HomeMy WebLinkAbout8/2/2000 - STAFF REPORTS (5) DATE: AUGUST 2, 2000
TO: COMMUNITY REDEVELOPMENT AGENCY
FROM: DIRECTOR OF REDEVELOPMENT
APPROVAL OF RADIO ROAD INFRASTRUCTURE IMPROVEMENTS AS AN AGENCY
CAPITAL PROJECT
RECOMMENDATION:
It is recommended that the Agency approve the infrastructure improvements on
Radio Road, in the former Highland Gateway project area, as an Agency capital
project, and approve a reimbursement agreement with the City of Palm Springs for
the construction of those improvements, to effectuate the Redevelopment Plan for
the Highland Gateway Redevelopment Project, now part of Merged Redevelopment
Project Area #1.
BACKGROUND:
In 1998, when Desert Fountain Gas experienced a catastrophic structural fire and
began to go through the approval process for their reconstruction, they sought
Agency assistance for their project,which is located at the corner of Radio Road and
North Indian Canyon Drive in the Highland-Gateway Redevelopment Project Area.
There was little the Agency was able to do in the form of direct assistance in their
rebuilding project, but did agree to cover the costs of the street improvements on
Radio Road that the owners would now be required to construct because of the
rebuilding. Had the building not burned down and they had not ever had to rebuild,
they would never have been required to construct those improvements; so it was
considered a burden over and above replacing the building.
The Planning Commission agreed, in their Conditions of Approval on the project, to
defer the construction of those street improvements — curb, gutter and sidewalk
estimated at$32,000—until the Agency was able to construct those improvements.
That phase of the Radio Road improvement was recently adopted by the Agency in
the 2000-01 budget.
In discussing the projectwith Planning and Engineering, however,they identified the
more immediate need on Radio Road to be an unpaved section of the road just west
of Anza. The estimated cost of constructing those improvements was $61,000.
Agency staff instructed the City Engineer to proceed with the design and bidding of
those Radio Road improvements in the Fall of 1999 — constructing the unpaved
section. Funds were available in the project area's Commercial Rehab Program
account in the amount of $65,000. Those funds were transferred into a new line
item for Radio Road improvements. In order to achieve efficiencies (and therefore
cost savings), the City Engineer bid the project with two other street improvement
projects: Cerritos Road and Hermosa Drive (Bid 99-20). The strategy paid off—the
low bidder on the Radio Road portion of the project was approximately $39,000,
significantly less than estimated.
Nevertheless, in orderfor the Agency to pay forthe improvements as contemplated,
either separate agreements with the contractor(one for Cerritos and Hermosa with
the City, the other for Radio with the Agency) would need to be drafted and
executed, or the City and Agency need to make findings that the Agency's
construction of those improvements is appropriate and the Agency and City would
enter a reimbursement agreement for that portion of the contract. Since separate
contracts would necessitate two sets of insurance certificates and two separate sets
of bonds (performance bonds, labor bonds, etc.), not to mention the legal cost of
drafting two agreements, much of the savings to the three projects would be
eliminated with separate agreements. These additional costs were not specified in
c "
the bid, either, which would mean that they would need to be negotiated with the
contractor and added to the contracts.
The Redevelopment Plan for the Project Area states that the Agency is "authorized
to install and construct, or to cause to be installed and constructed,within or without
the Project Area, for itself or for any public body or entity, for the benefit of the
Project Area, public improvements and public utilities, including, but not limited to,
the following: (1) over and underpasses; (2) sewers; (3) natural gas distribution
systems; (4)water distribution systems; (5) parks, plazas and pedestrian paths; (6)
playgrounds; (7) storm drains and related facilities; (8) parking facilities; (9)
landscaping; and (10) street and alley improvements and bridges." (§324)
Furthermore, §324 states that the "Agency may enter into contracts, leases and
agreements with the City or other public body pursuant to this Section 324..." Staff
therefore recommends the following actions: the Agency adopts the capital project
through resolution and approves a Reimbursement Agreementwith the City, and the
City Council makes the findings that the construction of those public improvements
is appropriate for the Agency to do and also approves the Reimbursement
Agreement with the Agency.
Radio Road is a General Plan street, so the improvements receive a Class 1
exemption from CEQA, per Section 15301 of the California Code.
Funds were already appropriated in 1999-2000 in account 807-8187-65106 and
were part of the Agency's continuing appropriations in account 811-8191-65106.
The account numbers changed due to the recent project area mergers.
JOHN Sj RAYM OND l
Directop'of Redevelopment
APPROVED:
�y-cutive Director
ATTACHMENTS:
1. Agency Resolution
2. Reimbursement Agreement
3. City Council Resolution
REVIEWED BY DEPT.OF FINANCE
REIMBURSEMENT AGREEMENT
August_, 2000
Palm Springs, California
FOR VALUE RECEIVED, the undersigned ("Agency") hereby promises to
reimburse the CITY OF PALM SPRINGS, a public body, corporate and politic ("City"), the
Contract Sum paid to Matich Construction of San Bernardino, California, for the costs of
constructing certain street improvements constructed on in the City of Palm Springs on
Radio Road, between McCarthy and Anza, in the former Highland Gateway
Redevelopment Project Area and awarded under City Bid 99-20, in an amount not to
exceed Sixty-Five Thousand Dollars ($65,000.00).
a. Repayment by Agency. Agency shall pay in full to the City the Contract
Sum paid by the City to the Contractor, plus the City costs of bidding,
inspection, and project administration, in lawful money of the United
States, no later than sixty (60) days after the Notice of Completion has
been signed by the City Engineer. No interest is due the City under this
Agreement.
b. Prepayment. This Agreement sum may be prepaid in whole or in part at
any time without penalty, provided the payment is at least equal to the
Contract Sum plus the City costs incurred to that date, plus a contingency
of ten percent (10%) of the sum of the Contract Sum plus City costs.
