HomeMy WebLinkAboutEOT-2024-0004_PowerPoint PresentationExtension of Time – West Coast Self-Storage
890 North Gene Autry Trail
Agenda Item 2.A.
Case No. EOT-2024-0004
June 26, 2024
P L A N N I N G
S E R V I C E S
DEPARTMEN T
PROJECT DETAILS
•61,704-SF self -storage facility
•3.55 -Acre undeveloped parcel
•Leasing office, loading areas, RV/boat
parking area, customer parking
•CORRECTION: Max. Building Height:
16’-8”
CASE 3.2802 MAJ (West Coast Self-Storage)
Major Development Permit Application & Major Architectural Review Application
P L A N N I N G
S E R V I C E S
DEPARTMEN T
PROJECT REVIEW PROCESS
03/09/2022
Planning Commission Approved a
Major Development Permit
application
PLANNING COMMISSION
Major Development Permit Application
Reviewed Features:
Conformance with development standards
Building placement & massing
Access
Circulation
Landscape & open space (Stormwater mgmt.)
Water & sewer
Environmental impact
ARC/ARC SUBCOMMITTEE
Major Architectural Review Application
Reviewed Features:
Architectural design
Façade & fenestration
Materials & color
Shading
Landscape design
Outdoor lighting
Mechanical equipment screening
Final
Project
Approval
P L A N N I N G
S E R V I C E S
DEPARTMEN T
PROJECT HISTORY
03/09/2022
Planning
Commission
Approved a Major
Development
Permit application
03/09/2022
PLANNING
COMMISSION
Major Development Permit
Application
APPROVED
04/04/2022
ARC
Major Architectural Review
application
CONTINUED
07/05/2022
ARC
Major Architectural Review
Application
APPROVED,
SUBJECT TO ARC
SUBCOMMITTEE
REVIEW
11/03/2022
ARC
SUBCOMMITTEE
Major Architectural Review
Application
APPROVED Entitlements
are due to
expire on
07/20/2024
Planning Commission
Major Development Permit Application
ARC (Final Approval)
Major Architectural Review Application
Planning Commission
Major Development Permit Application
ARC Review (Final Approval)
Major Architectural Review Application
***NO CHANGES ARE PROPOSED TO THE FINAL APPROVED PLANS***
CURRENT STATUS
•Grading permit has been issued for building pad installation (06/14/2024)
P L A N N I N G
S E R V I C E S
DEPARTMEN T
NEXT STEPS
•Building pad installation and pad certification need to be completed
•Following the building pad certification, secure a building permit and commence above-ground
construction
EXTENSION OF TIME
•May be granted pursuant to PSZC Sections 94.04.00(H)(2) and 94.04.01(G)(2), subject to the
requirements of PSZC Section 94.12.00
•Planning Commission must make the findings specified in PSZC Section 94.12.00(D)
•PSZC Section 94.12.00(D)(7) - Financial inability and market conditions are not considered
valid reasons to justify an extension of time request
•Project has been delayed by industry-wide team member retention issues and a prolonged
engineering value analysis process
P L A N N I N G
S E R V I C E S
DEPARTMEN T
ANALYSIS BY STAFF
•No changes are proposed to the final approved plans
•Applicant has demonstrated its commitment to the project (e.g . $125,000 water connection fee,
Caltrans encroachment permit, City grading permit)
•Building pad installation and certification process is anticipated to be completed sometime in
July – Commencement of above-ground construction is near
•Project meets the required findings stated in PSZC Section 94.12.00
P L A N N I N G
S E R V I C E S
DEPARTMEN T
RECOMMENDATION
•Planning Commission adopt the draft resolution and approve the extension of the
original entitlement approval by one (1) year until July 20, 2025
P L A N N I N G
S E R V I C E S
DEPARTMEN T
Extension of Time – West Coast Self-Storage
890 North Gene Autry Trail
Agenda Item 2.A.
Case No. EOT-2024-0004
June 26, 2024
P L A N N I N G
S E R V I C E S
DEPARTMEN T