HomeMy WebLinkAbout11-15-23 - Airport Commission Minutes Page 1 of 7
AIRPORT COMMISSION
ACTION SUMMARY MINUTES OF REGULAR ADJOURNED MEETING
Wednesday, November 15, 2023 – 5:30 P.M.
_____________________________________________________________________
1. CALL TO ORDER:
Vice Chairman Corcoran called the Airport Commission Meeting to order at 5:30 P.M.
and Vice Chairman Corcoran asked Commissioner Park to lead the Pledge of
Allegiance. The meeting was held in-person and via videoconference.
2. POSTING OF THE AGENDA: Posted on November 9, 2023.
3. ROLL CALL:
Commissioners Present:
Dave Banks (Palm Springs) Margaret Park (Riverside County)
Robert Berriman (Indian Wells) Jan Pye (Desert Hot Springs)
Daniel Caldwell (Palm Springs) M Guillermo Suero (Palm Springs)
Kevin Corcoran (Palm Springs) - Vice Chair Rick Wise (Indio)
David Feltman (Palm Springs) Kevin Wiseman (Palm Desert)
J Craig Fong (Palm Springs) Keith Young (Rancho Mirage)
Tracy Martin (Palm Springs)
Commissioners Absent: Aftab Dada (Palm Springs), Denise Delgado (Coachella),
Todd Burke (Palm Springs), Kathleen Hughes (La Quinta), Tony Michaelis (Cathedral
City)
Staff Present:
Jeremy Keating, Assistant Airport Director
Victoria Carpenter, Airport Administration Manager
Jacob Colella, Airport Maintenance Superintendant
Geremy Holm, City Attorney
Christina Brown, Executive Program Administrator
Others Present:
Ryan Evers, AECOM
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 2 of 7
4. ACCEPTANCE OF THE AGENDA:
ACTION: Accept the Agenda as presented. Moved by Commissioner Wise,
seconded by Commissioner Pye, and unanimously approved noting the
absence of Commissioners Burke, Dada, Delgado, Hughes and Michaelis.
5. PUBLIC COMMENTS: None
6. APPROVAL OF THE MINUTES:
ACTION: Approve the minutes of the Airport Commission Meeting of June 21, 2023.
Moved by Commissioner Pye, seconded by Commissioner Wise and approved
by the following roll call vote: 8 Yes; 5 Abstain; and noting the absence of
Commissioners Burke, Dada, Delgado, Hughes and Michaelis.
7. DISCUSSION AND ACTION ITEMS:
7.A In-Line Baggage Handling System
Vice Chairman Corcoran stated that this item was more of a clarification. Assistant
Airport Director Keating introduced the Airport’s Baggage Handling System consultant
Ryan Evers who would be making the presentation for the In-Line Bagge Handling
System.
Ryan Evers, Program Director at AECOM for the Baggage System Projects in the
West Region and Senior Architect Michael Monis presented the PSP Baggage
Handling Systems In-Line Screening Architectural Alternatives to the Commission.
Commissioner Young posed a question regarding Mr. Evers’ use of the term
“redundant” and whether it simply meant that the plan allows for one or more
components of the system to be down and to still operate. Mr. Evers confirmed
Commissioner Young’s understanding of the baggage program, and he provided
additional technical details. Assistant Airport Director interjected to introduce Airport
Maintenance Superintendent Jacob Colella.
Commissioner Fong had a question regarding Alternative 1 and Alternative 2, as one
provided more shade and cover than the other, and he asked which Alternative was
more expensive. Mr. Monis replied that Alternative 1, with the full roof, would be the
more expensive alternative. Mr. Evers added that the options were interchangeable
with the façade and elevations. Mr. Keating clarified that the goal for today was not to
select the roof, it was to select the architectural renderings. Commissioner Fong said
that he believed that the option with the full roof would be a better option as it provides
more cover and shade for the employees, especially with the desert summer weather.
ITEM 6
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 3 of 7
Commissioner Wiseman inquired about the number of people who would be working
inside the building on a regular basis. Mr. Evers explained that there would be an
operations and control room that would include two workstations plus a supervisor’s
station with a maximum of three to four people working in that room, he said that there
would also be a space for the Transportation Security Administration (TSA) for
approximately four to six people, and he noted that in 2042, the two spaces could
have a maximum of eight to ten people and that it would probably be more in the range
of six to seven people. Commissioner Wiseman asked if in the typical workplace
location, would the employees be experiencing the benefits of the natural light or
would they be in an office within the building. Mr. Evers said it would be an office
environment and that parts of the building would benefit from natural lighting in the
mornings. Mr. Monis added that another consideration would be glazing versus non-
glazing for the windows, which would help with lighting and diminish the need for
artificial lighting in the building during the day. Commissioner Wiseman asked about
the impact that this would have on cooling costs for the building during the summer
months. Mr. Monis indicated that there would be an overhang and the windows would
potentially be frosted to help with the cooling costs, and he said that they had not
calculated the difference in HVAC cooling costs between having the overhang and the
frosted glass and not having the items.