C. Late Charge. Agency agrees that if it fails to make any payment provided
for herein more than ten (10) days after the due date thereof, Agency
hereby agrees to pay to City a late charge equal to five percent (5%) of
any payment which is not made within ten (10) days after the due date
thereof, not as a penalty, but for the purpose of defraying the expenses
incident to handling such delinquent payment. Such late charge
represents the reasonable estimate of a fair average compensation for the
loss that may be sustained by City due to the failure of Agency to make
timely payments. Such late charge shall be paid without prejudice to the
right of City to collect any other amount provided to be paid or to declare a
default under this Agreement. Such late charge shall be payable not later
than thirty (30) days after the due date of the delinquent payment.
d. Acceleration of Obligation. Upon the failure to make payment due under
this Agreement as and when the same becomes due and payable
(whether by extension, acceleration or otherwise), or any breach of any
other promise or obligation in this Agreement or in any other instrument
now or hereafter securing the indebtedness evidenced hereby, then, and
in any of such events, City may, at its option, declare this Agreement and
the entire indebtedness hereby evidenced, including, without limitation, all
accrued interest, to be immediately due and payable and collectible then
or thereafter as City may elect, regardless of the date of maturity, and
notice of the exercise of said option is hereby expressly waived by
Agency.
e. Severability. The unenforceability or invalidity of any provision or
provisions of this Agreement as to any persons or circumstances shall not
render that provision or those provisions unenforceable or invalid as to
any other provisions or circumstances, and all provisions hereof, in all AA
CAA.Y?
other respects, shall remain valid and enforceable.
f. Modifications. Neither this Agreement nor any term hereof may be
waived, amended, discharged, modified, changed or terminated orally; nor
shall any waiver of any provision hereof be effective except by an
instrument in writing signed by Agency and City. No delay or omission on
the part of City in exercising any right hereunder shall operate as a waiver
of such right or of any other right under this Agreement.
g. No Waiver by City. No waiver of any breach, default or failure of condition
under the terms of this Agreement or the obligation secured thereby shall
be implied from any failure of the City to take, or any delay be implied from
any failure by the City in taking action with respect to such breach, default
or failure from any prior waiver of any similar or unrelated breach, default
or failure.
h. Governing Law. This Agreement has been executed and delivered by
Agency in the State of California and is to be governed and construed in
accordance with the laws thereof.
IN WITNESS WHEREOF, Agency has executed this Agreement as of the date
and year first above written.
"Agency"
COMMUNITY REDEVELOPMENT AGENCY
OF THE CITY OF PALM SPRINGS,
a California municipal corporation
By:
Chairman
ATTEST:
Assistant Secretary
APPROVED AS TO FORM:
Agency Counsel
Cad q
RESOLUTION NO.
OF THE COMMUNITY REDEVELOPMENT AGENCY OF THE
CITY OF PALM SPRINGS, CALIFORNIA,APPROVING THE
CONSTRUCTION OFSTREET IMPROVEMENTS ON RADIO
ROAD TO EFFECTUATE THE PURPOSES OF THE
REDEVELOPMENT PLAN IN THE HIGHLAND-GATEWAY
PROJECT AREA (MERGED PROJECT AREA#1)
- - - - - - - - - -- -- -
WHEREAS Radio Road is a General Plan street of the City of Palm Springs, but a portion
of Radio Road between Anza and McCarthy has never been paved; and
WHEREAS constructing improvements on a General Plan Street is a Class 1 exemption
from CEQA, per Section 15301 of the California Code; and
WHEREAS the City and Redevelopment Agency seek to encourage the improvement of
property, construction of new facilities, and retention of jobs within redevelopment areas;
and
WHEREAS this development will benefit the project area by serving as a catalyst for future
developments in the former Highland Gateway Redevelopment Project Area, and
WHEREAS the Agency desires to implement the Redevelopment Plan for the Highland-
Gateway Redevelopment Project Area, which §324 allows the Agency to construct public
improvements and enter into agreements with the City or other public agencies to facilitate
those improvements.
NOW THEREFORE, the Community Redevelopment Agency of the City of Palm Springs,
California, does hereby resolve the following:
SECTION 1. The construction of street improvements on Radio Road between McCarthy
and Anza, paid for as a capital project of the Community Redevelopment
Agency pursuant to §324 of the Redevelopment Plan, is hereby approved.
SECTION 2. It is appropriate for improvements to be constructed which will benefit the
community as a whole and implement the Redevelopment Plan for that
Project Area.
SECTION 3. The Reimbursement Agreement between the Community Redevelopment
Agency and the City of Palm Springs is hereby approved.
SECTION 4. The Executive Director or his designee are authorized to sign all necessary
documents in a form approved by the Agency Counsel.
ADOPTED this day of , 2000.
AYES:
NOES:
ABSENT:
ATTEST: COMMUNITY REDEVELOPMENT AGENCY
OF THE CITY OF PALM SPRINGS,
CALIFORNIA
By
Assistant Secretary Executive Director
REVIEWED AND APPROVED: L_