HomeMy WebLinkAbout9/20/2000 - STAFF REPORTS (6) DATE: September 20, 2000
TO: City Council
FROM: City Engineer
APPROVE CONSTRUCTION CHANGE ORDER NO. FIVE (5) TO G & M CONSTRUCTION
RECOMMENDATION:
That the City Council approve Construction Change Order No. Five (5) to G and M
Construction, for a decrease of<$6,697.99> forthe Underground Storage Tank Removal
and Replacement Project, City Project 95-17.
BACKGROUND:
On January 21, 1998, City Council of the City of Palm Springs awarded G and M
Construction the contract for the Underground Storage Tank Removals and Replacement
project.
This change order consists of the following work:
Schedule A - City Yard (Site No. 1)
Bid Item 3, Removal and Disposal of Contamination Material,decreased($8,550.00).This
bid item is lump sum. The decrease amount was calculated from the contractor's actual
invoice to remove the contaminated soil. Item F, Grade Level Fills,was added($2,570.60)
due to a design change for fuel delivery safety, per the City's consulting engineer.
Originally, fuel delivery to the aboveground tanks was to be from the top of the tanks,
using a stairway. By adding these grade level fills at the bottom of these tanks, liability for
injury would be reduced. Item G, Gas/Diesel Pump and Shelf, was added ($2,700.00) to
provide an emergency backup fuel system in the event there is a power failure. By having
these fuel pumps mounted on the aboveground fuel tanks, City personnel can continue
to fuel their vehicles. Item H, Relocate existing waterline, was added($402.80) because
the existing water line conflicted with the removal of the underground storage tank, per
plans. Items 1-1 through 1-5, were added ($2,240.00) per Riverside County HazMat
Agency's new testing requirements. Item J, Relay for the Gate Controller, was added
($221.40) to make the proposed new gate system integrate with the electrical system of
the existing gate. Item K, Twin Diesel Dispenser, was added ($1,920.00)to provide more
fuel dispensing for vehicles and equipment per the recommendation of the City's
consulting engineer and Fleet Operations Supervisor. The original contract Plans and
Specifications called out for single diesel dispenser. In the revised plan where the
aboveground storage tanks were installed in one central location, it was recommended by
the City's consulting engineer and Fleet Operations Supervisor to upgrade the single diesel
dispenser to a twin diesel dispenser. Credit was applied for the single diesel dispenser.
.CA
September 20, 2000
City Project 95-17 Underground Storage Tank Removal and Replacement Project
City Council Report for Change Order No. Five (5)
Page 2 of 3
Item L, Break away Hose, was added ($298.80) due to an accident. A vehicle drove off
with the fuel dispenser still in the fuel tank of the vehicle. The fuel management system
was not on line when this occurred and it could not be determined who was the
responsible person who broke it. Item M, Relocate Air and Water Dispenser, was added
($922.80) per the recommendation of the Fleet Operations Supervisor to keep the air and
water dispenser away from the fuel island,allowing only vehicles to fuel. Item N was added
($ 404.39) per the recommendation of the Fleet Operations Supervisor to have a spare
circuit board for the gate controller to insure that if the circuit board fails, City personnel
can still have access in and out of the City Yard at all times.
Schedule B - Palm Springs Airport (Site No. 2)
Bid Item 3, Removal and Disposal of Contamination Material,was credited to the contract
($350.00) due to no contamination found during the removal of the under ground storage
tank.
Schedule C - Co-Gen Plant (Site No. 3)
Bid Item 3, Removal and Disposal of Contamination Material, was credited to the contract
($350.00)due to no contamination found during the removal of the under ground storage
tank.
Schedule D -Ave. 34, Lift Station (Site No. 4)
Bid Item 3, Removal and Disposal of Contamination Material, was credited to the contract
($350.00) due to no contamination found during the removal of the under ground storage
tank.Also, per the recommendation of the City's consulting engineer and US Filter, added
($300.00)and installed a day tank for the existing generator to insure start-up in the event
of a power failure.
Schedule E- Wastewater Treatment Plant (Site No. 5)
Bid Item 3, Removal and Disposal of Contamination Material, was credited to the contract
($700.00) due to no contamination found during the removal of the under ground storage
tank.
