HomeMy WebLinkAbout2/7/2001 - STAFF REPORTS (2) 9
DATE: February 7, 2001
TO: City Council
FROM: Assistant Director of Aviation via Acting Director of Aviation
AIRPORT ENGINEERING SERVICES CONTRACT SERVICES AGREEMENT
NO. 3138 -AMENDMENT NO. 10
RECOMMENDATION:
It is recommended that the City Council approve Amendment No. 10 for Airport
Engineering Services under Contract Services Agreement No. 3138 with Washington
Infrastructure Services, Inc. (formally Raytheon Engineers & Constructors / Isbill
Associates, Inc.) for a final contract closeout payment in an amount not-to-exceed
$219,810.00.
SUMMARY:
Amendment No. 10 to Agreement No. 3138 for additional airport engineering services
is necessary for the final closeout payment for (3) three FAA Airport Improvement
Program (AIP) grant projects, 90% funded by the FAA with 10% Airport match, with
Washington Infrastructure Services, Inc. for an amount not to exceed $219,810.00
BACKGROUND:
Airport Engineering Services with Washington Infrastructure Services, Inc. (originally
Isbill Associates, Inc.) have been provided under agreement No. 3138 as approved by
the City Council per Minute Order No. 5065, since September 2, 1992.
Several FAAAIP Grant projects have had ongoing engineering services required since
their inception. With increased federal requirements related to the Runway Extension
and Improved SafetyArea construction, plus other project specific changes, increased
engineering costs were incurred during the contract term for three (3) AIP Grant
Projects.
The regulatory requirements from the FAA, primarily during the main runway extension
projects, forced several re-designs of the runway ends. They included additional
Porous Friction Coating for 1500' of the north end of the runway and relocation of the
displaced threshold on the south end of the runway in order to accommodate a 1000'
stopway, which is the overrun area needed for an aircraft when they might need to
abort a takeoff.
The original estimate related to Amendment No. 10 was for $253,000. Airport staff
met with representatives from Washington Infrastructure Services, Inc. on December
18, 2000 to finalize the amounts and verify all federal reports were submitted for each
AIP project.
Total cost for the additional airport engineering services as shown in Amendment No.
10 for the (3) specific AIP grant projects is in an amount not to exceed $219,810.00.
If approved, final change orders reflecting these amounts will be sent to the FAA for
reimbursement(90% FAA with 10%matching fund). Funds are available underAirport
Federal Grants account nos. 415-6600-56004 Noise Berm, 415-6600-56008 Noise
Mitigation & 415-6600-56017 Second Phase Runway Extension. o=?A
i
Airport Engineering Services Contract Services Agreement a
��
Amendment No. 10
February 7, 2001
Page 2
The Airport Commission recommended City Council approD�Ef
his item at its January
3, 2001 meeting.
APPROVED:
R f IFF A F. SMOOT, A.A.E.
Assistan`{ Dir for of Aviation Interim Director of Aviation
APPROV D �J�b�iti
City Manager
Attachments: 1. Resolution
2. Amendment No. 10 REVIEWED BY DK DF FINANCE
AMENDMENT NO. 10
AGREEMENT NO. 3138, AIRPORT ENGINEERING SERVICES
THIS TENTH AMENDMENT to Agreement No. 3138 for Contract Services, (herein
"Agreement") made and entered into on this day of 2001, by and
between the CITY OF PALM SPRINGS (herein "City') and ISBILL ASSOCIATES,
RAYTHEON INFRASTRUCTURE, INC., (herein "Engineer") is hereby effective
2001 as follows:
Part II III Design Engineering &Topographic Surveys (All figures are Lump Sums):
Project 22C — Design of C.O. #1, #2 & #4ALP Update, Vicinity
Map, Pavement Strength & Record Drawings
$68,377.00
Original Project: 173,800.00 (Amend #4)
Previous Amendments: 5,000.00 (Amend #7)
This Amendment: 68,377.00
New Project Total: 247,177.00
Part IV Field Engineering (All figures are Lump Sums):
Project 22A— Detention Pond & Noise Wall Grading
$ 6,775.00
Original Project: 43,500.00 (Amend #4)
Previous Amendments:13,000.00 (Amend #7)
This Amendment: 6,775.00
New Project Total: 63,275.00
Project 22B — Delays by Contractor 45 days beyond
Contract time— Liquidated Damages
$ 10,916.00
Original Project: 31,000.00 (Amend #4)
Previous Amendments: 0
This Amendment: 10,916.00
New Project Total: 41,916.00
Project 22C - Increase in contract time of 125 days
$126,687.00
Original Project: 282,700.00 (Amend #4)
Previous Amendments: 3,500.00 (Amend #7)
This Amendment: 126,687.00
New Project Total: 412,887.00
Project 25 - Relocate Farrell Dr.