Commissioner Feltman asked how the inline Baggage Handling System (BHS)
alternatives would intersect with the various terminal proposals in the long-term
Master Plan. Mr. Evers acknowledged that he had asked the same question in the last
Master Plan meeting, and he said that they would coexist in harmony. He said that
they had worked with the Master Plan team to do some overlays to ensure that the
development of the Master Plan objectives would not be impacted by the BHS
alternatives and that the two projects could coexist throughout the evolution of the
Master Plan, and he noted that the space was not a primarily allocated space for any
of the Master Plan projects.
Vice Chairman Corcoran asked if the alternatives had been designed to meet the
demands in the 20-year long range plan, what happens if the Commission were to
pick Option 3 which is building a whole new airport, would any of the BHS equipment
move to Option 3 or would the Airport have to start over. Mr. Evers said that if a brand-
new airport was to be built, adjacent to the existing terminal, typically a new system
would need to be designed to fit within that space as part of the design process of the
new terminal. Commissioner Berriman inquired about the process for physically
clearing baggage that requires additional TSA screening. Mr. Evers reviewed the
system process for rerouting the 20% of failed bags that require additional TSA
screening.
Commissioner Martin asked for clarification regarding the purpose of the open canopy
area with a carousel, especially with the desert winds, high heat, and dust, and he
said that he was seeking to understand the logic. Mr. Evers provided technical details
regarding the baggage carousel, and he said that the reason the baggage carousel
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 4 of 7
would be located outside was because the airlines would be loading the baggage from
the baggage carousel on to carts and tugs and the baggage would be transported to
the airplanes, and he said that due to the size of the baggage carousel which can be
the size of a football field, it would be difficult to enclose the baggage carousel. He
said that it would be a good idea to provide shade and misters in the locations that it
would be appropriate.
Before voting on the recommendation, Commissioner Caldwell asked if the staff had
a recommendation. Airport Maintenance Superintendent Colella stated that the staff
would like to move forward with recommending the option that includes the windows
because staff believes that this option would reduce power consumption from the
lighting which would reduce the overall cost of ownership of the system over the
course of 15 years.
ACTION: To recommend that the City Council approve architectural concept design
#1 with windows. Moved by Commissioner Caldwell, seconded by Commissioner
Fong and approved by the following roll call vote: 12 Yes; 1 Abstain; and noting
the absence of Commissioners Burke, Dada, Delgado, Hughes and Michaelis.
Commissioner Martin added that he abstained from voting on the motion because he
was struggling to approve a motion without fully understanding the financial
implications. Mr. Evers stated that they do have a professional estimator on their team
who is running the Rough Order of Magnitude (ROM) estimates as required. TSA has
a strict process on how the Airport can use the TSA grant funds for the design and
that the AECOM team was creating a round one schematic design estimate for the
alternatives presented, as required. He noted that there were two canopies that
needed to be added to the design and that the AECOM team would be providing the
project costs to the Airport staff. Mr. Keating said that it was staff’s plan to come back
to the Commission once AECOM had moved further down with the design and that
having the Commission make a recommendation on the design alternative was a key
piece that staff needed to identify to decide on how to move forward.
Commissioner Young asked if the presumption was that if the Commission were to
select Alternative 3 in process the next couple of months, the inline BHS design
process would need to be fully stopped, and if the assumption is correct, would the
Commission then look at alternate solutions to improve the current bag situation
during that presumptively long interval until Alternative 3 is selected. Mr. Keating said
that the current system must be fixed immediately, and the BHS project cannot wait
on the Master Plan process. Commissioner Feltman inquired about the timeline for
the BHS project. Mr. Evers said that this type of project typically takes 20 to 24 months.
7.B Measure J Projects Update
Assistant Airport Director Keating stated that the Measure J Commission meeting was
set for the following day, and that he and Commissioner Feltman would be presenting
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 5 of 7
the four projects that the Airport Commission voted to recommend at the last Airport
Commission meeting. Vice Chairman Corcoran added that he had had an opportunity
to meet with the Measure J Oversight Committee Chairperson Naomi Soto and that
he had given her a heads up on the thought process that led the Airport Commission
to land on those four recommendations.
7.C Financial Summary Update
Airport Administration Manager Carpenter provided an overview of the financial
summary ending October 31, 2023, which was provided in the agenda packet.
7.D Concessions Update
Airport Assistant Director Keating noted that the updated concession projected
opening dates schedule was provided in the agenda packet, and he also noted that
he included the permit status of the projects, per the Commission’s request. He said
that the schedule reflects that almost every project was expected to start in December.
