HomeMy WebLinkAbout20573 - RESOLUTIONS - 3/26/2003 RESOLUTION NO. 20573
OF THE CITY COUNCIL OF THE CITY OF
PALM SPRINGS,CALIFORNIA,APPROVING
A CONSTRUCTION SCHEDULE RECOVERY
PLAN FOR PHASE I CONVENTION CENTER
EXPANSION/REMODEL PROGRAM. A94577
WHEREAS the City has undertaken the remodel of the Convention Center involving the
kitchen and additional meetings rooms and design issues along with unknown conditions
have resulted in a delay in schedule as much as three weeks; and
WHEREAS the Convention Center is contractually obligated to provide facilities for incoming
groups which require an on-time completion; and
WHEREAS the project management team has met and developed a strategy to recover the
schedule,
NOW THEREFORE BE IT RESOLVED BY THE City Council of the City of Palm Springs as
follows:
Section 1. Turner Construction Company contract #A4577 is hereby amended to
' authorize an additional superintendent on the project for a nine-week period
at $29,700.
Section 2. The construction project management team is hereby authorized to utilize
overtime to accelerate the remaining schedule up to a total of$25,000.
Section 3. The contingency account is hereby increased by $101,000 and the Project
Administrator is authorized to approve change orders up to that total amount.
ADOPTED this -)6t day of March 2003.
AYES: Members Mills, Oden, Reller-SPurgin and Mayor Kleindienst
NOES: None
ABSENT: Member Hodges