Granite Construction claim,
Ken Kinenow testimony
$ 7,055.00
Original Project: 265,000.00 (Amend.#6)
Previous Amendments: 0
This Amendment: 7,055.00
New Project Total: 272,055.00 A 3
Except as specifically worded herein, all terms and conditions of the Agreement shall
remain in full force and effect and performance of services under the Amendment shall
be governed by the provisions of the Agreement.
IN WITNESS WHEREOF, the parties have executed and entered into this Amendment
as of the date stated below:
ATTEST: CITY OF PALM SPRINGS, CALIFORNA
By:
City Clerk City Manager
APPROVED AS TO FORM:
City Attorney
CONTRACTOR:
(Check One: individual
partnership
corporation)
(NOTARIZED) By:
Signature
Print Name and Title
(NOTARIZED) By:
Signature
Print Name and Title
Mailing Address:
(Corporations require two signatures: one from each of the following: A. Chairman of
Board, President, any Vice President; AND B. Secretary, Assistance Secretary,
Treasurer, Assistant Treasurer, or Chief Financial Officer.)
End of Signatures
RESOLUTION NO. 19982
OFTHE CITYCOUNCIL OF THE CITYOF PALM SPRINGS, CALIFORNIA,
APPROVING AMENDMENT NO. 10 FOR AIRPORT ENGINEERING
SERVICES UNDER CONTRACT SERVICES AGREEMENT NO. 3138
WITH WASHINGTON INFRASTRUCTURE SERVICES, INC. (FORMALLY
RAYTHEON ENGINEERS & CONSTRUCTORS/ISBILL ASSOCIATES,
INC.) FOR A FINAL CONTRACT CLOSEOUT PAYMENT IN AN AMOUNT
NOT-TO-EXCEED $219,810.00.
WHEREAS, Amendment No. 10 to Agreement No. 3138 for additional airport engineering
services is necessary for the final closeout payment for(3)three FAA Airport Improvement
Program (AIP) grant projects, 90% funded by the FAA with 10% Airport match; and
NOW THEREFORE BE IT RESOLVED by the City Council of the City of Palm Springs,
California, that this tenth amendment for Airport Engineering Services under Contract
Services Agreement No. 3138 with Washington Infrastructure Services, Inc. (formally
Raytheon Engineers&Constructors/Isbill Associates, Inc.)forfour(4)Construction Change
Orders is hereby approved as follows:
Section 1. For airport engineering services in connection with AIP-22, Farrell
Drive Change Order No. 1 in an amount not-to-exceed $7,055.00.
Section 2. For airport engineering services in connection with AIP-22, Runway
13R/31 L Change Order No. 3 in an amount not-to-exceed
$195,064.00.
Section 3. For airport engineering services in connection with AIP-21 Noise Wall
Change Order No. 2 in an amount not-to-exceed $6,775.00.
Section 4. For airport engineering services in connection with AIP-20 Noise
Berm Change Order No. 2 in an amount not-to-exceed $10,916.00.
ADOPTED this 7" day of February, 2001.
AYES: Members Jones, Oden, Reller—Spurgin and Mayor Kleindienst
NOES: None
ABSENT: Member Hodges
ATTEST: CITY OF PALM SPRINGS, CALIFORNIA
By
City Clerk City Manager
REVIEWED &APPROVED AS TO FORM