Schedule F - Wastewater Treatment Plant Lift station at the Golf Course (Site No. 6)
Bid Item 3, Removal and Disposal of Contamination Material, was credited to the contract
($700.00)due to no contamination found during the removal of the under ground storage
tank.
Schedule J - Police Department (Site No. 10)
Items B-1 through B-3, Overfill Alarm, was added ($722.80) per the requirements of the
Riverside County HazMat Agency to upgrade the existing underground fuel tank with an
overfill alarm system which will detect a spill, in the event of a fuel leak.
Credit($6,976.58)was applied in Change Order No. 1 because the cost to purchase the
aboveground storage tanks for Schedules A, B, C. E and F did not exceed estimated cost
Credit($1,425.00)for Item A,A/C Unit,was applied to Change Order No. 3. This item was
deleted because the temperature in the Lift Station would not exceed the recommended
operating temperature for the Veeter Root system.
September 20, 2000
C.P 95-17 Underground Storage Tank Removals and Replacement
City Council Report for Change Order No. Five (5)
Page 3 of 3
162 additional working days will be added to the contract due to the extra work (15) and
testing requirements (147) for the new fuel system.
Credit to be applied to the following accounts:
Replace Underground Fuel Tank:
Schedule A - City Yard: #261-1395-54006 (Replace Undrgd Fuel Tanks) < $4,122.14 >
Schedule B -Airport: #341-6400-54010 (Fuel St. Tank Replacement) < $ 443.92 >
Schedule C - Muni Co-Gen Plant: #261-1395-54006 (same as above) < $ 434.30 >
Schedule D -Ave. 34 Lift Station: #342-6820-54006 (Repl Fuel Tank) < $ 50.00 >
Schedule E - Wastewater Treatment Plant: #342-6820-54006 ( ) < $ 828.39 >
Schedule F - Lift Station @ Golf Course: #342-6820-54006 ( ) < $ 819.24 >
Total De
cre < $6 697.99 >
— i�
APPROVED: r����
DAVID J. BARAKIAN OTT MIKESELL
City Engineer Director of Facilities
APPROVED:
' Ci Manager
Attachment: Minute Order MEWED BY DR O ME
Change Order No. Five (5)
r -
CITY OF PALM SPRINGS
CONTRACT CHANGE ORDER
To: G & M Construction Date: September 6, 2000
211 Mesquite Ave. Project No.: C.P. 95-17
Palm Springs, CA 92264 Project Name: Underground Storage Tank
Removals and Replacement
Change Order No.: Five 5
Attn: Mike Marantz Contract Purchase No.: 806347
Account Number(s): 341-320-0670-8014.
342-320-0682-7513, 161-320-0495-7980
Agr.# 3902 M.O.# 6093 Res.#
A.CHANGES IN WORK:
Increase to Contract(New Items): Schedule A-City Yard(Site No. 1)
Bid Item Description
F Provide and Install Grade Level Fills
G Provide and Install 1 ea: Gas Pump/Shelf, Diesel Pump/Shelf, Fittings & Piping and Spare
Gas Pump
H Relocate Existing Water Line
1-1 Additional Tests for MTBE per Riverside Co. HazMat
1-2 Additional Analyzation Testing- Metals, per Riverside Co. HazMat
1-3 Additional Analyzation Testing-Benzine, per Riverside Co. HazMat
1-4 Additional Analyzation Testing-Volatiles, per Riverside Co. HazMat
1-5 Additional Dry Ice Requirement per Riverside Co. HazMat
J Relay Redesign for Gate Controller
K Add Twin Diesel Dispenser, Hoses and Nozzle
L Replace Breakaway Hose
M Relocate Air and Water Dispenser
N Spare Circuit Board for Gate Controller
Increase to Contract(New Items): Schedule D-Ave. 34 Lift Station (Site No.4)
Bid Item Description
B Provide and Install Day Tank for Generator
Increase to Contract(New Items): Schedule J-Police Department(Site No. 10)
Bid Item Description
B Provide and Install Overfill Alarm Controller and Parts
Decrease to Contract Items
Schedule A-City Yard(Site No. 1)
Bid Item Description
3 Removal and Disposal of Contamination Material
Schedule B-Palm Springs Airport(Site No. 2)
Bid Item Description
3 Removal and Disposal of Contamination Material
Schedule C-Co-Gen Plant(Site No. 3)
Bid Item Description
3 Removal and Disposal of Contamination Material
September 6,2000
