HomeMy WebLinkAbout5/2/2001 - STAFF REPORTS (7) DATE: May 2, 2001 TO: City Council FROM: City Engineer APPROVE CONSTRUCTION CHANGE ORDER NO. 2 TOAMERICAN ASPHALT REPAIR & RESURFACING CO., INC. RECOMMENDATION: That the City Council approve Construction Change Order No.2 to American Asphalt Repair & Resurfacing Co., Inc., for a decrease of $11,488.48 for the 2000/01 Annual Slurry Seal Program, City Project No. 00-27. SUMMARY In Schedules A and B, total quantities were less than contract amount and in Alternate Schedule C, total quantity was more than contract amount. In combining all schedules, contract amount results in a decrease to the contract. BACKGROUND: On February 7, 2001, City Council of the City of Palm Springs awarded American Asphalt Repair & Resurfacing Co., Inc. the contract for the 2000 / 2001 Annual Slurry Seal Program Project. All slurry seal quantities were measured by both the City and the Contractor. Total Final As-Built quantities were less than contract amounts.The following summary for each schedule shows the increase and decrease amounts: Schedule A - ($ 1,142.79), Decrease Schedule B - ($ 13,432.72), Decrease Alternate Schedule C - $ 3,087.02, Increase The City deleted the following streets because of upcoming Desert Water Agency water main projects: Schedule A - Farrell Drive from Tamarisk Road to Alejo Road Schedule B-Baristo Road from Sunrise Way to Compadre Road, Compadre Road from Ramon Road to Baristo Road Funds will be unencumbered in account number no.134 - 4498 - 50100 (2000/01 Annual Slurry Seal) -Aff5L DAVID J. BARAKIAN City Engineer APPROVED: �, City Manager ATTACHMENTS: 1. Minute Order 2. Change Order No. 2 REVIEWED BY DEPT.OF FINANCE --1 1#4 CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: American Asphalt Repair&Resurfacing Co Inc Date: April 13, 2001 14436 Santa Ana Ave. Project No.: C.P. 00-27 Fontana, CA 92337 Project Name: 2000/2001 Annual Slurry Seal Program Change Order No.: Two (2) Attn: Dan Bohnett-Superintendent Contract Purchase No.: 116418 Account Number(s): 134-4498-50100 Agr.#4338 M.O.#6789 Res.# A. CHANGES IN WORK: Increase to Contract Items Alternate Schedule C: Item Description No. 1 Construction of Rubberized Emulsion-Aggregate Slurry Seal, REAS (or Flex Seal), including mobilization, traffic control, remove and replacement of RPMs, pavement markings and all appurtenant work on Tahquitz Canyon from El Cielo Road to Indian Canyon Decrease to Contract Items Schedule A: Item Description No. 1 Construction of Type II Slurry Seal, including Mobilization, Traffic Control, Removal & Replacement of Reflectorized RPMs & Pavement Markings & all appurtenant Work on various streets within Section 12 Schedule B: Item Description No. 1 Construction of Type II Slurry Seal, including Mobilization, Traffic Control, Removal&Replacement of Reflectorized RPMs & Pavement Markings & all appurtenant Work on various streets within Section 13 B. CHANGES IN CONTRACT COST: Increase to Contract Item Schedule C Item Description No. 1 Construction of Rubberized Emulsion-Aggregate Slurry 20,929 @$0.1475 $ 3,087.02 Seal, REAS(or Flex Seal), including mobilization,traffic control, remove and replacement of RPMs, pavement markings and all appurtenant work on Tahquitz Canyon from El Cielo Road to Indian Canyon April 13, 2001 C.P. 00-27 2000/2001 Annual Slurry Seal Program Change Order No.Two (2) Page 2 of 3 Continued, B. CHANGES IN CONTRACT COST: Decrease to Contract Item-Schedule A Item Description No. 1 Construction of Type II Slurry Seal, including 16,443 SF @$0.0695 ($ 1,142.79) Mobilization,Traffic Control, Removal & Replacement of Reflectorized RPMs& Pavement Markings&all appurtenant Work on various streets within Section 12 Decrease to Contract Item-Schedule B: Item Description No. 1 Construction of Type II Slurry Seal, including 193,555 SF @$0.0694 ($ 13,432.72) Mobilization,Traffic Control, Removal& Replacement of Reflectorized RPMs&Pavement Markings&all appurtenant Work on various streets within Section 13 TOTAL DECREASE CHANGE ORDER = < $ 11,488.48 > NOTE: No additional markup will be added to any items in this Contract Change Order. All cost per each item are final. C. REASON FOR CHANGE: In Alternate Schedule C, quantity was field measured by both the Contractor and the City. Quantity exceeded contract estimate. In Schedule A, quantity was field measured by both the Contractor and the City. Quantity was under contract estimate. Also,the City deleted Farrell Drive from Alejo Road to Tamarisk Road due to upcoming Desert Water Agency water main project. In Schedule B, quantity was field measured by both the Contractor and the City. Quantity was under contract estimate. Also, the City deleted the following streets due to upcoming Desert Water Agency water main projects: Baristo Road from Sunrise Way to Farrell Drive Baristo Road from Farrell Drive to Compadre Road Compadre Road from Ramon Road to Baristo Road D.SOURCE OF FUNDS: 2000/2001 Annual Slurry Seal Account Number: 134-4498 - 50100 = < $ 11,488.48 > Summary of Costs Contract Time Original Contract Amount: $ 382,219.74 Original Completion Date: April 24, 2001 This Change Order: ($ 11,488.48) Days Added for this C.C.O.: 0 Previous Change Order(s): ($ 3,921.72) Previous Days Added: 0 Revised Contract Amount: $ 366,809.54 Revised Completion Date: April 24,2001 ?A 3 April 13,2001 C.P. 00-27 2000/2001 Annual Slurry Seal Program Change Order No. Two (2) Page 3 of 3 Continued, have received a copy of this Change Order and the City Approval: above AGREED PRICES are acceptable to the contractor. Submitted By Date Field Engineering Supervisor By Approved By � Date City Engineer Title Approved by Date Date City Manager Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (1) �Ay MINUTE ORDER NO. 6841 APPROVING CONSTRUCTION CHANGE ORDER NO. 2 TO AMERICAN ASPHALT REPAIR & RESURFACING CO., INC., FOR A DECREASE OF $11,488.48 FOR THE 2000/01 ANNUAL SLURRY SEAL PROGRAM, CITY PROJECT NO. 00-27. ------------------ I HEREBY CERTIFY that this Minute Order, approving Construction Change Order No. 2 to American Asphalt Repair & Resurfacing Co., Inc., for a decrease of $11,488.48 for the 2000/01 Annual Slurry Seal Program, City Project No. 00- 27, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 2nd day of May, 2001. PATRICIA A. SANDERS City Clerk