: It is recommended that City Council approve Contract Change Order No. 1 to E. L. Yeager Construction Company, for an increase of $74,300.00, for a total contract amount of $300,075.00, for the Crossley Tract Street and Drainage Improvements, Phase 4, City Project No. 00-31. SUMMARY: Contract Change Order No. 1 will add installation of sewer laterals and sleeves for future gas service to each vacant lot located on Marguerite Street. BACKGROUND: On June 6, 2001, the City Council awarded E. L. Yeager Construction Company the contract for the Crossley Tract Street and Drainage Improvements, Phase 4, City Project 00-31. This project is the final phase of the Community Development Block Grant investments made to generally improve this low income neighborhood. Subsequent to award of this project, staff received numerous inquiries from potential home builders regarding the vacant lots within this neighborhood. Specifically, of the forty lots located on Marguerite Street,twenty-eight are vacant. Potentially, the completion of this project will stimulate development of the vacant lots. In that event, the newly constructed street would be trenched and excavated for sewer, water and gas service laterals for each vacant lot at the time of development. Staff has coordinated with Desert Water Agency and Southern California Gas Company to facilitate installation of service laterals prior to construction of the street improvements. In this way, all underground service laterals will be in place and no street cuts will be required as the vacant lots develop. This proposed change order covers the following items: Increase to Contract Items (New): Item A is proposed to be added to the contract to provide for the installation of four inch vitrified clay pipe (VCP) sewer laterals, and connections to the exist sewer main within Marguerite Street. Item B is proposed to be added to the contract to provide for compensation to the contractor for sheeting, shoring and bracing, or equivalent method, which is required by law for excavations exceeding four feet in depth. /A Construction Change Order No. 1 to E. L. Yeager Construction Company August 1, 2001 Page 2 Item C is proposed to be added to the contract to provide for the installation of one inch schedule 40 yellow polyethylene (PE) pipe for use as sleeves for future gas service laterals. Fifteen working days will be added to the contract to allow for the construction time required for the new contract items. As the sewer,water and gas service laterals are ultimately the responsibility of the owner(s) of the vacant lots, approval of this contract change order will temporarily subsidize those owners the cost for installing the laterals. However, staff intends to utilize the authority granted by Resolution 16031, adopted by the City Council on October 15, 1986, that allows the City to install off-site improvements that are the responsibility of a property owner in advance of developing their property, and to seek reimbursement from the property owner as a condition of development of the property at the time application for building permits is made. In this way, over time as the vacant lots develop the City will recover the costs associated with this change order. Sufficient funds are available in block grant account no. 137-4801-63503 (Street Improvements, Crossley Tract). Please note that all costs are being paid for by outside HUD block grant funds and no local general funds are required, and further, that these costs will be reimbursed as discussed above, and redistributed into the City's block grant account for future use by block grant projects. DAVID J. BARAKIAN City Engineer APPROVED: City Manager G ATTACHMENTS: 1. Minute Order REVIEWED BY DEPT.OF FINANCE _-PO #76 2 CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: E.L.Yeager Construction Company Date: July 20 2001 P.O.Box 87 Project No.: C.P. 00-31 Riverside CA 92502 Project Name: Crossley Tract Phase 4 Change Order No.: One (1)) Attn: Gary Baxter- Superintendent Contract Purchase No.: Account Number(s): 137-4801-63503 Agr.