HomeMy WebLinkAbout6213 - MINUTE ORDERS - 7/29/1998 MINUTE ORDER NO. 6213
aAPPROVING CONSTRUCTION CHANGE
ORDER NO. 13 TO GRANITE
CONSTRUCTION COMPANY BY
INCREASING THE CONTRACT BY
$278,779.74, AND EXTENDING THE
CONTRACT DURATION BY 9 DAYS
AND AN ADDITIONAL EXTENSION TO
THE CONTRACT COMPLETION DATE
FROM MAY 2, 1998 UNTIL JULY 15,
1998 (PUNCH LIST WAS COMPLETED)
TO OFFSET THE ACCRUED
LIQUIDATED DAMAGES, FOR THE
MID-VALLEY PARKWAY, CITY
PROJECT NO. 94-19.
------------------
I HEREBY CERTIFY that this Minute Order, approving Construction Change Order
No. 13 to Granite Construction Company by increasing the contract by $278,779.74,
and extending the contract duration by 9 days and an additional extension to the
contract completion date from May 2, 1998 to July 15, 1998 (Punch List was
Completed) to offset the accrued liquidated damages, for the Mid-Valley Parkway,
City Project No. 94-19, was adopted by the City Council of the City of Palm
Springs, California, in a meeting thereof held on the 29th day of July, 1998.
JUDITH SUMICH
City Clerk
a