HomeMy WebLinkAbout11/17/1999 - STAFF REPORTS (19) DATE: November 17, 1999 TO: City Council FROM: City Engineer CONSTRUCTION CHANGE ORDER NO. 1 TO CONTRERAS CONSTRUCTION CO. RECOMMENDATION: That the City Council approve Construction Change Order No.1 to Contreras Construction Co., for an increase of$24,967.06 for Additive Bid Schedule H and 7 sack concrete for the schedules B &C bus pads, on the 1998/99 Citywide Sidewalk Construction project, City project No. 98-18. An additional 5 working days shall be granted for this work. BACKGROUND: On September 15, 1999, City Council of the City of palm Springs awarded Contreras Construction Co. the contract for schedules A through F for the 1998/99 Citywide Sidewalk Construction project. The bid consisted of eight bid schedules (A through H), the first six of which (A through F) are funded from the SB 821 program. Due to lack of funds, the final 2 schedules (G and H) were not awarded. Bid results for the recently awarded 1998/99 Crack6lling program were significantly below the budgeted amount, providing an opportunity to construct Bid Schedule H since both projects are Measure A funded. Schedule H consists of sidewalk and curb along the west side of Avenida Caballeros in the vicinity of Raymond Cree Middle School. Staff feels this sidewalk would be of great benefit to students who walk to school. Schedule H was part of the original bid and the contractor has agreed to accept his bid prices as payment for this Change Order. An additional 5 working days is provided for in the specifications in the event Schedule H is constructed. In addition, 7 sack concrete in lieu of 6 sack, as called for in the project specifications, will result in higher strength and allow the bus pads to be open to traffic in 4 days rather than 7. Sufficient funds are available in account number 134-4498-50157 (Local Measure A Sidewalk Safety Grant). ,e6 DAVID J. 13ARAKM City Engineer APPROVED: l ) City Manager iu DOOMED ATTACHMENTS: 1. Minute Order 2. Contreras Construction C.C.O. No.1 17ft CITY OF PALM SPRINGS 170*4%, CONTRACT CHANGE ORDER To: Contreras Construction Company Data. November 4, 1999 44A17 Golf Center Parkway,Suite 10 Project No.: C.P.98-18 P.O.Box in$ Project Name: 1998199 Citywide Sidewalk Indio,Ca. 92201 Construction Project Change Order No.: One(1) Attu: Henry Contreras Contract Purchase No.: 909165 Account Number(s): 4491-50157, 4499-50157 Agr.x 4141 M.O. M 6488 Res. # A. CHANGES IN WORK: Increase to Contract Items: Contract Additive Bid Schedule H per project plans and specifications Item Description No. 1 Initial Mobilization 2 Traffic Control 3 Clearing and Grubbing 4 Remove A.C.Pavement 5 Remove P.C.C.Impmvements 6 Construct Sidewalk 7 Construct Type'B-Access Ramp 8 Construct Curb Regan and Spandrel 9 Construct Type A2.6 Curb 10 Construct Type Al-12 Curb 11 Construct 3'A.C.Pavement 12 Construct 6"Crushed Miscellanea:,Base 13 Relocate Traffic Sign 14 Relocate Mailbox 15 Remove Tree Increase to Contract Items(Now): A. 7 Sack Concrete in lieu of 6 sack for the bus pads on Schedules B&C(Ramon Rd.) B. CHANGES IN CONTRACT COST, Increase to Contract Items: Additive Bid Schedule H Item Description No. 1 Initial Mobilization Lnmp Sum $ 1,000.00 2 Traffic Control Lump Sean $ 1,000.00 3 Clearing and Grubbing Lump Sum $ 3,000.00 4 Remove A.C. Pavement 400 SF®$1.50 $ 600.00 5 Remove P.C.C.Improvements 250 SF®$2.00 $ 500.00 6 Construct Sidewalk 2,025 SF®$3.00 $ 6,075.00 7 Construct Type B'Access Rain 3 