Loading...
HomeMy WebLinkAbout5/3/2000 - STAFF REPORTS (4) Date: May 3, 2000 To: City Council From: City Engineer CONSTRUCTION CHANGE ORDER NO. 1 TO 4-CON ENGINEERING, INC. RECOMMENDATION: That the City Council approve Construction Change Order No. 1 to 4-Con Engineering, Inc., in the amount of$26,435.20 for a total contract cost of $212,898.20,for Indian Avenue Overhead Seismic Retrofit project, City Project No. 96-43. BACKGROUND: On October 6, 1999, City Council awarded 4-Con Engineering, Inc.the contract for Indian Ave. Overhead Seismic Retrofit. The project consisted of Me construction of reinforced concrete, manufacturing and installation of structural steel, blast cleaning and painting , in order to seismically retrofit Indian Ave. Bridge No. 56C-0026 which crosses over the Union Pacific Railroad now the Palm Springs Train Station. After construction had begun,the contractor was notified by the design engineer of Moffatt&Nichol Engineers, that the structural steel members to be manufactured for the project were considered to be'main members'. Due to this designation, it was required that a significantly more stringent standard of welding,testing and repair of these members be followed. This designation and subsequent use of the higher standards resulted in additional costs being incurred by the contractor. In addition to these are costs associated with additional spot blasting, cleaning and undercoat painting due to actual quantifies exceeding the original estimate. This change order includes reimbursement of costs to the contractor due to additional requirements dictated by the design engineers, and payment for pertinent additional materials. The total adjustment to the agreement for these items is$28,436.20. Cal Trans has agreed to reimburse the City for all costs associated with this change order. Sufficient funds to cover this change order are available in account number 4491-50171 Indian Avenue Overhead Seismic Retro J"4A�— David J. n City Engineer APPROVED: e City Manager ATTACHMENTS: 1. Minute Order 2. Construction Change Order No. 1 CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: 4 Can Engineering, Inc. Date: March 20, 2000 P.O. Box 3448 Project No. 96-43 Ranch Cucamonga, CA 91729 Project Name: Indian Ave. Overhead Seismic Retrofit Change Order No. One (1) Attn: Dieco DeAndrade Contract Purchase No. 909141 Account Number: 4491-50171 Agr.# 4135 M.O.# 6470 Res. # A. CHANGES IN WORK: INCREASE TO CONTRACT QUANTITIES Bid Schedule item No.: 8. Spot Blast, Clean and Paint Undercoat ADDITIONAL ITEMS A. Girder Bracket Welding, Testing, Inspection and Repair B. Transverse Tie Plate Welding, Testing, Inspection and Repair B. CHANGES IN COST: INCREASE TO CONTRACT QUANTITIES Bid Schedule Item No.: 8. Spot Blast, Clean and Paint Undercoat 64.74 SF 0 $50.00/SF $3,237.00 ADDITIONAL ITEMS A. Girder Bracket Welding,Testing, Inspection and Repair LUMP SUM $15,031.68 B. Transverse Tie Plate Welding, Testing, Inspection and Repair LUMP SUM $8,167.62 TOTAL NET CHANGE ORDER AMOUNT • $26.436.20 C. REASONS FOR CUMOES: Actual, measured quantities for bid schedule, item No. 8 (Spot Blast Clean and Paint Undercoat) were in excess of the estimated quantity of 192 SF. Actual quantity was 256.74 SF. These quantities were verified by the design engineer. Transverse Tie Plates and Girder Brackets were designated as Main Members by the design engineer after the start of construction. This designation required a significantly higher standard of welding, testing, inspection and repair during the manufacturing process. 21 working days will be added to the contract for the additional work involved with girder brackets and Tie plates. • Note: No additional mark ups will be added to any Item on this Change Order.AN cost per each hem are fatal. /d1%;1 Construction Change Order No. 1 Page 2 D. SOURCEQF FUNDS; Funds are available in Account No. 1-50171 Indian Ave. Overhead Seismic Retrofit. Original Contract Amount: 4 186AM00 Original Completion Data: January 21,2000 This Change Order. 4 28AW.2D Days Added for this C.C.O.: -21- Previous Change Order(s): 4 0.00 Previous Days Added: -0- Revised Contract Amount: 4 212,888.20 Revised Completion Data: February 23, 2000 1 have received a copy of this Change City Approval: Order and the above AGREED PRICES are acceptable to the contractor. Submitted by: Date Engineering Field Supervisor BY Approved by: Data City Engineer Date Approved by: Dats City Manager Distribution: Conformed-File Copy Engineering (1) Engineering File (1) Finance (1) Engineering Reid Inspector (1) Contractor (1) Engineering Field Supervisor (1) City Clerk (1) Purchasing Agent (1) MINUTE ORDER NO. APPROVING CONSTRUCTION CHANGE ORDER NO. 1 TO 4-CON ENGINEERING, INC., IN THE AMOUNT OF$26,436.20 FOR A TOTAL CONTRACT COST OF $212,898,20, FOR INDIAN AVENUE OVERHEAD SEISMIC RETROFIT PROJECT, CITY PROJECT NO. 96-43 I HEREBY CERTIFY that this Minute Order approving Construction Change Order No. 1 to 4 Con Engineering, Inc., In the amount of$26,436.20 for Indian Avenue Overhead Seismic Retrofit project, City Project No. 96-43,was approved by the City Council of the City of Palm Springs, California, in a meeting thereof held on the 19th day of April 2000. PATRICIA A. SANDERS City Clerk