C.P. 95-17 Underground Storage Tanks and Removal
Change Order No. Five (5)
Page 2 of 6
A.CHANGES IN WORK:
Decrease to Contract Items
Schedule D-Ave. 34 Lift Station (Site No. 4)
Bid Item Description
3 Removal and Disposal of Contamination Material
Schedule E-Wastewater Treatment Plant(Site No. 5)
Bid Item Description
3 Removal and Disposal of Contamination Material
Schedule F-Wastewater Treatment Plant Lift Station on the Golf Course (Site No. 6)
Bid Item Description
3 Removal and Disposal of Contamination Material
Decreases to Contract Change Order No. One(1) Storage Tanks for the following Schedules:
Bid Item Description
Schedule A-City Yard
Schedule B-Airport
Schedule C- Muni Co-Gen Plant
Schedule E-Wastewater Treatment Plant
Schedule F-Lift Station at Golf Course
Decreases to Contract Change Order No. Three (3) Schedule D -Ave. 34
Bid Item Description
A Install A/C Unit for Veeter Root System
B. CHANGES IN CONTRACT COST:
Increases to Contract(New Items): Schedule A- City Yard(Site No. 1)
Bid Item Description
F Provide and Install Grade Level Fills Lump Sum $ 2,570.60
G Provide and Install 1 ea: Gas Pump/Shelf, Lump Sum $ 2,700.00
Diesel Pump/Shelf, Fittings & Piping and
Spare Gas Pump
H Relocate Existing Water Line Lump Sum $ 402.80
1-1 Additional Tests for MTBE Lump Sum $ 600.00
1-2 Additional Analyzation Testing-Metals Lump Sum $ 250.00
1-3 Additional Analyzation Testing-Benzine Lump Sum $ 540.00
1-4 Additional Analyzation Testing-Volatiles Lump Sum $ 500.00
1-5 Additional Dry Ice Requirement Lump Sum $ 350.00
J Relay Redesign for Gate Controller Lump Sum $ 221.40
K Twin Diesel Dispenser, Hoses and Nozzle Lump Sum $ 1,920.00
L Breakaway Hose Lump Sum $ 298.80
M Relocate Air and Water Dispenser Lump Sum $ 922.80
N Spare Circuit Board for Gate Controller Lump Sum $ 404.39
Sub-Total $ 11,680.79
shor
September 6, 2000
C.P. 95-17 Underground Storage Tanks and Removal
Change Order No. Five (5)
Page 3 of 6
B. CHANGES IN CONTRACT COST:
Increase to Contract(New Items): Schedule D-Ave. 34 Lift Station(Site No. 4)
Bid Item Description
B Provide and Install Day Tank for Generator Lump Sum $ 300.00
Increase to Contract(New Items): Schedule J - Police Department(Site No. 10)
Bid Item Description
B Provide and Install Overfill Alarm Controller Lump Sum $ 722.80
Decrease to Contract Items:
Schedule A-City Yard (Site No. )
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 8,550.00)
Schedule B- Palm Springs Airport(Site No.2)
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 350.00)
Schedule C -Co-Gen Plant(Site No. 3)
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 350.00)
Schedule D-Ave. 34 Lift Station(Site No. 4)
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 350.00)
Schedule E-Wastewater Treatment Plant(Site No. 5)
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 700.00)
Schedule F-Wastewater Treatment Plant Lift Station on the Golf Course (Site No.6)
Bid Item Description
3 Removal and Disposal of Contamination Material Lump Sum ($ 700.00)
Sub-Total ($ 11,000.00)
Decreases to Contract Change Order No. One (1) Storage Tanks for the following Schedules:
Bid Item Description
Schedule A-City Yard Lump Sum ($ 6,550.73)
Schedule B -Airport Lump Sum ($ 93.92)
Schedule C- Muni Co-Gen Plant Lump Sum ($ 84.30)
Schedule E-Wastewater Treatment Plant Lump Sum ($ 128.39)
Schedule F- Lift Station at Golf Course Lump Sum ($ 119.24)
Sub-Total ($ 6,976.58
Decreases to Contract Change Order No.Three(3)Schedule D-Ave. 34
Bid Item Description
A Install A/C Unit for Veeter Root System Lump Sum ($ 1,425.00)
sh
September 6, 2000
C.P. 95-17 Underground Storage Tanks and Removal
Change Order No. Five (5)
Page 4 of 6
B. CHANGES IN CONTRACT COST:
TOTAL NET CHANGE ORDER (CREDIT) _ ( $ 6,697.99 )
NOTE: No additional markup will be added to any New Items in this Chanae Order.All cost per each
item are final.