He added that for the most part, all the retail space has been ready to permit and that
staff was waiting for the contractor to be selected, as permits cannot be issued until
there is a contractor in place. Paradies and The Marshall Retail Group (MRG) reported
that they had been struggling with finding bidders, and Mr. Keating said that staff was
confident that both Paradies and MRG were close to selecting their preferred
contactors and that the projects would start sometime in the December timeframe,
and he said that this may slightly delay a couple of the opening dates.
Commissioner Feltman said that while he agreed that it may be difficult to find
contractors, he found it hard to imagine that the Airport cannot find anyone, and he
asked if there was a cost reason for this issue. Airport Assistant Director Keating noted
that these were Paradies and MRG’s projects and that the Airport was not the one
bidding the projects out, he said that Paradies and MRG had reported that they have
had to reach out to private companies due to the lack of success during their first and
second bidding rounds with local vendors, who did not demonstrate interest in the
projects and that the private companies were expressing more interest, and staff had
walked five or six contractors around the Airport to view the project sites. Mr. Keating
said that Paradies and MRG were feeling more confident about being able to hire
contractors, they were currently reviewing the contractor’s documentation and that
they should be selecting their contractors soon.
Commissioner Wiseman shared his concerns with the new opening date for El Marisol
and Coachella Valley Coffee and meeting the coffee needs of the travelers during the
peak season. Mr. Keating said that PSP Coffee was still open, which has been
meeting these needs for the past two years and that El Mirasol is a new restaurant,
therefore, nothing is closed at that location. Commissioner Wiseman asked whether
the commissary inside El Marisol would be completed sooner. Mr. Keating said yes,
a bit sooner because they got a head start on the commissary, and he clarified that it
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 6 of 7
is all one project because the commissary cannot be used until the front of the house
is open.
7.E 2024 Airport Commission Meetings
Executive Program Administrator Brown noted that the schedule for the 2024 Airport
Commission Regular Meetings was included in the agenda packet. She said that the
regular meetings would continue to be held on the third Wednesday of the month at
5:30 p.m. except for the June Commission meeting which falls on the Juneteenth
holiday and that the new proposed date is Tuesday, June 18th for this Commission
meeting. Vice Chairman Corcoran requested that calendar invites be sent to all
Commissioners.
ACTION: Approve the 2024 Airport Commission Meetings Schedule. Moved by
Commissioner Wise, seconded by Commissioner Park and approved by the
following roll call vote: 13 Yes; and noting the absence of Commissioners
Burke, Dada, Delgado, Hughes and Michaelis.
7.F Marketing Update
The Marketing updates were provided with the agenda packet. Vice Chairman
Corcoran reported that Deputy Director of Aviation, Marketing and Air Service Meier
was attending an event.
8. COMMISSIONERS REQUESTS AND REPORTS:
Vice Chairman Corcoran reported that the Palm Springs Air Museum received the
Palm Award for Visitor Experience from Visit Greater Palm Springs.
Vice Chairman Corcoran reported that Commissioner Gerald Adams had resigned,
and the City would be filling the Palm Springs vacancy as soon as possible.
9. REPORT OF CITY COUNCIL ACTIONS:
9.A. Past City Council Actions
9.B. Future City Council Actions
10. RECEIVE AND FILE:
10.A Airlines Activity Report October 2023
10.B Airline Activity Report Fiscal Year Comparison
11. COMMITTEES:
11.A Future Committee Meetings
Palm Springs Airport Commission
Action Summary Minutes of Regular Adjourned Meeting
November 15, 2023
______________________________________________________________________
Page 7 of 7
Vice Chairman Corcoran announced that there were openings in some of the Airport
Commission sub-committees, and he suggested that this matter be postponed until
December to allow Chairman Dada additional time to work on assigning the new
committee members to the sub-committees with vacancies. For those Commissioners
that were interested in being appointed to a sub-committee, especially the new
Commissioners who have not been appointed to a sub-committee, Vice Chairman
Corcoran asked that those Commissioners send a note to Executive Program
Administrator Brown to express their interest in serving on a sub-committee. Ms.
Brown noted that there were vacancies in the Budget Committee, the Marketing
Committee, and the Ad Hoc Design Review Committee.
Vice Chairman Corcoran noted that the Airport Commission Strategic Planning
Session and Master Plan Update meeting was currently scheduled for December 6,
2023, from 1:00 p.m. to 4:00 p.m., and he asked Airport Assistant Director to provide
some information regarding what was being planned and how staff was going to use
that time. Mr. Keating reported that most of the time would be dedicated to matters
that the Airport Commission met about at the previous year’s Strategic Planning
Session and that much of the information would be project-based which would include
reviewing the projects that had been scheduled, the progress of the previous projects,
and the projects moving forward. Vice Chairman Corcoran stated that he and
Chairman Dada would be meeting with the Airport staff on December 1st to review the
agenda and to provide their feedback before the December 6th meeting.
ADJOURNMENT: