Loading...
HomeMy WebLinkAbout2/21/2001 - STAFF REPORTS (5) Date: February 21, 2001 TO City Council FROM: David J. Barakian, City Engineer APPROVE CONSTRUCTION CHANGE ORDER NO. 2 TO ENVIRONMENTAL CONTROL SYSTEMS RECOMMENDATION: That the City Council approve Construction Change Order No.2 to Environmental Control Systems, decreasing their contract by $18,800 for the deletion of Bid Schedule C, (Desert Moon) to the Asbestos Abatement and Demolition project, City Project No. 98-05. SUMMARY: The Desert Moon building located at 2150 N. Palm Canyon Drive was to be demolished as part of City Project# 98-05 Asbestos Abatement and Demolition (various locations). At the time of this project, the City could not obtain the Court's approval to demolish this building as planned. The Bid Item for this work is being deleted from the contract with Environmental Control Systems. BACKGROUND: City Project# 98-05 Asbestos Abatement and Demolition (various locations), was awarded to Environmental Control Systems and began in September of 1999. Initially, there were a total of 5 locations that were to be demolished, one of which was the Desert Moon located at 2150 N. Palm Canyon Drive. Although the City had received an order from the Court allowing for the demolition, the owner successfully appealed to the Court to stop the demolition. Eventually, Environmental Control Systems completed the demolition of all remaining locations and one additional location that was added per Change Order#1. At the completion of the project on April 10, 2000, Environmental Control Systems was asked if they would be interested in keeping the contract open while the City pursued the Court's permission to demolish the building. The Contractor agreed and the contract was held open. The City was unable to obtain permission to demolish this location and in September of 2000 Environmental Control Systems requested that the contract be closed. The appeal was heard in December 2000 and, according to Rutan &Tucker, it is not known when a decision on the appeal will be issued. This deletion is being made as a balancing change order to the project. Funds will be returned to account number 4151-43260 (Asbestos Abatement). A4, APPRO EV D:, eifi DAVID J. BARAKIAN City Manager r� City Engineer ATTACHMENT: 1. Minute Order 2. Construction Change Order No.2 CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: Environmental Control Systems Inc. Date: January 29, 2001 29160 Goetz Road f Project No. 98-05 Quail Valley, CA 92587 Project Name: Asbestos Abatement and Demolition Change Order No. Two (2) Attn: Ronald NfcDaniel Contract Purchase No. 906612 Account Number:4151-43260 Agr.# 4111 M.O.# 6424 Res. # A_CUANGES IN WORK: DECREASE,10 CONTRACT QUANTITIES A. Deletion of Bid Schedule C Lump Sum B. CHANGES IN COST: DECREASE TO CONTRACT QUANTITIES A. Deletion of Bid Schedule C Lump Sum = $18,800.00 TOTAL NET CHANGE ORDER CREDIT AMOUNT ($18,800.00) C. REASONS FOR CHANGES: The City could not obtain Court approval to demolish the Desert Moon (located at 2150 N. Palm Canyon), at the time of this project. Therefore, this bid item was removed from the contract. The originally estimated completion date for this project was January 11, 2000. Due to delays caused by legal issues surrounding the Desert Moon, and the addition of 3709 El Dorado per change order #1, project time was deferred. The actual completion date for the project (less 'the Desert Moon), was April 10, 2000. Environmental Control Systems had 11 working days remaining at the completion of the original contract work (less Desert Moon). 71 working days will be added to this change order which will reflect the contract time deferred per change order#1 and prov.Je the 11 working days that ECS had on the books prior to deferment of time. " Note: No additional mark ups will be added to any item on this Change Order. All cost per each item are final. D. SOURCE OF FUNDS: Funds shall be returned to the following account: 4151-43260 (Asbestos Abatement and Demolition) Item B 6-42 Summary of Costs Contract Time Original Contract Amount: $106,000.00 Original Completion Date: Dec 9, 1999 This Change Order: $ (18,800.00) Days Added for this C.C.O.: -71- Previous Change Order(s): $ 19,200.00 Previous Days Added: -20- Revised Contract Amount: $106,400.00 Revised Completion Date: April 25, 2000 1 have received a copy of this Change City Approval: Order and the above AGREED PRICES are acceptable to the contractor. Submitted by Date Field Engineering Supervisor By Approved By— Date City Engineer Date Approved By Date City Manager _ Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor City Clerk (1) Purchasing Agent 1 MINUTE ORDER NO. 6802 APPROVING CONSTRUCTION CHANGE ORDER NO. 2 TO ENVIRONMENTAL CONTROL SYSTEMS, DECREASING THEIR CONTRACT BY $18,800 FOR THE DELETION OF BID SCHEDULE C (DESERT MOON) TO THE ASBESTOS ABATEMENT AND DEMOLITION PROJECT, CITY PROJECT NO. 98-05. ------------------ I HEREBY CERTIFY that this Minute Order, approving Construction Change Order No. 2 to Environmental Control Systems, decreasing their contract by $18,000 for the deletion of Bid Schedule C (Desert Moon) to the Asbestos Abatement and Demolition Project, City Project No. 98-05, was adopted by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 21 s`day of February, 2001. PATRICIA A. SANDERS City Clerk