Each®$1,200.00 $ 3,600.00 8 Construct Curb Return and Spandrel 250 SF®$8.00 $ 2,000.00 9 Construct Type A2-6 Curb 132 IF®$15.00 $ 1,980.00 10 Construct Type Al-12 Club 42IF®$15.00 $ 630.00 11 Construct 3'A.C.Pavement 725 SF 0$2.50 $ 1,812.50 12 Construct 6' Crashed Miscellaneous Base 725 SP®$2.00 $ 1,450.00 13 Relocate Traffic Sign 4 Each®$150.00 $ 600.00 14 Relocate Mailbox 1 Each® 150.00 $ 150.00 IS Remove TWO 2 Bach®$150.00 $ 3W.00 Sub-Total $ 24,697.50 Increase to Contract Items(New): A. 7 Sack Concrete in lien of 6 sack Lump Sum $ 269.56 TOTAL NET CHANGE ORDER = $ 24,967.06 NOTE:No additional markup will be added to any items in this Contract Change Order. All cost per each item are final. November 4, 1999 C.P. 98-181998/99 Citywide Sidewalk Construction project Change Order No. 1 Page 2 of 2 C.REASON FOR CHANGE: This bid consisted of eight(8)bid schedules(A through H), the first six of which(a through F)am funded fion the SB 821 program.Due to lack of fiords,the final two bid schedules(G and H)were not awarded.Bid results fa the recently awarded 1998/99 Crackfilling program were significantly below the budgeted amount, providing an opportunity to construct Additive Bid Schedule H since both projects we Measure A fimded. Schedule consists of sidewalks and curb along the west side of Avenida Caballeros in the vicinity ofRaymond am Middle School. Staff feels this sidewalk would be of great benefit to students who walk to school. Schedule H was Pad of the original bid and the contractor has agreed to accept his bid prices as payment for this Change Order. Additional 5 working days will be added to the contract for the above work,per Specifications. Per the recommendation of the Contractor and the approval of the City Engineer,to change tha ate mix design from 6 sack concrete to7 sack concrafe,i1musmgI%C.C., for the 2 proposed bus pads onRamon Road.Bydoing this,it will add strength to concrete and also tainimiw traffic control(lane closure)from 7 days to 4 days. D. SOURCE OF FUNDS: Local Measure A-Sidewalk Safety Grant Account Number: 134 -4498 - 50157 = $ 24,967.06 Summary of Coats Contract Time Original Contract Amount: $ 74,070.00 Original Completion Data: Jan. 3.2000 This Change Order: $ 24,967.06 Days Added for this C.C.O.: 5 previous Change Order(s): $ 0.00 Previous Days Added: 0 Revised Contract Amount: $ 99,037.06 Revised Completion Data Jan. 10,2000 I have received a copy of this Change Order and the City Approval: above AGREED PRIGS am acceptable to the contractor. Submitted By Date Engineering Field Supervisor By Approved By.Data Tide City Engineer Date Approved by Date City Manager Distribution: Original Conformed Copies Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Field Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) purchasing Agent (1) 170 MINUTE ORDER NO. APPROVING CONSTRUCTION CHANGE ORDER NO. 1 TO CONTRERAS CONSTRUCTION CO., FOR AN INCREASE OF $24,967.06, FOR THE ADDITIVE SCHEDULE H AND 7 SACK CONCREPE ON SCHEDULES B &C BUS PADS, ON THE 1998/99 CITYWIDE SIDEWALK CONSTRUCTION, CITY PROJECT NO. 98-18 I HEREBY CERTIFY that this Minute Order approving Construction Change Order No. 1 to Contreras Construction Co., for an increase of$24,967.06, for the Additive Schedule H and 7 sack concrete on schedules B& C bus pads, on the 1998/99 Citywide Sidewalk Construction, City Project No. 98-18, was approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 17th day of November 1999. PATRICIA A. SANDERS City Clerk 176