HomeMy WebLinkAboutItem 3A - Public Comment - OswithLandTrust
1
July 18, 2025
Palm Springs City Council
City of Palm Springs
3200 E Tahquitz Canyon Way
Palm Springs, CA 92262
Subject: Consideration of Environmentally Sensitive Alternative at South Palm Canyon Drive
& Bogert Trail low crossing bridge
Dear Mayor and Members of the City Council,
On behalf of Oswit Land Trust (OLT), we appreciate the opportunity to submit this letter
regarding the City’s proposed flood project at the low water crossing at South Palm Canyon
Drive and Bogert Trail.
Oswit hired a civil water resources engineer with 35-year experience to evaluate, conduct
engineering modeling and determine if there was an alternative that would achieve the same
public safety goals but reduce the habitat destruction for the endangered bighorn sheep and
other wildlife. We were successful in this endeavor.
We respectfully submit an environmentally sensitive alternative. We have attached the 40-page
full engineering analysis with copies of all the modeling and studies that were performed using
the same methods used by county flood controls, corps of engineers, the state and the federal
governments.
This environmentally sensitive alternative has been shown to achieve better flood control
performance and preserve 2.5 acres of sensitive pristine desert habitat (including eliminating
the need for streambed alteration), which is critical for the federally endangered Peninsular
bighorn sheep—a species increasingly threatened by habitat loss, fragmentation, and human
2
disturbance. Photo evidence (attached) confirms regular sightings of sheep in the flat wash area
of Oswit Canyon.
Overview of City’s Proposal
• Low-water crossing bridge system consisting of a 5-barrel box culvert.
• New engineered 2.5-acre channel west of the culvert.
• Rock-lining of channel for erosion control.
• Based on a 2001 Tettemer hydrograph with a 2,955 cfs peak flow estimated using
conservative methods.
*The current city design does not fully eliminate flood risk at the intersection as there will
continue to be water that will enter the roadway south of the bridge system and flow north
toward the Bogert Trail intersection.
Oswit Land Trust’s AlternaKve
• Retains the City’s bridge / culvert design (majority of the current design).
• Eliminates the engineered channel, preserving the natural wash and bighorn habitat.
• Introduces a roughly 2.5-foot-high floodwall along the sidewalk at South Palm Canyon
Drive to prevent overtopping (see attached rendering).
o Two options were analyzed: a short floodwall to the City/Oswit property line
and a long floodwall to match road grade. We support the short wall.
• Incorporates erosion control measures (e.g., riprap) at culvert inlet/outlet (which is
required in city design as well).
• Hydrologic modeling using HEC-RAS 2D shows this alternative performs at least as well
as and likely outperforms the City’s proposal. See the water levels in the chart below.
3
Key Findings
• Under both a 100-year and a more intense design storm, OLT's alternatives reduce
water depth at the Bogert Trail intersection at least as well as and likely better than
the Channel system.
• No additional erosion risk compared to current conditions.
• Preserves natural wash and habitat for endangered wildlife.
Responses to Staff Concerns
1. Performance and Reliability
City staff was concerned that the velocity (speed of the water), would not be handled
with the alternative design. However, velocities remain within safe thresholds on both
the city design and the alternative design. The velocity profiles at most locations are not
greater in the alternative design compared to the city design. Riprap can control any
erosion at the culvert inlet where velocities may increase. Reminder: this is not a river;
it's a design handling a 100-year flood, which is the storm that has a 1% (1 in 100)
probability of happening in any year.
2. Land Ownership and Permitting
The recommended short-wall design lies entirely on City/OLT property, ending at the
City’s southern easement boundary—no tribal land is affected, simplifying approvals. In
4
addition, the flood wall would only be constructed adjacent to the sidewalk within a
typical Right of Way easement. Any embankment to the west of the flood wall required
to stabilize the floodwall would likely not extend significantly westward depending on
how it was designed.
3. Timeline and Funding Risks
Additional modeling and detailed design to have the addition of the wall ready for bid
would take no more than one to two months. The bulk of the city's original design is
remaining the same. The city can be working on this alternative while finishing its
environmental review updates. In fact, including this alternative in the environmental
review could benefit the environmental review process.
4. Uncertain Costs
Many costs (culvert, road, inlet/outlet) remain unchanged. Replacing a 2.5-acre channel
with a narrow wall and embankment along the sidewalk has the potential to be cost-
neutral or cost-saving. Concerns over increased cost are premature and speculative
without an estimate. City staff had stated the cost of just the rock in the proposed
channel would be nearly 1.5 million dollars. This alternative eliminates the need for
such rock and eliminates the need to grade, build a maintenance road, etc. It is quite
likely that building a 2.5 ft wall along the sidewalk would cost less than building a
channel lined with rip rap.
