HomeMy WebLinkAbout11/15/2000 - STAFF REPORTS (7) a
DATE: November 15, 2000
TO: City Council
FROM: City Engineer
CONSTRUCTION CHANGE ORDER NO. ONE (1) TO GRANITE CONSTRUCTION
COMPANY
RECOMMENDATION:
That the City Council approve Construction Change Order No. One (1) to Granite
Construction Company, for an increase of$80,277.65 to the Mid-Valley Parkway
Phase 3, Gene Autry Trail and Ramon Road Traffic Signal and Street
Improvements, City Project 99-13.
BACKGROUND:
On August 2,2000, Council awarded Granite Construction Company a contract for
construction of the Mid-Valley Parkway Phase 3, Gene Autry Trail and Ramon
Road Traffic Signal and Street Improvement project.
This change order consists of extra work being added to the project that includes
Ramon Road improvements obligated to be constructed by Lowe's Home
Improvement Warehouse, Inc., ("Lowe's). Council will consider approval of the
Ramon Road improvement reimbursement agreement between the City and
Lowe's as a separate agenda item;that agreement facilitates advance payment for
the extra work that is the subject of Contract Change Order No. 1.
The construction of Lowe's Ramon Road improvements by Granite will avoid
conflicts that would have occurred between the City's project and Lowe's. With
Granite currently under contract to construct City Project 99-13, adding Lowe's
work to the project allows the entire portion of Ramon Road to be widened and
modified at the same time, avoiding conflicts between the two projects and
challenges for traffic control and public safety.
The extra work includes removal and relocation of existing driveway entrances,
removal and reconstruction of existing raised median improvements, and traffic
striping and signage. The total adjustment to the agreement for the extra work is
$80,277.65, 100% of which is paid for by the advance payment made by Lowe's,
pursuant to the Ramon Road improvement reimbursement agreement.
Sufficientfunds to facilitate this change order are available in account number 134-
4498-50133 (Local Measure A MVP Ph 3).
1
I IV
DAVID J. BARAKIAN
City Engineer
APPROVED: ?��
City Manager
ATTACHMENTS:
1. Minute Order
2. Change Order No. 1
REVIEWED BY DEPT.OF FINANCE
� � Z
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: Granite Construction Company Date: October 5, 2000
P. O. Box 50085 Project No.: 99-13
Watsonville, CA 95077-5085 Project Name: MidValley Parkway Phase III — Gene:
Autry Trail and Ramon Road Traffic Signal and Street
Improvements
Change Order No.: One (1)
Attn: John Douglas Contract Purchase No.: 116172
Account Number: 134-4498-50133
Agr.#: 4261
M.O.# 6682 Res. #
A. CHANGES IN WORK:
Increase to Contract Quantities
Increases to the bid items below are to account for extra work being added to the project
associated with Ramon Road street improvements related to the Lowe's Home Improvement
Warehouse development adjacent to the project. The extra work includes removal and
reconstruction of existing driveway approaches, removal and reconstruction of existing median
island improvements, and traffic striping and signage, pursuant to improvements shown on revisions
to the approved drawings, sheets 4, 5, and 10, by Mainiero, Smith and Associates.
Bid Items
5. Remove Existing Curb & Gutter
6. Remove Existing Sidewalk
7. Remove Existing AC Pavement
8. Remove Existing Cross Gutter
9. Remove Existing Curb Return and Spandrel
10. Remove Existing Curb
14. Construct Type Al-6 Curb
15. Construct Type A2-8 Curb
21. Construct Curb Return and Spandrel
22. Construct Type D2 Cross Gutter
26. Construct 4" (100mm) Colored PCC Sidewalk
27. Construct Median Cobble Stone
36. Construct 5" (130mm) AC Pavement
37. Construct 4" (100mm) Class II Base
Extra Work at Force Account
Construction of four (4) Type C Curb Ramps, per City of Palm Springs Standard Drawing
No. 214; installation of two (2) type R-10 signs and posts; installation of five (5) Type IV (L)
white thermoplastic markings; installation of 185 linear feet of traffic striping per Caltrans
Standard Plan A20C, Detail 38C; and traffic control.
