HomeMy WebLinkAbout10/4/2006 - STAFF REPORTS - 2.K.City Council Staff Report OCTOBER 4, 2006 CONSENT CALENDAR Subject: AMENDMENT NO. 2 TO THE INDIAN AVENUE/1-10 INTERCHANGE CONTRACT SERVICES AGREEMENT, CP#00-14 From: City Manager Initiated By: Director of Public Works/City Engineer SUMMARY Approval of this amendment revises the total contract amount for professional environmental and design services to $1,334,562, an increase of $340,720 for new engineering tasks and a prolonged project schedule in the project approval (PA/ED) Phase of the Indian Avenue/1-10 Interchange_ RECOMMENDATION: 1) Approve Minute Order No. "APPROVING AMENDMENT NO. 2 TO AGREEMENT NO. 4318 WITH DOKKEN ENGINEERING IN AN AMOUNT OF $340,720 FOR A REVISED TOTAL CONTRACT AMOUNT OF $1,334,562, FOR NEW ENGINEERING TASKS AND A PROLONGED PROJECT SCHEDULE IN THE PROJECT APPROVAL (PANED) PHASE OF THE INDIAN AVENUE/1-10 INTERCHANGE PROJECT, CP#00-14.° 2) Authorize the City Manager to execute all necessary documents. STAFF ANALYSIS: On December 6, 2000 City Council approved Contract Services Agreement Number 4318 with Dokken Engineering for engineering design and environmental services for the Indian Avenue/1-10 Interchange Project, City Project Number 00-14 in the amount of $943,842. On May 21, 2003, City Council approved Amendment #1 to the agreement for $50,000 in additional environmental and design services due to unforseen environmental issues and additional alternative design requirements from Caltrans and the Federal Highway Administration. Since that time, the Consultant has been required to make changes due to continuously revised requirements of Caltrans, which has resulted in the PANED Phase of the project being extended from the anticipated 1-2 years to more than 5 years_ ITEM NO. • �° City Council Staff Report October 4, 2006 - Page 2 Dokken Engineerinq A#2, CP#00-14 The impact of the budget was primarily due to the following: A. Delay in the environmental approval schedule: The primary reason for delay, indeed the reason for delay in the schedules of all the Indian/1-10 projects has been the ongoing negotiations between Caltrans, FHWA, CVAG and the Resource Agencies over the endangered species impacts on the freeway interchange projects. B. New project approval requirements: The introduction by Caltrans of several new requirements for project approval overthe course of the extended project schedule- C. Changing design standards: The changing of design standards over the course of the extended project schedule has adversely impacted the budget. D. Frequent turnover of Caltrans over -site staff and conflicting direction during the environmental process has resulted in the introduction of additional project coordination and management costs, including team meetings. The Consultant, Dokken Engineering has been providing excellent service to the City through this process; however, staff feels it is not reasonable to expect these continuous delays and changes to be forced upon Dokken without compensation. City and CVAG staff agree that additional compensation is due to Dokken for this work. AlthoughDokken's initial submittal request was for $787,000, staff negotiations have resulted in the agreed upon total increase of $340,720. The reduction was primarily due to the fact that although additional time was spent by Dokken as a result of project changes and revisions, some of those revisions were included in the language of the original contract and therefore staff could not recommend additional fees for that work_ This request has received the approval of the CVAG TAC on September 8, 2006; the Transportation Committee on September 11, 2006; and the Executive Committee o September 25, 2006. 