HomeMy WebLinkAbout3D OCR
CITY COUNCIL STAFF REPORT
DATE: JUNE 5, 2023 BUSINESS & LEGISLATIVE
SUBJECT: APPROPRIATE FUNDS FOR HOMELESS NAVIGATION CENTER AND
EARLY ENTRY FACILITY IN THE AMOUNT OF $5,000,000 AT 3589
MCCARTHY ROAD.
FROM: Scott C. Stiles, City Manager
BY: Community & Economic Development Department
Engineering Services Department
SUMMARY:
Development of the Homeless Navigation Center (Navigation Center) at 3589 McCarthy
Road (Site) is continuing forward with major milestones still on schedule. Sitework and
utility infrastructure work is scheduled to begin in July 2023, production of the modular
units is underway with delivery scheduled for Fall 2023, and the facilities are expected to
be ready for the first residents in February 2024.
Bids for construction of the Navigation Center were received in May 2023 and were higher
than budgeted. As such, the development team is proposing to reduce construction costs
through the redesign and repurposing of Building 24 and Building 8 on the Navigation
Center campus, and to use existing office space in Building C. Doing so will help mitigate
the increased construction costs and have the added benefit of using Building 8 as an
Early Entry Facility which will house individuals who are waiting to be placed in the
independent living modular units. Building 24 and Building C will incorporate the
operations that were initially planned for Building 8.
This request is to allocate $5,000,000 from the Fiscal Year 2024 General Fund Budget
for additional costs relative to the Navigation Center and to add an Early Entry Facility at
the Site. The County of Riverside will also be increasing its contribution by $3,000,000 to
assist with the construction costs of the facility.
RECOMMENDATION:
Approve $5,000,000 in the Fiscal Year 2024 General Fund Budget for additional costs
relative to the Navigation Center and to add an Early Entry Facility at 3589 McCarthy
Road.
Item 3D - Page 1
City Council Staff Report
June 5, 2023 -- Page 2
Navigation Center and Shelter Implementation Actions
BACKGROUND:
At its February 9, 2023 meeting, the City Council approved additional funding for the
Navigation Center in the amount of $3,000,000. Total construction costs at that time
(including land) were estimated to be $31,695,202. The estimated costs were based on
design development phase drawings and not the final construction phase drawings. As
such, the estimates were not based on the final developed drawings. The $31,695,202 in
funding for the project is broken down as follows:
Funding Sources Amount % of Total
HomeKey Grant (City/County) $16,035,202 51%
ARPA (County) 7,000,000 22%
IEHP / Molina (County) 5,500,000 17%
City Funds 3,160,000 10%
Total $ 31,695,202 100%
Tilden-Coil Constructors (Tilden-Coil), the Project Construction Manager At Risk (CMAR)
requested bids for the Navigation Center in April 2023 when the final construction phase
drawings were complete. Bids were submitted in May 2023 but were much higher than
initially anticipated. The development team began evaluating several potential cost cutting
and value engineering options to reduce the costs as much as possible.
If approved, the revised funding sources would include the County contributing an
additional $3,000,000 for a total of $15,500,000, and the City contributing an additional
$5,000,000 for a total of $8,160,000, with the breakdown as follows:
Funding Sources Amount % of Total
HomeKey Grant (City/County) $16,035,202 40%
ARPA (County) 8,000,000 20%
IEHP / Molina (County) 7,500,000 19%
City 8,160,000 21%
Total $ 39,695,202 100%
The proposed revisions include utilizing Building 8 as an Early Entry Facility where
individuals can transition from the Access Center on El Cielo Road to the Navigation
Center. Having the Early Entry Facility integrated with the Navigation Center allows
individuals to receive wrap-around services at the Early Entry Facility while working
towards more independent living in the residential modules at the Navigation Center.
STAFF ANALYSIS:
The Project will include 80 prefabricated residential units and includes the rehabilitation
of two buildings on the Site (Buildings 8 and 24). The residential units will include
Item 3D - Page 2
City Council Staff Report
June 5, 2023 -- Page 3
Navigation Center and Shelter Implementation Actions
kitchenettes and bathroom facilities. Five of the units are for families and 10 units are for
transitional age youth. The Project also includes a children’s play area; general parking;
green space; hardscape and landscape. Building 8 was planned for daytime services and
administration uses; Building 24 was planned for operational services; and Building C
was not considered a part of the Navigation Center Project.
