HomeMy WebLinkAbout5/16/2001 - STAFF REPORTS (13) DATE: May 16, 2001
TO: City Council
FROM: City Engineer
CONSTRUCTION CHANGE ORDER NO. 3 TO E.L.YEAGER CONSTRUCTION
RECOMMENDATION:
That the City Council approve Construction Change Order No. 3 to
E.L.Yeager Construction, for an increase of $85,212.00 for the East Palm
Canyon / Gene Autry Trail Widening, for a total contract amount of $1,292,254.83
City Project No. 92-36.
SUMMARY:
Install additional irrigation, landscape and hydro-seed areas, remove additional
roadway excavation and compensate for traffic control delays.
BACKGROUND:
On May 17, 2000, City Council awarded E.L.Yeager Construction the contract for
the East Palm Canyon / Gene Autry Trail Widening project.
This proposed change order covers the following items:
Increase to Contract Items (New):
Item I is proposed to be added at the recommendation of Park Maintenance
Supervisor. Approximately 700 ft. west of Gene Autry Trail, north side of East
Palm Canyon, the parkway area required regrading in order to adequately
maintain it. This required additional irrigation and hydro seeding .
Item J is proposed to be added at the recommendation of the Landscape
Architect. During the construction of the storm drain pipe Lines A and B, outlet
structure and the re-aligning of the curb return at N.E. corner of Broadmoor and
East Palm Canyon, all existing irrigation and landscape were destroyed. There
were no provisions for any irrigation and landscape to be reconstructed.
Reconstruction of all irrigation and landscape is required in this area in order for
this not to have a "bare spot" at this corner, in relation to the existing area. A
partial credit is given under Item 34 for maintenance repair.
Item K is proposed to be added at the recommendation of Park Maintenance
Supervisor. The existing irrigation water main from 723 ft. west to 203 ft. west of
Gene Autry Trail is now under the new street section. For maintenance purposes,
it is proposed to re-install a new irrigation water main in the re-aligned landscape
area behind the new curb.
Item L was added due to changes in the street section required by the State of
California for their portion of East Palm Canyon. The street section changed from
4 in. AC over 8 in. Class II Base to 6 in. AC over 8 in. Class II Base. This change
was mandated by Caltrans. All work was done under force account at Caltrans'
direction.
Item M is proposed to be added due to delays as a result of the following:
City special event for Veterans Day Parade. Staff instructed the contractor not to
install storm drain across Gene Autry Trail at East Palm Canyon until after the
parade. (7 days)
/M
City Project 92-36, East Palm Canyon / Gene Autry Trail
May 16, 2001
Page 2 of 2
Caltrans reviewed process to approved traffic control plan submitted by the
contractor. (6 days)
Construction staking for the 24 in. RCP storm drain pipe. (6 days)
Storm drain design change from 18 in. RCP to 2 ea, 12 in. RCP, due to conflict
with existing SCE conduit at Gene Autry Trail and East Palm Canyon. Design
change was reviewed by both the City and Caltrans and was constructed. (11
days)
Street section change on Caltrans's portion of East Palm Canyon from 4 in. AC
over 8 in. Cl II Base to 6 in. AC over 8 in. Cl II Base, including grading out
additional 2 inches of dirt and compaction. (12 days)
Re-design of signal pole base at SE corner of East Palm Canyon and Gene Autry
Trail, including the construction of the re-design and review and approval process
by both the City and Caltrans. (19 days)
Construction scheduling conflicts with the contractor's prior construction schedule
commitments. (17 days)
The total delay days are 78.
Because of these delays, the contractor was required to have the traffic control
system in place. Traffic control system included K-rail rental, arrow boards, crash
cushions, signs and additional materials related to road closures, in compliance
with Caltrans standards. Original completion date was Nov. 8, 2000. All traffic
control devices were removed by the contractor on Jan. 23, 2001. Total days
between Nov. 8 through Jan. 23 is 76. Cost for traffic control for Items I through K
will be provided by the contractor and is included in this cost.
