DATE: September 15, 1999
TO: City Council
FROM: Landside & Security Supervisor and Deputy Di�. 'of Aviation - Admin. via
Director of Aviation
CHANGE ORDER FOR THE TAXI HOLDING FACILITY PROJECT NO. 9"7
RECOMMENDATION:
That the City Council approve Change Order No. 1 with James E. Simon Co.,for
site certification of the taxi holding facility at the Palm Springs International Airport
for an amount not-to-exceed $17,150.
BACKGROUND:
The taxi/bus holding building project was divided into two parts;the vehicle staging
and taxi paddng lot(including rough grading), and the actual building construction. I
The separation of the two projects occurred because sufficient funding was not
available for the entire project upon inception of the initial design. In separating
these two projects,the full over excavation and site certification of the building pad
was omitted from the scope of work. ' Change Order No.1 must now be
incorporated into the building contract in order to proceed with the project.
Funds are available in account no. 415-6400-56020; no general fund monies are
necessary for this project.
i
A minute order is attached for City Council consideration.
Bill Weaver any
Landside &Security Supervisor Deputf DI -A min
t
, n _ I
APPROVED:
Jeri L. Riddle City Manager
Director of Aviation
Attachments: 1. Change Order
2. Minute Order rA
PPROVED
ECUNFII
• I '
11� �-
CITY OF PALM SPRINGS
PALM SPRINGS INTERNATIONAL AIRPORT
CONSTRUCTION CHANGE ORDER
To. James E. Simon Co. Date: September 15, 1999
P.O. Box 10990 Project No. City Project 99417
Indio, CA 92202 Project Name: TsA Holding Facility
Change OrderAo. 1
Contract Purchase No. 906252
Attn: ATTN: Roger Wallentine Account No.416-6400-56020
Description of Chance to be Made:
Related to the certification and over excavation of the building pad.
1. Over excavate building site per soils report recommendations
2. Soil testing and reports
3. Civil engineer surveying and dad certification
4. Construction water
5. 1 Contour grading and cleanup of site
6. Relocate existing severer dean-out
7. No cost permits are included In quote
8. Site pad srW surrounding area will be put back to finished grade
Sunk of Costmme
Original Contract Price $396,863.00
Total of all Previous Change Orders $0
Total of this Change Order $ 17,150.00
Total Contract Price $414,013.00
This Change Order increases the contract time by&worldng days.
I have received a copy of this Change Order City Approval:
and the above AGREED PRICES arse acceptable Submitted by.
to the actor. D of Aviation
r
By Date:
Title: Approved by:
City manew
Date: Data:
Distribution:
Oginal Conformed Copies Conformed-File Coot
Airport (1) Purchasing Agent (1)
City Clerk (1)
Finanoe (1)
James E. Simon Co. (1)
i
i
• I
1 -
MINUTE ORDER NO. 6484
APPROVING CHANGE ORDER NO.• 1
WITH JAMES E. SIMON CO., FOR SITE
CERTIFICATION OF THE TAXI HOLDING
FACILITY AT THE PALM SPRINGS
INTERNATIONAL AIRPORT IN AN
AMOUNT NOT TO EXCEED$17,150.
1 HEREBY CERTIFY that this Minute Order, approving Change Order No. 1 with
James E. Simon Co., for site certification of the taxi holding facility at the Patin Springs
International Airport in an amount not to exceed $17,150, was adopted by the City
Council of the City of Patin Springs, Califonda, in a meeting thereof held on the 15th
day of September, 1999.
ATRICIA A. SANDERS
City Clerk