Palm Springs Fulfillment CenterCase # 3.4361 MDP
November 13, 2024
DEPARTMENT OF
PLANNING
SERVICES
Request:
•Major Development Permit (Case 3.4361)
•Certify a Final Environmental Impact Report (FEIR)
•Adoption of Statement of Overriding Considerations
•Adopt the Mitigation Monitoring and Reporting Program
DEPARTMENT OF
PLANNING
SERVICES
Zoning Map
Red Box permits buildings over
40 feet tall per PSZC
City Council adopted Ordinance
# 2056 amending the PSZC
relative to development
standards for the E-1 and M-1
zones to allow for
warehouses/fulfillment uses
Site Aerial
Zoning – M-2 allowing by
right warehouse/fulfillment
center uses
General Plan - Industrial
Proposal – Warehouse/Fulfillment Center
Parcel = 38 - Acres
Building = 739,360-Square Feet
•727,360-Square Feet – Warehouse
•12,000-Square Feet – Office SpaceSetbacks = Vary from 62 feet (west), 152 (east) to 312 feet (side)Building Height = 50 feet
DEPARTMENT OF
PLANNING
SERVICES
Site Plan
Site Circulation
Building Prespective
Materials
Existing conditions at 19th Avenue
Existing conditions at north end of project
Site Perspective Looking South
Site Perspective Looking Southwest
Site Perspective Looking North from I-10
Environmental Impact Report
Less than Significant
•Aesthetics, Air Quality, Energy, Hazardous Materials, Hydrology, Water Quality, Noise, Public Services, Cultural Resources, Utilities Less than Significant with Mitigation Measures
•Biological Resources, Cultural Resources, Geology – SoilsSignificant and Unavoidable Impacts
•Greenhouse Gas Emissions and Transportation
DEPARTMENT OF
PLANNING
SERVICES
Statement of Overriding Considerations
The Planning Commission determines that the specific benefits of the project outweigh unavoidable adverse impacts based upon the following:
1.Land Use Benefits: Project consistent with General Plan and Zoning, site location appropriate, project provides 718 permanent jobs, increase in e-commerce.2.Meet Market Demands for Industrial Space: Project meets growing need for industrial space, supports goods movement industry, improve lead times for delivery to consumers.3.Economic and Fiscal Benefits: Project encourages economic growth and diversity within the City, increase annual property tax revenue through collection of taxes, licenses, and fees, introduction of a new industry to the City and broaden the economic base.4.Public Infrastructure Benefits: Project would improve public infrastructure, roads, water, sewer lines, pay substantial development impact fees.
•Adopt Statement of Overriding Considerations
DEPARTMENT OF
PLANNING
SERVICES
Recommendation – CEQA
•Certify Final Environmental Impact Report (EIR)
•Adopt Statement of Overriding Considerations
•Adopt Mitigation Monitoring Program
DEPARTMENT OF
PLANNING
SERVICES
Recommendation – Development Permit
•Approve subject to conditions:
•Findings:1.By-Right use in M-2 zone and Industrial GP2.Use is consistent with the M-2 zone3.Project meets development standards4.Building height and massing consistent 5.Setbacks consistent with development standards6.Adequate access to adjacent streets7.On-site circulation can accommodate anticipated use8.Landscaping and open space conforming to development standards9.Public Infrastructure adequate to serve project10.Certify CEQA EIR and Statement of Overriding Considerations11.No adverse effects on public welfare, health and safety