Decrease to Contract Item:
Item 34 is a lump sum bid. On Plan Sheet No. P-4, Plant Legend, the contractor
shall provide $1,500.00 to be used for plant material not listed on the legend. The
City deleted this portion of the work and will receive credit from the contractor.
Additional working days (61) will be added per the following:
10 days for Items I through K.
2 days for Item L
49 days for coordinating and scheduling the above work
Funds are available in Measure A local share account number 4498-50174 (E.
Palm Canyon / Gene Autry Trail Widening) and Measure A Regional share
account number 4497-50174 (E. Palm Canyon / Gene Autry Trail Widening)
jWL-1
DAVID J. BARAKIAN
City Engineer
APPROVED:
City Manager
Attachment: Minute Order REVIEWED BY DEPT.OF FINANCE
Change Order No. 3
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: E.L.Yeager Construction Company Date: May 4, 2001
P.O.Box 87 Project No.: C.P. 92-36
Riverside CA 92502 Project Name: East Pam Canyon /Gene
Autry Trail Widening
Change Order No.: Three (3)
Attn: Gary Baxter-Superintendent Contract Purchase No.: 909476
Account Number(s): 4497-50174,
4498-50174
Agr.#4223 M.O.#6618 Res.#
A. CHANGES IN WORK:
Increase to Contract Items(New):
Item Description
I Install Irrigation and Hydroseed west of Gene Autry Trail on East Palm Canyon
J Install Irrigation and Hydroseed east of Broadmoor on East Palm Canyon
K Install new irrigation waterline west of Gene Autry on East Palm Canyon
L Remove additional roadway excavation due to changes in the street section
M Traffic control delays
Decrease to Contract Item:
Item Description
34 Landscape and irrigation
B. CHANGES IN CONTRACT COST:
Increase to Contract Items(New):
Item Description
I Install Irrigation and Hydroseed west of Gene Autry Force Account $ 6,431.64
on East Palm Canyon Estimate
J Install Irrigation and Hydroseed east of Broadmoor on Force Account $ 8,236.98
East Palm Canyon Estimate
K Install new irrigation waterline west of Gene Autry on Force Account $ 3,867.27
East Palm Canyon Estimate
L Remove additional roadway excavation due to changes Force Account $ 22,176.11
in the street section Estimate
M Traffic control delays Agreed Price $ 46,000.00
Sub-Total $ 86,712.00
Decrease to Contract Item:
Item Description
34 Landscape and irrigation Agreed Price ($ 1,500.00)
TOTAL NET CHANGE ORDER = $ 85,212.00
NOTE: No additional markup will be added to any items in this Contract Change Order.
) 143
May 4,2001
C.P. 92-36 East Palm Canyon/Gene Autry Trail Widening
Change Order No.Three(3)
Page 2 of 3
C. REASON FOR CHANGE:
Increase to Contract Items(New):
Item I will be added per the recommendation of Park Maintenance Supervisor. Approximately 700 ft. west of
Gene Autry Trail,north side of East Palm Canyon,there were no provisions for irrigation or hydroseed.
Item J will be added per the recommendation of the Landscape Architect. During the construction of the storm
drain pipe Lines A and B, outlet headwall structure and the re-aligning of the curb return at N.E. corner of
Broadmoor and East Palm Canyon, all the existing irrigation and landscape was destroyed. There were no
provisions for any irrigation and landscape to be reconstructed. Reconstruct all irrigation and landscape in this
area. If not reconstructed, there will be a "bare spot" at this corner, in relation to the existing area. A partial
credit is given under Item 34 for landscape maintenance.
Item K will be added per the recommendation of Park Maintenance Supervisor. The existing irrigation water
main from 723 ft.west to 203 ft.west of Gene Autry Trail is now under the new street section. For maintenance
purposes, re-install a new irrigation water main in the re-aligned landscape area behind the new curb.
Item L was added due to changes in the street section for the State of California portion of East Palm Canyon.