5. Maintenance Access
The maintenance road the city staff is referring to would only be built if a channel was
constructed. Without a channel there is no need to drive into the canyon and no need
for a road.
6. Land Area and Habitat Impact
The floodwall’s width is approximately 1 foot. The width of the western embankment
along the floodwall depends on how it is designed and keyed into the existing
topography. An earthen embankment might be 5 feet in width to provide a 2:1 slope
from the top of the flood wall to the elevation of the sidewalk. It would extend
westward as necessary to meet the existing land elevation, which may be another few
feet depending on the topography. Another embankment option is the application of a
5
rock-filled gabion system, which would be narrower than an earthen embankment,
possibly on the order of another 2 to 3 feet from the sidewalk, resulting in an impacted
area no more than 4 feet wide from the sidewalk. The entire floodwall embankment
system would be located within areas adjacent to the roadway that are already
degraded by road runoff. Unlike the City’s plan, this alternative avoids destroying
pristine habitat used by bighorn sheep and other desert species.
7. Environmental Clearance
Preliminary analysis suggests environmental impacts will be less than the original
design, supporting a streamlined clearance process. In addition, we encourage the city
to gather the opinions of US Fish and Wildlife Services, California Fish and Wildlife,
Bighorn Institute and others regarding which design they support to have the least
impact on endangered bighorn sheep and other wildlife.
The city staff report mentions that this is the fifth design that has been submitted by Oswit
Land Trust. Just to clarify, this is the only alternative that we have fully modeled and evaluated.
This was an incredibly expensive endeavor for a non-profit to take on but we were committed
to finding a solution that addresses both public safety and protection of critical habitat. Almost
5 years ago we submitted ideas to the city, but those ideas were never given the amount of
evaluation/modeling that this alternative has been given.
Other than this current design (which was originally developed to support the construction of
hundreds of houses in the canyon [Proposed Eagle Canyon Development]), we are unaware of
any other alternative flood designs the city has considered. With the change of use of the
canyon, we would expect the city would look at alternatives.
Conclusion
Oswit Land Trust's environmentally sensitive alternative provides the same or more effective
flood control, protects sensitive habitat and is potentially cost-neutral or even a less
expensive solution to the City’s current/original flood design. It not only meets engineering
6
and public safety goals but also avoids irreparable harm to the habitat of the endangered
Peninsular bighorn sheep—a species often observed in this exact floodplain. (See attached
photo.)
Palm Springs has a unique opportunity to implement a solution that reflects both sound
engineering and environmental stewardship. We urge the Council to support this alternative
and allow it to proceed toward implementation. Engineering and modeling can be completed
with the alternative ready to bid within 30 to 60 days. We are happy to supply the city with all
studies and modeling that were completed by our engineer. In addition, the city can certainly
work with our engineer to move things along even faster.
Thank you for your kind attention to our concerns.
With regard,
Jane Garrison, Executive Director
Attachments:
Photo: Peninsular bighorn sheep on Oswit Canyon floodplain
Photo of potential flood wall along sidewalk
Engineering analysis
Bio of Richard Haimann, P.E., BCWRE, QSD, QISPcc: USFWS
7
cc.
Palm Springs Planning Services
planning@palmspringsca.gov
Mayor Ron deHarte, City of Palm Springs
ron.deharte@palmspringsca.gov
Naomi Soto, City of Palm Springs
Naomi.Soto@palmspringsca.gov
Grace Elena Garner, City of Palm Springs
Grace.Garner@palmspringsca.gov
Jeffrey Bernstein, City of Palm Springs
Jeffrey.Bernstein@palmspringsca.gov
ScoC SDles, City of Palm Springs
ScoC.SDles@palmspringsca.gov
David H. Ready, City of Palm Springs
David.Ready@palmspringsca.gov
Alyssa Chavez, City of Palm Springs
alyssa.chavez@palmspringsca.gov
Nora Ayala, City of Palm Springs
Nora.Ayala@palmspringsca.gov
Peter SaDn, Coachella Valley ConservaDon Commission
psaDn@cvag.org
8
Kathleen Brundige, Coachella Valley ConservaDon Commission
kbrundige@cvag.org
Jeff Villepique, California Department of Fish and Wildlife
jeff.villepique@wildlife.ca.gov
Chris Fust, California Department of Fish and Wildlife
chris.fust@wildlife.ca.gov
Heather Brashear, California Department of Fish and Wildlife
Heather.Brashear@wildlife.ca.gov
Jacob Skaggs, California Department of Fish and Wildlife
Jacob.Skaggs@wildlife.ca.gov
Lory Salazar-Velasquez, U.S. Fish and Wildlife Service
lory_salazar-velasquez@fws.gov
Noelle A Ronan, U.S. Fish and Wildlife Service
noelle_ronan@fws.gov
Mary Beth Woulfe, U.S. Fish and Wildlife Service
marybeth_woulfe@fws.gov