#4368 M.O. #6856 Res. # A. CHANGES IN WORK: Increase to Contract Bid Items (New): Item Description A Installation of four inch (4") vitrified clay pipe (VCP) sewer laterals to the center of each vacant lot (29 in total) in conformance with Greenbook Standard Specifications and the attached Special Provisions. B Provisions for sheeting, shoring, bracing or equivalent method, in conformance with the attached Special Provisions. C Installation of one inch (1") schedule 40 yellow polyethylene (PE) pipe at each property line, from right-of-way to right-of-way in conformance with Greenbook Standard Specifications and the attached Special Provisions. B. CHANGES IN CONTRACT COST: Increase to Contract Bid Items (New): Item Description A Install 4 in. VCP Sewer Lateral 900 LF @ $67.00 $ 60,300.00 B Sheeting, Shoring, Bracing or Equivalent Method Lump Sum $ 3,000.00 C Install 1 in. Schedule 40 Yellow PE Pipe 1,000 LF @ $11.00 $ 11,000.00 Sub-Total $ 74,300.00 TOTAL NET CHANGE ORDER = $ 74,300.00 NOTE: No additional markup will be added to any items in this Contract Change Order. C. REASON FOR CHANGE: Perthe recommendation of the Director of Public Works/City Engineer, install 29 sewer laterals and 1 in. Schedule 40 Yellow PE pipe sleeves for future gas services to the remaining vacant lots as part of this project. By installing these utility laterals now, it eliminates the need to cut into the new street at the time the vacant lots develop, thus avoiding numerous pavement trench cuts within a new street. 1,44 July 20, 2001 C.P. 00-31 Crossley Tract Phase 4 Change Order No. 1 Page 2 of 2 SOURCE OF FUNDS: Crossley Tract Phase 4 Account No.: 137 -4801 -63503 = $ 74,300.00 Summary of Costs Contract Time Original Contract Amount: $ 225,775.00 Original Completion Date: This Change Order: $ 74,300.00 Days Added for this C.C.O.: 15 Previous Change Order(s): $ 0.00 Previous Days Added: 0 Revised Contract Amount: $ 300,075.00 Revised Completion Date: I have received a copy of this Change Order and the City Approval: above AGREED PRICES are acceptable to the contractor. Submitted By Date Field Engineering Supervisor By Approved By Date Title Director of Public Works/City Engineer Approved By Date Date City Manager Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (1) IA 10-13 - SANITARY SEWER 10-13 .1 Materials . Vitrified clay pipe shall conform to Standard Specification 207-8 . Vitrified clay pipe joints shall conform to Standard Specification 208-2 . Cement mortar shall conform to Standard Specification 201-5 . 10-13 .2 Methods. Installation and testing of vitrified clay pipe shall conform to Standard Specification 306-1 . 2, 306-1 . 3 and 306-1 .4 and these Special Provisions . 10-13 .2 .1 Excavation, Backfill and Compaction. Prior to any excavation the Contractor shall pothole to determine the location and/or grades of connections or underground utilities, structures or fixtures in the alignment of the proposed sewer. Excavation for sewer pipe, laterals, fittings and appurtenances shall be in open trench to the line and grade as required to provide five feet (51 ) minimum cover at property line, with 2% minimum slope to the sewer main. The trench bottom shall be graded to provide a smooth, firm, moist and stable foundation. At each joint, the bottom of the trench shall be shaped in such a manner to relieve the bell of the pipe of all load. All rock shall be removed to a depth of six inches (611 ) below the bottom of the pipe . Embankment and over-excavated areas shall be filled to provide a trench bottom as previously described. Backfill of the trench about the pipe, laterals, fittings and appurtenances will be with select sand material free of debris, rock and similar hard, sharp objects to a distance of 12 inches minimum. The Engineer shall approve all backfill materials . Backfills shall be compacted to 90°s +/- 20 at optimum moisture content . Compaction under pavements, structures and fixtures shall conform to the specified density. Surplus materials shall be legally disposed of. All excavation, backfill, compaction, and material disposal costs shall be considered as included in the unit price of that item for sewer pipe, laterals, fittings or appurtenances . 10-13 .2 .2 Laterals. Installation of laterals shall conform to City of Palm Springs Standard Drawing 405 and these Special Provisions . The letter "S ' ' shall be etched or otherwise permanently marked within the concrete curb face directly above the lateral . 