The street section changed from 4 in. AC over 8 in. Class II Base to 6 in. AC over 8 in. Class II Base. This
change was mandated by Caltrans.All work was done under force account.
Item M will be added due to delays as a result of the following:
City special event for Veterans Day Parade. Instructed the contractor not to install storm drain across Gene
Autry Trail at East Palm Canyon until after the parade. (7 days)
Caltrans review process to approved traffic control plan submitted by the contractor. (6 days)
Construction staking for the 24 in. RCP storm drain pipe. (6 days)
Storm drain design change from 18 in. RCP to 2 ea, 12 in. RCP, due to conflict with existing SCE conduit at
Gene Autry Trail and East Palm Canyon. Design change was reviewed by both the City and Caltrans and was
constructed. (11 days)
Street section change on Caltrans's portion of East Palm Canyon from 4 in. AC over 8 in. Cl II Base to 6 in.AC
over 8 in. CI II Base, including grading out additional 2 inches of dirt and compaction. (12 days)
Re-design of signal pole base at SE corner of East Palm Canyon and Gene Autry Trail, including the
construction of the re-design and review and approval process by both the City and Caltrans. (19 days)
Construction scheduling conflicts with the contractor's prior construction schedule commitments. (17 days)
The total delay days are 78.
Because of these delays, the contractor was required to have the traffic control system in place. Traffic control
system included K-rail rental, arrow boards, crash cushions, signs and additional materials related to road
closures, in compliance with Caltrans standards. Original completion date was Nov. 8, 2000. All traffic control
devices were removed by the contractor on Jan. 23, 2001. Total days between Nov. 8 through Jan. 23 is 76.
Cost for traffic control for Items I through K will be provided by the contractor and is included in this cost
Decrease to Contract Item:
Item 34 is a lump sum bid. On Plan Sheet No. P-4, Plant Legend, the contractor shall provide $1,500.00 to be
used for plant material not listed on the legend. The City deleted this portion of the work and will receive credit
from the contractor.
Additional working days(61)will be added per the following:
10 days for Items I through K.
2 days for Item L
49 days for coordinating and scheduling the above work
i1� A y
May 4,2001
C.P. 92-36 East Palm Canyon/Gene Autry Trail Widening
Change Order No.Three (3)
Page 3 of 3
SOURCE OF FUNDS:
Gene Autry Trail/East Palm Canyon Widening Account No.: 4497 - 50174 = $ 63,056.88
Account No.: 4498 - 50174 = $ 22,155.12
Summary of Costs Contract Time
Original Contract Amount: $ 1,198,952.00 Original Completion Date: Nov. 8,2000
This Change Order: $ 85,212.00 Days Added for this C.C.O.: 61
Previous Change Order(s): $ 8,090.83 Previous Days Added: 76
Revised Contract Amount: $ 1,292,254.83 Revised Completion Date: June 8, 2001
1 have received a copy of this Change Order and the City Approval:
above AGREED PRICES are acceptable to the
contractor. Submitted By Date
Field Engineering Supervisor
By Approved Bye Date
City Engineer
Title
Approved by Date
Date City Manager
Distribution:
Original Conformed Copies Conformed-File Copy
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
114s,
mil
MINUTE ORDER NO. 6850
APPROVING CONSTRUCTION
CHANGE ORDER NO. 3 TO E.L.
YEAGER CONSTRUCTION, FOR AN
INCREASE OF $85,212 FOR THE
EAST PALM CANYON/GENE AUTRY
TRAIL WIDENING, FOR A TOTAL
CONTRACT AMOUNT OF
$1,292,254.83, CITY PROJECT NO.
92-36.
------------------
I HEREBY CERTIFY that this Minute Order, approving Construction Change
Order No. 3 to E.L. Yeager Construction, for an increase of$85,212, for the East
Palm Canyon/Gene Autry Trail Widening, for a total contract amount of
$1,292,254.83, City Project No. 92-36, was adopted by the City Council of the
City of Palm Springs, California, in a meeting thereof held on the 16th day of
May, 2001.