HomeMy WebLinkAboutItem 3D - Staff Report Page 5 (Revised 5-Year CIP)5 YEAR
C APITAL
IMPROVEMENT
PROGRAM
C ITY OF
PALM SPRINGS FY2023-2027DRAFTupdated: June 9, 2022
2
INTRODUCTION
The City’s Capital Improvement Program (CIP) includes major projects to construct
new, replace or upgrade existing City infrastructure including but not limited to its
bridges, buildings, facilities, drainage systems, parks, streets, highways, traffic
signals and utilities.
The following schedules are included on the pages that follow:
1. Five Year Capital Improvement Program Funding
a. A one-page funding summary for the entire five-year plan.
b. List of Projects by Fund for each Fiscal Year
c. Table of Projects and Accounts
2. City Council Priorities
3. Detailed Project Information Sheets. These pages provide the project’s
description, justification, conformance to City Council priorities, location,
conformance to the General Plan, a breakdown of the cost estimate, and the
project’s funding over the next five fiscal years.
4. Appendix
a. List of Revenue Funds. These pages provide a brief explanation of the
various funds that may be used on Capital Improvement Projects
b. Historical list of City Project numbers
OBJECTIVES
The objectives of the Five-Year CIP are:
• Promote sound financial planning in the implementation of capital projects
• Identify and forecast funding needs and sources to maximize federal, state,
regional, and local funding sources
• Implement projects that meet the community and City Council goals
• Complete capital improvements in a timely and systematic manner
3
5-Year Capital Improvement Program
Tips and Guide to Using it Effectively
Section 1: This section summarizes funding data and shown in three ways.
By Fund By Fiscal Year By Project Account
Section 2: Restatement of City Council Priorities for quick reference
Section 3: Detailed project information sheets
If you are viewing the electronic copy, each project has a
second notes page, so that the hard copy version will be
on the same page when printed on 2 sides.
Sorted by City Project Number YY-##
First 2 digits are the year the project
was conceived, then the next 2 digits
are in the sequential order projects
were developed for that year
Project Title
Council Priority
Location
Proj. Description
Proj. Justification
General Plan Conf. A project may have
multiple funding
sources. This matrix
shows the funds and
how it is split over the
next 5 years. Data is
more realistic in the
first year and are
rough projections in
further out years
Rough cost
estimates based on
available data. If
actual costs are
available, then the
data is updated
Project Priority can be:
• Essential (start
within 1 year)
• Necessary (start
within 1-3 years)
• Desirable (start
within 3-5 years)
• Deferrable