10-13 .3 Testing and Video. Testing, in accordance with the Standard Specifications, will be required after completion and acceptance of the roadway subgrade preparation. The sewer lines, manhole to manhole, shall be analyzed by videotape photography. Should the analysis indicate a change in the sewer line alignment or damage to the utility, the Contractor shall repair the affected area immediately, at no extra cost to the City. 7r4s' 10-13 .4 Measurement and Payment. Payment for vitrified clay pipe shall be made at the unit price per linear foot, and shall constitute full compensation for removal and disposal of all resulting materials, all labor, materials, equipment and incidentals, trenching, placement, backfill, complete in place, as required in the Standard Specifications and these special provisions . 10-13 .5 Sheeting, Shoring, and Bracing or Equivalent Method. Payment for temporary sheeting, shoring, bracing or equivalent method will be based upon completion of all planning, design, engineering, furnishing, and construction, and the removal and disposal of all such temporary sheeting, shoring, and bracing at the lump sum price, complete, as required under the provisions of any permits, and in accordance with the requirements of OSHA and the Construction Safety Orders of the State of California, pursuant to the provisions of Section 6707 of the California Labor Code. 10-13 . 6 Protection of Existing Improvements. Should there be any existing improvements that were known to the Contractor prior to excavation, the Contractor shall restore or replace the existing improvements to their original or better condition, at the Contractor' s own expense. 10-14 - UTILITY LINE SLEEVES 10-14 .1 Materials . Polyethylene (PE) pipe shall conform to Standard Specification 207-19 . All polyethylene (PE) pipe used for utility line (natural gas) sleeves shall be rolled, one inch (1 " ) nominal diameter, schedule 40 yellow color pipe. 10-14 .2 Methods. Installation of polyethylene (PE) pipe shall conform to Standard Specification 306-1 .2 and 306-1 .3 and these Special Provisions . Prior to any excavation the Contractor shall pothole to determine the location and/or grades of connections or underground utilities, structures or fixtures in the alignment of the proposed sewer. Excavation for utility line (natural gas) sleeves shall be provided such that a minimum 2411 cover from gutter flowline, or 30 " minimum cover, whichever is greater, is achieved. A minimum 6 " separation between utility line sleeves and other utilities shall be maintained. The trench bottom shall be graded to provide a smooth, firm, moist and stable foundation. All rock shall be removed to a depth of six inches (611 ) below the bottom of the utility sleeve . Backfill of the trench about the pipe, laterals, fittings and appurtenances will be with select sand material free of debris, rock and similar hard, sharp objects to a distance of 12 inches minimum. The Engineer shall approve all backfill materials . 7 Backfills shall be compacted to 90% +/- 2% at optimum moisture content . Compaction under pavements, structures and fixtures shall conform to the specified density. The letter "G" shall be etched or otherwise permanently marked within the concrete curb face directly above the utility sleeve . 10-14 .3 Measurement and Payment. Payment for polyethylene (PE) pipe shall be made at the unit price per linear foot, and shall constitute full compensation for removal and disposal of all resulting materials, all labor, materials, equipment and incidentals, trenching, placement, backfill, complete in place, as required in the Standard Specifications and these special provisions . 7A7 MINUTE ORDER NO. 6898 APPROVING CONTRACT CHANGE ORDER NO. 1 TO E.L. YEAGER CONSTRUCTION COMPANY FOR AN INCREASE OF $74,300, FOR A TOTAL CONTRACT AMOUNT OF $300,075, FOR THE CROSSLEY TRACT STREET AND DRAINAGE IMPROVEMENTS, PHASE 4, CITY PROJECT NO. 00-31. ------------------ I HEREBY CERTIFY that this Minute Order, approving Contract Change Order No. 1 to E.L. Yeager Construction Company for an increase of $74,300, for a total contract amount of $300,075, for the Crossley Tract street and drainage improvements, Phase 4, City Project No. 00-31, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 1st day of August, 2001. PATRICIA A. SANDERS City Clerk