Palm Springs Fulfillment Center
Case # 3.4361 MDP
January 23, 2025
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
History of Project
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
Request: Planning Commission approved:
•Major Development Permit (Case 3.4361)
•Final Environmental Impact Report (FEIR)
•Statement of Overriding Considerations
•Mitigation Monitoring and Reporting Program
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
Site Aerial
Zoning – M-2 allowing by
right warehouse/fulfillment
center uses
General Plan - Industrial
Zoning Map
Red Box permits buildings over
40 feet tall per PSZC
City Council adopted Ordinance
# 2056 amending the PSZC
relative to development
standards for the E -1 and M-1
zones to allow for
warehouses/fulfillment uses
Proposal – Warehouse/Fulfillment Center
Parcel = 38 - Acres
Building = 739,360-Square Feet
•727,360-Square Feet – Warehouse
•12,000-Square Feet – Office Space
Setbacks = Vary from 62 feet (west), 152 (east) to 312 feet (side)
Building Height = 50 feet
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
Site Plan
Building Elevation
Simulation
From I-10
Simulation
Looking South
from Indian
Canyon Drive
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
Potential Economic Impact
Impact Category Warehouse Fulfillment Center
Construction Jobs 553 jobs/year over
18 months Same as Warehouse
Permits and Fees Up to $6,625,000
Permanent Jobs 819 Jobs
Property Tax - Local Share $153,195 Same as Warehouse
Local Sales Tax Revenue
(Construction)$1,502,563 Same as Warehouse
Local Sales Tax Revenue
(Operations)$1,532,323 $7,661,618
Induced Economic Impact
(Construction)$130,500,000 Same as Warehouse
Induced Economic Impact
(Operations)$76,555,800 $109,504,800
Bases of Appeal :
•Disagree with EIR determination on Green House Gas
Emissions (GHG)
•Challenge the decision of the Planning Commission
•Decision should be made by City Council
DEPARTMENT O F
P LA NN IN G
S E R V I C E S
Staff Recommendation:
Deny appeal and uphold the Planning Commission decision to:
•Certify a Final Environmental Impact Report
•Adopt the Statement of Overriding Considerations
•Adopt the Mitigation Monitoring Program
•Approval a Major Development Permit