1 FISCAL IMPACT: I Finance Director Review: An offsetting budget adjustment will increase the Indian/1-10 Interchange Project account 134-4497-50185 to cover this amendment. There is no cost to the City's general fund. �- David J. Barakian Thomas J. WAson Directorof Public Works/City Engineer Assistant City Manager -Development Services David H. Ready City Manager Attachments: 1. Minute Order 2. Amendment #2 MINUTE ORDER NO. APPROVING AMENDMENT NO. 2 TO AGREEMENT NO. 4318 WITH DOKKEN ENGINEERING IN AN AMOUNT OF $340,720 FORA REVISED TOTAL CONTRACT AMOUNT OF $1,334,562, FOR NEW ENGINEERING TASKS AND A PROLONGED PROJECT SCHEDULE IN THE PROJECT APPROVAL (PA/ED) PHASE OF THE INDIAN AVENUEl1-10 INTERCHANGE PROJECT, CP#00-14 I, James Thompson, City Clerk of the City of Palm Springs, California, hereby certify that this Minute Order Approving Amendment No. 2 to Agreement No. 4318 with Dokken Engineering in an Amount of $340,720 for a revised total contract amount of $1,334,562, for new engineering tasks and a prolonged project schedule in the Project Approval (PA/ED) Phase of the Indian Avenue/i-10 Interchange Project, Cp#00-14, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 41h day of October, 2006. James Thompson, City Clerk AMENDMENT NO. 2 TO CONTRACT SERVICES AGREEMENT NO. 4318 WITH DOKKEN ENGINEERING INDIAN AVENUE/1-10 INTERCHANGE, CP#00-14 The following articles of Agreement No. 4318 are hereby amended to read as follows: SCHEDULE OF COMPENSATION (Exhibit °C") - Shall be amended as follows: New Total Increase Task 1.0, Subtask Total Lump Sum shall be increased to $ 126,705 $ 80,100 Task 2.2, Subtask Total Lump Sum shall be increased to $ 66,333 $ 52,190 Task 2.4, Subtask Total Lump Sum shall be increased to $ 26,819 $ 13,820 Task 2.6, Subtask Total Lump Sum shall be increased to $ 41,026 $ 13,620 Task 2.7, Subtask Total Lump Sum shall be increased to $ 171,334 $ 63,290 Task 2.9, Subtask Total Lump Sum shall be increased to $ 68,465 $ 14,260 Task 2.10, Subtask Total Lump Sum shall be increased to $ 61,846 $ 12,350 Task 2.11, Subtask Total Lump Sum shall be increased to $ 29,834 $ 10,010 Task 3.5, Subtask Total Lump Sum shall be increased to $ 18,440 $ 11,240 Task 4.1, Subtask Total Lump Sum shall be increased to $ 170,010 $ 13,400 Task 4.2, Subtask Total Lump Sum shall be increased to $ 91,050 $ 18,050 Task 4.3, Subtask Total Lump Sum shall be increased to $ 100,060 $ 14,060 Task 4.4, Subtask Total Lump Sum shall be increased to $ 38,650 $ 13,150 Task 4,5, Subtask Total Lump Sum shall be increased to $ 34,980 1$ 1.180 $340,720 Total For Project shall be increased to $1,334,562 Except as specifically amended by this Amendment#2, all terms and provisions of Agreement #4318 shall remain in full force and effect. Purchase Order Number(s): Agreement Number: Original City Council Approval: Original Minute Order Number: Original Contract Amount. - Amount of Previous Increase(s) Amount of This Increase Amended Total: Account Number(s): 116346 4318 December 6, 2000 6761 $ 943,842 $ 50,000 $ 340,720 $1,334,562 134- 497-50185 SIGNATURES ON NEXT PAGE Dokken Engineering, CP#00-14 Amendment No. 2 Page 2 ,ATTEST: By: City Clerk CONTRACTOR: DOKKEN ENGINEERING CITY OF PALM SPRINGS, a municipal corporation M City Manager Mailing Address: 9665 Chesepeake Drive, Suite 435, San Diego, CA 92123 CONTRACTOR: Check one: _Individual _Partnership _Corporation Sy. Signature (notarized) Name: Title: (This Agreement must be signed in the above space by one of The Iollowing: Chairman of the Board, President or any Vice President) State of County of On I Iss hefam me, 0 Signature (notarized) Name: Title: This Agreement must be signed in the above space by ono of the following: Secretary, Chief Financial Officer or any Assistant Treasurer) State of County of Iss On betble me, personally appeared personally appeared personally (mown to me (or proved to me on the basis of satisfactory personally known to me (or proved to me on the basis of satisfactory evidence) to be the person(s) whose name(s) is/arc suhscrihcd to the evidence) to be the pcmon(s) whose name(s) Ware subscribed to the Within instrument and acknowledged to me that he/she/they cxccuQcd within instrument and acknowledged to me that he/slit/tttcy executed the same in 1tis/her/their authorized capacity(ius), and that by the same in his/her/their authorized capacity(ics), and that by his/her/their signamre(s) on the instrument the pehxon(s), or the entity his/her/their siymature(s) on the instrument the persan(s), or the entity upon behalf of which the person(s) acted, executed the instrument. upon behalf of which the persan(s) acted executed the instrument. WITNESS my hand and official seal. WITNESS my hand and official seal Notary Signature: Notary Signature: Notary Seal: Notary Seal: