HomeMy WebLinkAbout12/6/2000 - STAFF REPORTS (9) r�
DATE: December 6, 2000
TO: City Council
FROM: City Engineer
CONSTRUCTION CHANGE ORDER NO. 2 TO GRANITE CONSTRUCTION
COMPANY
RECOMMENDATION:
That the City Council approve Construction Change Order No. 2 to Granite
Construction Company, for an increase of$35,140.00, for the Mid-Valley
Parkway Phase 3, Gene Autry Trail and Ramon Road Traffic Signal and Street
Improvements, City Project 99-13.
SUMMARY:
Granite Construction Company(Granite)is moving forward with construction of the
Mid-Valley Parkway Phase 3 project. The project occurs within State Highway 111
right-of-way, requiring oversight by the California Department of Transportation
(Caltrans). Caltrans determines the required pavement structural section at the
time of construction. That determination has resulted in an increase of the
pavement section over what was indicated on the approved plans. To maintain
the project schedule, the Contractor was instructed to proceed with the extra work
necessary to comply with Caltrans' requirements.
BACKGROUND:
On August 2,2000, Council awarded Granite a contract for construction of the Mid-
Valley Parkway Phase 3, Gene Autry Trail and Ramon Road Traffic Signal and
Street Improvement project. That award was based on construction bids from
approved plans that specified a pavement structural section of 4.5" of asphalt
concrete pavement over 6" of base material for Gene Autry Trail (State Highway
111).
However, it was understood that this pavement section was subject to change, as
Caltrans requires that a specific calculation be made prior to construction using
information obtained from materials taken from the project site. Based upon that
testing, a determination was made by Caltrans to require a pavement section of 6"
of asphalt concrete pavement over 8" of base material within State Highway 111,
resulting in an increase of materials and additional roadway excavation.
At the time Caltrans made their determination, Granite was ready to proceed with
construction of State Highway 111. Staff advised the City Manager of the
necessity to comply with Caltrans, and move forward with the extra work in order
to maintain the project schedule. Otherwise, the project would have been put on
hold until such time that staff could present this change order to the Council for its
consideration.
Contract Change Order No. 2 consists of extra work necessary to comply with
Caltrans' requirements to increase the required pavement structural section within
State Highway 111. That work includes additional roadway excavation, asphalt
concrete pavement and base material, increasing the contract amount by$35,140,
Change Order No. 2, City Project No. 99-13
December 6, 2000
Page 2
Sufficientfunds to facilitate this change orderare available in account number 134-
4498-50133 (Local Measure A MVP Ph 3), and 261-4491-50133 (Reimbursable
Mid-Valley Parkway Phase 3).
A
DAVID J. BARAKIAN
City Engineer
City Manager'
ATTACHMENTS:
1. Minute Order
2. Change Order No. 2
REVIEWED BY DEPT.OF FINANCE
1AZ
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: Granite Construction Company Date: November 27, 2000
P. 0. Box 50085 Project No.: 99-13
Watsonville, CA 95077-5085
Project Name: MidValley Parkway Phase III — Gene
Autry Trail and Ramon Road Traffic Signal and Street
Improvements
Change Order No.: Two (2)
Attn: John Douglas Contract Purchase No.: 116172
Account Number: 134-4498-50133 and
261-4491-50133
Agr.#: 4261
M.O.# 6682 Res. #
A. CHANGES IN WORK:
Increase to Contract Quantities
Increases to the bid items below reflect replacement of existing bid items with new bid items to
comply with Caltrans' requirements to increase the required pavement structural section within Gene
Autry Trail, and include additional roadway finish grading, asphalt concrete pavement and base
material.
Bid Items
44. Construct 6" (150mm) AC Pavement
45. Construct 8" (200mm) Class II Base
Extra Work at Force Account
Finish grading to re-grade portions of Gene Autry Trail to lower subgrade elevations to
facilitate the pavement structural section determined by Caltrans.
Decrease to Contract Quantities
Decreases to the bid items below reflect replacement of existing bid items with new bid items to
comply with Caltrans' requirements to increase the required pavement structural section within Gene
Autry Trail.
Bid Items
38. Construct 4.5" (110mm) AC Pavement
39. Construct 6" (150mm) Class II Base
B. CHANGES IN COST:
Increase to Contract Quantities
Bid Items
44. Construct 6" (150mm) AC Pavement:
40,200 SF @ $1.73 per SF = $69,546.00
45. Construct 8" (200mm) Class II Base:
40,200 SF @ $1.07 per SF = $43,014.00
1h3
Change Order No. 2
Mid-Valley Parkway, CP #99-13
Page 2
Extra Work at Force Account
Lump Sum Estimate = $ 7,000.00
Total Bid Item Increases: $119,560.00
Decrease to Contract Quantities
Bid Items
38. Construct 4.5" (110mm) AC Pavement:
40,200 SF @ $1.30 per SF = $52,260.00
39. Construct 6" (150mm) Class II Base:
40,200 SF @ $0.80 per SF = $32,160.00
Total Bid Item Decreases: $84,420.00
TOTAL NET CHANGE ORDER INCREASE: $35,140.00
C. REASONS FOR CHANGES:
Changes in Work were due to the addition of work necessary to comply with Caltrans' requirements
to increase the required pavement structural section within Gene Autry Trail, and include additional
roadway finish grading, asphalt concrete pavement and base material
Summary of Costs Contract Time
Original Contract Amount: $ 898,898.00 Original Completion Date: January 23, 2001
This Change Order: $ 35,140.00 Days Added for this C.C.O.: 2
Previous Change Order(s): $ 80,277.65 Previous Days Added: 15
Revised Contract Amount: $1,014,315.65 Revised Completion Date: 2/15/01
Contractor Approval: City Approval:
___________ Submitted by: Date:-
has/have received a copy of this Change Order Engineering Field Supervisor
and the above AGREED PRICES are acceptable
to the contractor. Approved by: Date:_
City Engineer
By:
Approved by: Date:_
Title: City Manager
Date:
Distribution:
Original Conformed Copies Conformed-File Copy
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
1 AY
MINUTE ORDER NO.
APPROVING CONSTRUCTION CHANGE ORDER NO. 2
TO GRANITE CONSTRUCTION COMPANY, FOR AN
INCREASE OF $35,140.00, FOR THE MID-VALLEY
PARKWAY PHASE 3, GENE AUTRY TRAIL AND RAMON
ROAD TRAFFIC SIGNALAND STREET IMPROVEMENTS,
CITY PROJECT 99-13.
I HEREBY CERTIFY that this Minute Orderapproving Construction Change Order No.2 to Granite
Construction Company,for an increase of$35,140.00,for the Mid-Valley Parkway Phase 3,Gene
Autry Trail and Ramon Road Traffic Signal and Street Improvements, City Project 99-13, was
approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on
the 6th day of December, 2000.