The estimated cost developed by Tilden-Coil at the design development phase in January
was lower than the construction phase drawing bid costs. The cost increase is due to
several factors including the following:
• Number of Bids Received – Tilden Coil has noted that a significant number of their
regular subcontractors did not bid on the project due to timing issues and the
complex nature of the work. The end result is a notable increase in construction
costs.
• Construction Phase bid costs vs Design Development Phase estimates – the cost
increase is partially due to the drawings not being fully developed at the design
development phase.
• Electrical Costs – During the design development phase it was anticipated that the
site may have to operate for about 4-6 months on temporary power as a means to
house patrons at the site as quickly as possible. The temporary power costs alone
exceeded $4.9 million.
• Site Infrastructure – the site requires extensive infrastructure upgrades to
accommodate the buildings and services being added to the Navigation Center.
As the project moved from the design phase to construction drawings, the
infrastructure upgrades became more evident.
• Service Provider and Community Input Design Features – Third-party service
provider and community input were incorporated into the design throughout the
process. These include walk-in refrigeration systems, large multi-purpose rooms,
recuperative care, loading dock and trash compactor, extensive landscaping and
hardscape, dog park features, shade and screening from the public. These
requested features also increased construction costs.
The development team was able to reduce the Project costs by $10,000,000 after a
thorough review of the plans, specifications and proposed amenities. This involves the
following revisions:
• Building 8 was initially designed to house daytime services and program
administration offices. It would have been accessible Monday through Friday for
eight hours a day. It included a reception area, intake room, case management,
employment services, and flex space for service providers to assist residents.
Building 8 will be re-designed and re-purposed to serve as an Early Entry Facility
where approximately 50 shelter beds will be available as an overnight facility.
Administrative functions and services will be relocated to other buildings at the site.
Item 3D - Page 3
City Council Staff Report
June 5, 2023 -- Page 4
Navigation Center and Shelter Implementation Actions
• Building C was originally planned for use a shelter facility using funds from the
County of Riverside’s Inland Empire Health Plan (IEHP) grant funds in the amount
of $5,500,000. Project HomeKey Funds could not be used for such a shelter facility
as congregate housing was not an allowable use of the HomeKey Funds.
However, plans for the shelter facility were put on hold as the IEHP funds were
needed for the Navigation Center.
The existing office space in Building C will used to replace some of the office
space, case management, employment services, and flex space that will be
eliminated from Building 8. Only minimal funds are needed for Building C as the
office space is already built out.
• Building 24 was intended to house 24-hour operational services. A large portion of
this building was taken up by the commercial kitchen which includes dry and cold
storage. It also had a large community dining / multi-purpose room, and a large
Community Corridor which was designed to also serve as a multipurpose room.
Recuperative care spaces were also included for individuals who are released from
hospital to continue their recovery with access to showers and nursing station. A
security office, laundry room, mail room, and loading docks were also part of
Building 24.
Building 24 will be re-designed to reduce the size of the commercial kitchen, dining/
multi-purpose room, and eliminate office space that can be provided in Building C.
The loading dock area will be removed from Building 24. Recuperative care space
can also be eliminated from Building 24 as recuperative care services can be
provided in the modular residential units as needed.
• Additional value engineering measures include:
o Reduced interior landscaping
o Reduced hardscape
o Elimination of awnings at the entryways
o Eliminate option for use of temporary power
o Eliminate keycard and electrified hardware at modular residential units
The cost of developing the Project with these changes, however, requires an additional
$5,000,000 from the City. The County of Riverside will also be contributing an additional
$3,000,000 to the project.
Early Entry Facility
When people experiencing homelessness in Palm Springs need to access an overnight
shelter or interim housing, the closest location of beds in the Coachella Valley are the
residential facilities in Indio operated by Martha’s Village and Kitchen (MVK) and
Coachella Valley Rescue Mission (CVRM). However, the distance to these shelter
facilities adds unnecessary complications. The Access Center on El Cielo Road will
Item 3D - Page 4
City Council Staff Report
June 5, 2023 -- Page 5
Navigation Center and Shelter Implementation Actions
provide limited shelter beds; the Early Entry Facility will be the second step in the process
to assist in providing housing for people experiencing homelessness and will be part of
the progression into the Navigation Center modular units, and preparation for being
placed in permanent housing after the Navigation Center. Without an adequate number
of such emergency and transitional housing beds, people experiencing homelessness
are forced to find shelter in encampments, tents, cars, and other places not meant for
human habitation.
