Loading...
HomeMy WebLinkAboutAgenda Item 2A - Dream Hotel TimelineDream Hotel –Construction TimelineAgenda Item #2A May 11, 2023 DEVELOPMENT SERVICES Item 2A - Page 1 Item 2A - Page 2 Part I –Site Work •Timeline: April 2023 to September 2024 •Permit submittal: 4/23 (grading), 10/23 (water, sewer) •Permit approval: 5/23 (grading), 11/23 (water, sewer) •Construction start: 8/23 •Construction finish: 9/24 DEVELOPMENT SERVICES Item 2A - Page 3 Part II –Dream Hotel & Condos •Timeline: March 2023 to December 2026 •Permit submittal: 10/23 (core & shell), 3/24 (main) •Permit approval: 1/24 (core & shell), 8/24 (main) •Construction start: 9/24 (core & shell), 2/25 (main) •Construction finish: 2/25 (core & shell), 12/26 (main) DEVELOPMENT SERVICES Item 2A - Page 4 Part III –North Villas •Timeline: August 2023 to December 2026 •Permit submittal: 7/24 •Permit approval: 12/24 •Construction start: 12/24 •Construction finish: 12/26 DEVELOPMENT SERVICES Item 2A - Page 5 Part IV –South Villas •Timeline: August 2023 to December 2026 •Permit submittal: 10/24 •Permit approval: 3/25 •Construction start: 3/25 •Construction finish: 12/26 DEVELOPMENT SERVICES Item 2A - Page 6