HomeMy WebLinkAbout20573 - RESOLUTIONS - 3/26/2003 RESOLUTION NO. 20573 OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS,CALIFORNIA,APPROVING A CONSTRUCTION SCHEDULE RECOVERY PLAN FOR PHASE I CONVENTION CENTER EXPANSION/REMODEL PROGRAM. A94577 WHEREAS the City has undertaken the remodel of the Convention Center involving the kitchen and additional meetings rooms and design issues along with unknown conditions have resulted in a delay in schedule as much as three weeks; and WHEREAS the Convention Center is contractually obligated to provide facilities for incoming groups which require an on-time completion; and WHEREAS the project management team has met and developed a strategy to recover the schedule, NOW THEREFORE BE IT RESOLVED BY THE City Council of the City of Palm Springs as follows: Section 1. Turner Construction Company contract #A4577 is hereby amended to ' authorize an additional superintendent on the project for a nine-week period at $29,700. Section 2. The construction project management team is hereby authorized to utilize overtime to accelerate the remaining schedule up to a total of$25,000. Section 3. The contingency account is hereby increased by $101,000 and the Project Administrator is authorized to approve change orders up to that total amount. ADOPTED this -)6t day of March 2003. AYES: Members Mills, Oden, Reller-SPurgin and Mayor Kleindienst NOES: None ABSENT: Member Hodges TEST: CITY OF PALM SPRINGS, CALIFORNIA ✓`��®.�_ tee% City Clerk City Manager a G REVIEWED &APPROVED AS TO FORM a/