03
B. CHANGES IN COST:
Increase to Contract Quantities
Bid Items
5. Remove Existing Curb & Gutter:
379 LF @ $3.00 per LF = $1,137.00
6. Remove Existing Sidewalk
3,814 SF @ $1.00 per SF = $3,814.00
7. Remove Existing AC Pavement
7,304 SF @ 1.00 per SF = $7,304.00
8. Remove Existing Cross Gutter
448 SF @ 1.00 per SF = $448.00
9. Remove Existing Curb Return and Spandrel
814 SF @ $1 .00 per SF = $814.00
10. Remove Existing Curb
663 LF @ $2.00 = $1,326.00
14. Construct Type Al-6 Curb
1,053 LF @ $15.00 per LF = $15,795,00
15. Construct Type A2-8 Curb
255 LF @ $17.00 per LF = $4,335.00
21 . Construct Curb Return and Spandrel
2,252 SF @ $5.00 per SF = $11,260.00
22. Construct Type D2 Cross Gutter
687 SF @ $6.00 per SF = $4,122.00
26. Construct 4" (100mm) Colored PCC Sidewalk
2,040 SF @ $3.00 per SF = $6,120.00
27. Construct Median Cobble Stone
420 SF @ 5.00 per SF = $2,100.00
36. Construct 5" (130mm) AC Pavement
7,071 SF @ $1.50 per SF = $10,606.50
37. Construct 4" (100mm) Class II Base
7,071 SF @ $0.65 per SF = $4,596.15
Extra Work at Force Account
Lump Sum Estimate = $6,500.00
TOTAL NET CHANGE ORDER INCREASE: $80,277.65
C. REASONS FOR CHANGES:
Changes in Work were due to the addition of work related to Ramon Road improvements associated
with the Lowe's Home Improvement Warehouse development located adjacent to the project.
Conflicts between Ramon Road improvements by Lowe's and improvements constructed by Granite
required coordination between the two projects and construction of all Ramon Road improvements
under one contract by Granite. The costs of Lowe's improvements to be paid to the City under a
separate reimbursement agreement.
D. SOURCE OF FUNDS:
Funds are available in the following account: #134-4498-50133 (Local Measure A MVP Ph 3);
100% of the cost of this change order is paid for by Lowe's pursuant to the Ramon Road
Improvement Reimbursement Agreement. Q
r I/
Summary of Costs Contract Time
Original Contract Amount: $ 898,898.00 Original Completion Date: January 23, 2001
This Change Order: $ 80,277.65 Days Added for this C.C.O.: -15-
Previous Change Order(s): 1 0.00 Previous Days Added: -0-
Revised Contract Amount: $ 979,175.65 Revised Completion Date: February 13, 2001
Contractor Approval: City Approval:
Submitted by: Date:
Field Engineering Supervisor
has/have received a copy of this Change
Order and the above AGREED PRICES are Approved by: Date:
acceptable to the contractor. Procurement Manager
By: Approved by: Date:
City Engineer
Title:
Approved by: Date:
Date: City Manager
Distribution:
Original Conformed Conies Conformed-File Copy_
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
104
r .
,43
E, 669 441 001
WESTERN PROPERTIES INC
767 5TH AVE #43RD
/y NEW YORK NY 10153
— •,,a 'RDIMp "
t
4� 4 669 396 114 �
33143 & DONNA SAVAGE
MESA VISTA DR
"A POINT CA 92629 ��
Sfl VFl.t41 RF- MR
l'f.Ji?N, T'40.a
rATTEMPTED
�:NG F� uNALgi R.c, a c s ON�,,�,a�a�4__.
h0T
MINUTE ORDER NO.
APPROVING CONSTRUCTION CHANGE ORDER NO. 1
TO GRANITE CONSTRUCTION COMPANY FOR AN
INCREASE OF $80,277.65 TO THE MID-VALLEY
PARKWAY PHASE 3, GENE AUTRY TRAIL AND RAMON
ROAD TRAFFIC SIGNALAND STREET IMPROVEMENTS,
CITY PROJECT 99-13.
I HEREBY CERTIFY that this Minute Order approving Construction Change Order No. 1 to Granite
Construction Company for an increase of$80,277.65 to the Mid-Valley Parkway Phase 3, Gene
Autry Trail and Ramon Road Traffic Signal and Street Improvements, City Project 99-13, was
approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on
the 15" day of November, 2000.