HomeMy WebLinkAbout20090 - RESOLUTIONS - 7/5/2001 RESOLUTION NO. 20090
' OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS,
CALIFORNIA, FINDING THAT THE BIDS FROM R. MOODY
CONSTRUCTION, R.E.FLEMMING, AND COMMERCIAL
DIVERSIFIED ARE NON-RESPONSIVE, AWARDING
CONTRACT TO PALM VALLEY CONSTRUCTION FOR THE
EXPANSION OF THE AIRPORT RESCUE AND FIREFIGHTING
STATION, CITY PROJECT #2000-32, AIP-32, SUBJECT TO
FEDERAL AVIATION ADMINISTRATION APPROVAL,IN THE
AMOUNT OF $877,000, INCLUDING ALTERNATES 1 AND 3,
ESTABLISHING PROJECT ADMINISTRATION PARAMETERS,
AND APPROVING CHANGE ORDER NO. 1 IN A DEDUCT
AMOUNT OF ($16,690).
WHEREAS the Palm Springs International Airport is in the process of replacing its fire fighting
vehicles with larger vehicles which can no longer be accommodated in the existing station bays;and
WHEREAS the Airport has received a federal grant to expand the station and plans have been
developed and bid competitively,
NOW THEREFORE BE IT RESOLVED as follows:
1. That the bids from R. Moody Construction, R.E. Fleming, and Commercial Diversified are
hereby found to be non-responsive as no DBE commitments were provided; and
2. That the Expansion of the Airport Rescue and Fire Fighting Station, City Project#2000-32,
AIP-32, subject to FAA approval, is hereby awarded to Palm Valley Construction in the
amount of$877,000, including Alternates 1 and 3; and
3. That the Assistant City Manager-Special Projects is hereby appointed as Project
Administrator; and
4. That the Project Administrator is hereby authorized to approved Change Orders up to 7%of
the project bid.
5. That Change Order No. 1 to the contract is hereby approved, related to accommodating
longer vehicles in a deduct amount of($16,690).
1
Resolution 20090
Airport Fire Station Expansion ,
July 5, 2001
Page Two
ADOPTED this 5th day of July , 2001.
AYES: Members Hodges, Jones, and Mayor Kleindienst
NOES: None
ABSENT: Members Reller-Spurgin.and Oden
ATTES CITY OF PALM SPRINGS, CALIFORNIA
City Clerk City Manager