C. REASON FOR CHANGE:
Increase to Contract (New Items):
Schedule A-City Yard (Site No. 1)
Item F was added due to a design change.This changewas recommended bythe City's consulting engineer,
Tait&Associates,for fuel delivery safety to the Aboveground Storage tanks. Originally,fuel delivery to the
aboveground tanks was to be from the top of these tanks, using a stairway. By adding these grade level fills
at the bottom of these tanks, liability for injury would be reduced.
Item G was added per the recommendation of the Fleet Operations Supervisor to have an emergency
backup fuel system in the event there is a power failure.By having these fuel pumps mounted on the above
ground fuel tanks, City personnel can continue to fuel their vehicles.
Item H was added because the existing water line to the City's car wash conflicted with the removal of the
existing underground storage tank.
Item 1-1 was added due to strictertesting requirements for MTBE per Riverside County HazMat Agency.This
test is to ensure there is no contamination in the ground that might lead into the ground water table.
Item 1-2 was added due to strictertesting requirement for Metals per Riverside County HazMat Agency.This
test is for waste oil leaks.
Item 1-3&4 was added due to stricter testing requirements for Benzine and Volatiles per Riverside County
HazMat Agency. These tests are for regulating excess vapor for unleaded fuel.
Item 1-5 was added into all existing underground storage tanks prior to removal to eliminate the oxygen in
the tanks. By doing this, it eliminates any chance of an explosion during removal. This was per Riverside
County HazMat Agency.
Item J was added to make the proposed new gate system integrate with the electrical system of the existing
gates.
Item K was added per the recommendation of the Fleet Operations Supervisor and the City's consulting
engineer, Tait & Associates. The original contract Plans and Specifications called out for a single diesel
dispenser. In the revised plan where the aboveground tanks were installed in one central location, it was
recommended by the Fleet Operations Supervisor and the City's consulting engineer, Tait&Associates,to
upgrade the single diesel dispenser to a twin diesel dispenser.The contractor credited the City for the single
nozzle dispenser.
Item L was added due to an accident. A vehicle drove off with the fueling dispenser still in the fuel tank of
the vehicle.The fuel management system was not on line when this occurred and it could not be determined
who was the responsible person who broke it.
3d7
September 6,2000
C.P. 95-17 Underground Storage Tanks and Removal
Change Order No. Five (5)
Page 5 of 6
C. REASON FOR CHANGE:
Increase to Contract(New Items):
Schedule A-City Yard (Site No. 1)
Item M was added per the recommendation of the Fleet Operations Supervisor to keep the air and water
dispenser away from the fuel island, allowing only vehicles to fuel. By keeping the air and water dispenser away
from the fuel island, this allows more vehicles and equipment to fuel and not having to wait for vehicles and
equipment that are only using the air and water dispenser.
Item N was added per the request of the Fleet Operations Supervisor who requested to have a spare circuit
board for the gate controller to insure that if the circuit board fails, City personnel can still have access in and
out of the City Yard at all times.
Schedule D-Ave. 34, Lift Station (Site No, 4)
Per the request of US Filter, install a day tank for the existing generator in the event of a power failure. Per the
Plans and Specification, no day tank was required. After numerous testings of the system, Tait agreed that a
day tank would work better to start-up the generator in the event of a power failure.
Schedule J-Police Department(Site No. 10)
Per the requirements of the County of Riverside, Health Services Agency, Department of Environmental Health,
upgrade the existing underground fuel tank with a overfill alarm system, which will detect spillage, in the event
of a fuel leak.