The City currently partners with MVK to operate the Access Center at 225 El Cielo Road
on a drop-in basis during the daytime and provides a variety of wrap-around services,
such as assisting individuals with securing health, disability, social security, and other
benefits; providing vouchers for use of laundry facilities and for bus pass system based
on client need; and case management to clients based on their individual need. However,
the Access Center does not provide sufficient space for overnight shelter on a continuing
basis.
The Early Entry Facility in conjunction with the Navigation Center will create a path to
housing where individuals can exit life on the streets, work towards independent living in
the residential modules of the Navigation Center, receive wrap-around services, job
training, and case management (Attachment A). Beds in the Early Entry Facility will be
also available for the Palm Springs Police Department to refer individuals to the
Navigation Center campus. Neither the Early Entry Facility nor the Navigation Center will
provide walk-up services; instead, individuals will be referred from the El Cielo Access
Center, referred by the Police Department, or referred by one of the City’s partner
organizations.
CONSTRUCTION SCHEDULE:
Tilden-Coil has received bids for the project and is ready to move into the construction
phase. As noted earlier, the bids came in higher than expected and through value
engineering the cost of the project has been reduced. As a result of value engineering,
several different trades are being rebid to conform to the value engineering redesign.
Tilden-Coil anticipates construction to begin in late July.
The design of the modular units is complete and is currently going through the
manufacturing process. Tilden-Coil anticipates the modular units to be delivered to the
site in the fall. In addition, the re-designed Building 8 (Early Entry Facility) is tentatively
scheduled to be completed by February of 2024. It is anticipated that Building 8 will use
the existing power source on the site will be the first component of the Navigation Center
facility to open. Unfortunately, the delivery of the power source equipment required to
power the rest of the facility is not anticipated until May of 2024. After the power source
is delivered in May of 2024, the contractor will finalize the construction of the remaining
facilities and deliver the completed project to the City in July 2024.
Item 3D - Page 5
City Council Staff Report
June 5, 2023 -- Page 6
Navigation Center and Shelter Implementation Actions
ALIGNMENT WITH STRATEGIC PLANNING:
The first major task in the Strategic Plan for Quality of Life (1A) with the key objective to
improve homelessness is to build a Navigation Center, provide integrative services, and
partner with homelessness providers for enhanced services.
FISCAL IMPACT:
At this time staff is requesting utilization of $5,000,000 to supplement construction costs
for the Navigation Center and to set up a new Early Entry Facility. If approved, funds in
the amount of $5,000,000 will be budgeted in the Fiscal Year 2024 General Fund Budget
for the Navigation Center and Early Entry Facility.
REVIEWED BY:
Department Director: Jay Virata
City Engineer: Joel Montalvo
Deputy City Manager: Flinn Fagg
City Manager: Scott Stiles
ATTACHMENT:
A) Path to Housing
Item 3D - Page 6
ATTACHMENT A
DRAFT Path to Housing
City of Palm Springs
Step 1 Step 2 Step 3 Step 4
El Cielo
Emergency Access Center
McCarthy Navigation
Center: Building 8
Early Entry Facility
McCarthy Navigation
Center:
Private Units
Permanent
Housing
•30 Beds
•Complete wraparound
services (mobile)
•Referral from PD, Access
Center staff, County
•May stay up to 30 days
•Walk out/drive out allowed
(with staff approval)
•50 Beds (in cubicles)
•Complete wraparound
services (on site)
•Referral required from El
Cielo Access Center
•May stay up to 180 days
(until private unit is available)
•Guests transported to transit
facilities (or drive out allowed
with staff approval)
•80 Residential Units
•Complete wraparound
services (on site)
•Referral required from either
El Cielo Access Center or
Building C
•May stay up to 365 days
(until permanent housing is
available)
•Guests transported to transit
facilities (or drive out allowed
with staff approval)
•Monarch Apartments
•Vista Sunrise II
•Aloe at Palm Canyon
•Section 8
•Housing Vouchers
Item 3D - Page 7