HomeMy WebLinkAbout18597 - RESOLUTIONS - 5/3/1995 RESOLUTION P10. 18597
OF THE CITY COUNCIL OF THE CITY OF PALM SPRINGS,
CALIFORNIA, CONDITIONALLY AWARDING CONTRACT TO
GRANITE CONSTRUCTION COMPANY, FOR RUNWAY SAFETY
AREA IMPROVE!VIENTS, CITY PROJECT #94-45 IN THE
AN!OUNT OF $3,915,91 5, AUTHORIZING THE CITY MANAGER
TO ACCEPT A FEDERAL AVIATION ADMINISTRATION GRANT ,
AND AUTHORIZING THE CITY CLERK TO PROCESS CONTRACT
DOCUMENTS PRIOR TO RECEIPT OF THE GRANT.
WHEREAS the Federal Aviation Administration has approved the second phase of the Airport's
Safety Area Improvement Program and is processing a grant request; and
WHEREAS the second phase work requires a main runway shutdown and is very time
sensitive so as to not inhibit Night activity after September 1, 1995; and
WHEREAS competitive bids were received of the Safety Area improvement Project, City
Project #94 45, on [`flay 3, 1995; and
WHEREAS after review of the bids, the lowest responsive, responsible bidder was determined
to be Granite Construction Company,
NOW THEREFORE BE IT RESOLVED as follows:
Section I. City Project #94-45, AIP 3-06-0181-17 18, is hereby awarded to Granite
Construction Coripany, in the amount of $3, 915,915, subject to FAA review
and acceptance of the recommended lowest responsive bidder.
Section 2. The City Clerk is hereby authorized to process the contract documents prior to '
receipt of the AIP-18 grant, in an effort to ensure timely start and completion
of the project.
Section 3. The City Manager is hereby authorized to accept on behalf of the City of Palm
Springs AIP 3-06-0181-18 Grant from the Federal Aviation Administration in an
amount not to exceed $3 million.
ADOPTED this 3rd day of May 1995.
AYES: Members Hodges, Kleindienst, lyons, Reller-Spur-gin and Mayor Maryanov
NOES: None
ABSENT: None
ATTEST: CITIj. \ASPRINT Ay�LIFORNIA
yCity Clerk ager
�..1 ,.
REVIEWED & APPROVED AS TO FORM