HomeMy WebLinkAbout2/2/2000 - STAFF REPORTS (10) DATE: February 2, 2000
TO: City Council
FROM: City Engineer
CONSTRUCTION CHANGE ORDER NO. 3 TO TAPUZ ENTERPRISES, INC. FOR MID-
VALLEY PARKWAY PHASE 1, LANDSCAPE IMPROVEMENTS
RECOMMENDATION:
That the City Council approve Construction Change Order No. 3 to Tapuz Enterprises,
Inc., for an increase of $45,424.22 for the Mid-Valley Parkway - Phase 1, Landscape
Improvements, City Project No. 95-38.
BACKGROUND:
On April 7, 1999, Council awarded Tapuz Enterprises, Inc. the contract for the Mid-
Valley Parkway - Phase 1, Landscape Improvements Project.
Bid Item A-There are 4 irrigation controllers proposed per plans and specifications in this
contract. Irrigation Controller A was to have its own electrical service pedestal. Irrigation
Controllers B and C were to have a combination of one electrical service pedestal.
Irrigation Controller D was to be tied into an existing electrical service pedestal. This
electrical work was not in the contractor's scope of work. Since there was no electricity
for the contractor to tie into, the City had to bid this portion out to the lowest bidder. The
City entered into a service agreement with ARB, Inc., to install 2 electrical service
pedestals, including conduit, pullboxes and transformer, per SCE approved plans and
specifications, for Irrigation Controllers A, B and C. The City contractor, Tapuz
Enterprises, Inc., per his construction schedule, installed all the proposed irrigation and
conduit for the irrigation controllers, including landscape, except palm trees and plants
around the palm trees in the median. After the power was available, the contractor still had
to wait until the City was cleared to do any work in the median island. In the meantime,
the contractor had to water the landscape by manual labor.
Total cost for this work is $19,889.50.
Items B & C - There is a court injunction currently in effect, restricting the contractor
from continuing with any work in the median island, from the west side of Dinah Shore
Bridge to Gene Autry Trail. All of the miscellaneous equipment items listed in Section B
for Items B and C in C.C.O. No. 3 are due to the court injunction delays. This includes
additional costs to maintain his construction yard, paying for his storage container as well
as office overhead for a one-month period.
Total cost for this work is $3,696.19.
Item D - The contractor, per plans and specifications, excavated to install 96 proposed
palm trees in the median island from thee west side of Dinah Shore Bridge to Gene Autry
Trail. Per the current court injunction and directive from the City, the contractor can't
install the proposed palm trees, per plans and specifications.
The cost to excavate and backfill these locations totals $3,185.16. i?A
040\
Change Order No. 3 Mid-Valley Parkway Phase 1 - Landscape Improvements
February 2, 2000
Page 2 of 3
Item E- The contractor had to re-trench 27 proposed palm tree locations in the west and
east sides of the Dinah Shore Bridge, including the median island in the Cathedral City
side of the project., due to the delays of the court injunction, restricting the contractor
from working. After several meetings with the City staff, restrictions from working in the
bridge planters and median island in the Cathedral City side were lifted and the contractor
completed this work per plans and specifications.
Three working days will be added to the contract.
Total cost for this work is $4,913.24.
Item F - Per plans and specifications, the existing electrical service pedestal was to be
within 10 ft. of the proposed Irrigation Controller D. The contractor found an existing
electrical service pedestal approximately 150 ft. north of the location in which the plans
call it to be. This cost, which is listed in Section B, Item F, includes preliminary
investigation to determine if an existing conduit could be used and install conductors from
the actual location of the existing electrical pedestal for the necessary tie-in to the
proposed tree lighting. The tie-in work is part of the contract and no additional cost will
be added .
Two working days will be added to the contract.
Total cost for this work is $3,600.00.
Item G - Per plans and specifications, the existing electrical service pedestal was to be
within 10 ft. of the proposed Irrigation Controller D. The contractor found an existing
electrical service pedestal approximately 150 ft. north of the location in which the plans
call it to be. This cost, which is listed in Section B, Item G, includes preliminary
investigation to determine if an existing conduit could be used, and providing and
installing the existing conduit from the actual location of the existing pedestal for the
necessary tie-in to the proposed irrigation. The tie-in work is part of the contract and no
additional cost will be added .
One working day will be added to the contract.
Total cost for this work is $1,200.00.
Item H - At the recommendation of the Director of Facilities, install tree staling for the
180, 15 gal. trees in the median island between west side of Dinah Shore Bridge and Gene
Autry Trail. These trees have flourished enough to necessitate tree staking, 2 wood stakes
with 4 ties each to control the growth alignment.
Four working days will be added to the contract.
Total cost for this work is $9,000.00
In addition to the ten working days added to the contract for the extra work above, sixty-
three working days are added because the contractor was not permitted to work due to the
court injunction.
The net increase for this change order totals $45,424.22
Change Order No. 3, Mid-Valley Parkway Phase 1 - Landscape Improvements
February 2, 2000
Page 3 of 3
Funds are available in account number 134-4497-50113 (Mid-Valley Pkwy Ph 1)
and reimbursement from Martin Communications.
Ifta
DAVID J. BARAKIAN
City Engineer
APPROVED:
le
City Manager
ATTACHMENTS:
1. Minute Order
2. Change Order No.3
3, Itemization of Martin Communications Respon�rbil,ty
'� �3
MINUTE ORDER NO.
APPROVING CONSTRUCTION CHANGE ORDER
NO. 3 TO TAPUZ ENTERPRISES, INC. FOR AN
INCREASE OF $45,424.22 FOR THE MID-VALLEY
PARKWAY - PHASE 1, LANDSCAPE IMPROVEMENTS,
CITY PROJECT NO. 95-38.
I HEREBY CERTIFY that this Minute Order approving Construction Change Order No.
3 to Tapuz Enterprises, Inc. for an increase of$45,424.22 for the Mid-Valley Parkway,
Phase 1, Landscape Improvements, City Project No. 95-38 adopted by the City Council
of the City of Palm Springs, California, in a meeting thereof held on the 2nd day of
February, 2000.
PATRICIA A. SANDERS
City Clerk