Item 2D
September 1, 2022
AMENDED
MILESTONE &
OPERATIONS
COVENANT
Executed on December 1, 2021
Applicant remains in good standing
per the agreement and has satisfied
each milestone either on time or
ahead of schedule.
2
3
Item
No.
Scope Required
Date
Date Satisfied
1 Confirm architect engagement 12/3/2021 12/1/2021
2 Architect to certify that plans are at least 30% complete 12/3/2021 12/1/2021
3 Owner to submit a plan to protect the historical
structures while demolition is taking place
12/1/2021 12/1/2021
4 Owner to install property screening as approved by the
Development Services Director
12/1/2021 12/1/2021
5 Owner to demolish vacant, non historical structures 5/1/2022 4/24/2022
6 Architect to certify that plans are at least 60% complete 2/1/2022 2/1/2022
7 Submit application to extend entitlements 3/1/2022 2/28/2022
8 Owner to commission a feasibility report by a nationally
recognized and mutually agreed upon firm
4/15/2022 4/7/2022
9 Submit a set of 80% complete construction drawings as
confirmed by the architect for plan check review
6/15/2022 6/13/2022
PERFORMANCE SCHEDULE
4
SITE DEMO
5
SITE DEMO
6
PROJECT RENDERINGS
7
PROJECT RENDERINGS
NEW CHURCH II, LLC
8