Decrease to Contract Item:
Schedule A-City Yard(Site No. 1)
Bid Item 3, Remove and Disposal of Contamination Material decreased. The decrease amount was calculated
from the contractors's actual invoice to remove the contamination.
Schedule B-Palm Springs Airport(Site No. 2)
Bid Item 3, Remove and Disposal of Contamination Material was deleted due to no contamination found during
the removal the underground storage tank.
Schedule C-Co-Gen Plant(Site No. 3)
Bid Item 3, Remove and Disposal of Contamination Material was deleted due to no contamination found during
the removal the underground storage tank.
Schedule D-Ave. 34, Lift Station (Site No.4)
Bid Item 3, Remove and Disposal of Contamination Material was deleted due to no contamination found during
the removal the underground storage tank
Schedule E-Wastewater Treatment Plant(Site No. 5)
Bid Item 3, Remove and Disposal of Contamination Material was deleted due to no contamination found during
the removal the underground storage tank
Schedule F-Wastewater Treatment Plant Lift Station at the Golf Course (Site No.6)
Bid Item 3, Remove and Disposal of Contamination Material was deleted due to no contamination found during
the removal the underground storage tank
J0i9 9
September 6, 2000
C.P. 95-17 Underground Storage Tanks and Removal
Change Order No. Five (5)
Page 6 of 6
C. REASON FOR CHANGE:
Decreases to Contract Change Order No. 1, Aboveground Storage Tanks
Cost to purchase aboveground storage tanks for Schedules A, B,C, E and F did not exceed estimated cost.
The difference was credited to the contract.
Decrease to Contract Change Order No. 3, A/C Unit
A/C Unit for the proposed Veeter Root System for Schedule D - Ave. 34, Lift Station (Site No. 4), was
deleted because the temperature in the Lift Station would not exceed the recommended operating
temperature for the proposed Veeter Root system.
162 working days were added due to the extra work (16) and the testing requirements for the new fuel
systems (147).
D.SOURCE OF FUNDS:
Replace Underground Fuel Tanks: Account No.
Schedule A-City Yard: 261-1395-54006 < $4,122.14>
Schedule B-Airport 341-6400-54010 < $ 443.92 >
Schedule C- Mini Co-Gen Plant 261-1395-54006 < $ 434.30 >
Schedule D-Ave. 34 Lift Station 342-6820-57000 < $ 50.00>
Schedule E-Wastewater Treatment Plant 342-6820-57000 < $ 828.39 >
Schedule F- Lift Station at the Golf Course 342-6820-57000 < $ 819.24 >
Total Decrease < $6,697.99 >
Summary of Costs Contract Time
Original Contract Amount: $224,950.00 Original Completion Date: Oct. 8, 1998
This Change Order: ($ 6,697.99) Days Added for this C.C.O.: 162
Previous Change Order(s): $280,768.04 Previous Days Added: 310
Revised Contract,Amount: $499,020.05 Revised Completion Date: Sept. 8, 2000
1 have received a copy of this Change City Approval:
Order and the above AGREED PRICES Submitted By Date:
are acceptable to the contractor. Field Engineering Supervisor
w
By Approved By Date:
City Engineer
Title Approved By Date
Director of Facilities
Date Approved By Date
City Manager
Distribution:
Original Conformed Conies Conformed-File Copy
Engineering (1) Engineering File (1)
Finance (1) Engineering Field Inspector (1)
Contractor (1) Engineering Field Supervisor (1)
City Clerk (1) Purchasing Agent (1)
5011
MINUTE ORDER NO.
APPROVING CONSTRUCTION CHANGE ORDER
NO. FIVE (5) TO G & M CONSTRUCTION, FOR A
DECREASE OF <$6,697.99> FOR THE
UNDERGROUNDSTORAGETANKREMOVALAND
REPLACEMENT PROJECT, CITY PROJECT NO.
95-17
I HEREBY CERTIFY that this Minute Order approving Construction Change Order No. Five (5)to
G and M Construction, for a decrease of < $6,697.99 > for the Underground Storage Tank
Removal and Replacement Project, City Project 95-17, was approved by the City Council of the
City of Palm Springs, California, in a meeting thereof held on the 201" day of September 2000.
PATRICIA A. SANDERS
City Clerk