Table of Projects and AccountsProject # Project Title Fund Budgeted FY20-21 Available Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 Total01-11 Indian Canyon Bridge Over UPRR 261 10,685,403.00$ 10,145,714.00$ 8,142,905.00$ 1,699,968.00$ -$ -$ -$ 19,988,587.00$ 01-11 Indian Canyon Bridge Over UPRR 134R 3,512,908.00$ 3,246,262.00$ 3,074,340.00$ 641,820.00$ -$ -$ -$ 6,962,422.00$ 01-11 Indian Canyon Bridge Over UPRR 134L 1,184,931.00$ 1,096,049.00$ 1,024,780.00$ 213,940.00$ -$ -$ -$ 2,334,769.00$ 01-11 Indian Canyon Bridge Over UPRR 420 4,000,000.00$ 3,991,600.00$ 6,000,000.00$ 3,000,000.00$ -$ -$ -$ 12,991,600.00$ 06-18 South Palm Canyon Bridge 261 955,308.00$ 848,594.00$ 4,600,506.00$ -$ -$ -$ -$ 5,449,100.00$ 06-18 South Palm Canyon Bridge 134L 72,708.00$ 71,583.00$ 346,044.00$ -$ -$ -$ -$ 417,627.00$ 06-18 South Palm Canyon Bridge 133 125,946.00$ 125,021.00$ -$ -$ -$ -$ -$ 125,021.00$ 06-18 South Palm Canyon Bridge 001 290,840.00$ 149,327.00$ -$ -$ -$ -$ -$ 149,327.00$ 08-25 Ramon Rd Over Whitewater River 261 555,899.00$ 449,751.00$ -$ 9,829,653.00$ 9,829,653.00$ 9,829,653.00$ -$ 29,938,710.00$ 08-25 Ramon Rd Over Whitewater River 134R 404,093.00$ 295,933.00$ -$ 2,227,365.00$ 2,227,365.00$ 2,227,365.00$ -$ 6,978,028.00$ 08-25 Ramon Rd Over Whitewater River 134L 172,209.00$ 139,448.00$ 100,000.00$ 296,982.00$ 296,982.00$ 296,982.00$ -$ 1,130,394.00$ 10-10 Vista Chino Low Water Crossing 261 5,671,445.00$ 3,491,412.00$ 2,907,767.00$ 2,907,767.00$ 33,831,739.00$ 33,831,739.00$ -$ 76,970,424.00$ 10-10 Vista Chino Low Water Crossing 134R 458,550.00$ 246,721.00$ 282,549.00$ 282,549.00$ 3,287,445.00$ 3,287,445.00$ -$ 7,386,709.00$ 10-10 Vista Chino Low Water Crossing 134L 445,431.00$ 375,021.00$ -$ -$ 1,012,160.00$ 1,012,160.00$ -$ 2,399,341.00$ 12-02 South Palm Canyon Over Tahquitz Creek 261 812,994.00$ 716,836.00$ 3,601,843.00$ 3,601,843.00$ -$ -$ -$ 7,920,522.00$ 12-02 South Palm Canyon Over Tahquitz Creek 134R 257,750.00$ 248,399.00$ 349,993.00$ 349,993.00$ -$ -$ -$ 948,385.00$ 12-02 South Palm Canyon Over Tahquitz Creek 134L 2,980.00$ -$ 116,664.00$ 116,664.00$ -$ -$ -$ 233,328.00$ 12-04 E Palm Canyon Over Palm Canyon Wash 261 542,802.00$ 284,222.00$ 1,295,193.00$ 5,180,776.00$ -$ -$ -$ 6,760,191.00$ 12-04 E Palm Canyon Over Palm Canyon Wash 134R 88,912.00$ 32,299.00$ 125,854.00$ 503,418.00$ -$ -$ -$ 661,571.00$ 12-04 E Palm Canyon Over Palm Canyon Wash 134L 111,620.00$ 92,973.00$ 41,953.00$ 167,806.00$ -$ -$ -$ 302,732.00$ 16-08 Main Library Renovation 260 -$ -$ 4,138,650.00$ 2,921,400.00$ -$ -$ -$ 7,060,050.00$ 16-08 Main Library Renovation 261 -$ -$ 4,138,650.00$ 2,921,400.00$ -$ -$ -$ 7,060,050.00$ 16-18 HSIP Cycle 8 Traffic Signal Modifications 261 2,199,341.00$ 2,117,242.00$ 550,000.00$ -$ -$ -$ -$ 2,667,242.00$ 16-18 HSIP Cycle 8 Traffic Signal Modifications 142 117,871.00$ 116,383.00$ 1,088,536.00$ -$ -$ -$ -$ 1,204,919.00$ 18-05 HSIP Cycle 9 Traffic Signal Modifications 261 71,264.56$ 14,082.93$ 1,399,200.00$ 232,236.00$ -$ -$ -$ 1,645,518.93$ 18-06 Victoria and Ruth Hardy Park Restrooms Renovation 260 -$ -$ 950,000.00$ -$ -$ -$ -$ 950,000.00$ 18-09 Fire Tower Training Facility 001 201,949.00$ 201,949.00$ -$ -$ -$ -$ -$ 201,949.00$ 18-09 Fire Tower Training Facility 260 -$ -$ 750,000.00$ -$ -$ -$ -$ 750,000.00$ 18-04 Plaza Theater 260 -$ -$ 1,000,000.00$ -$ -$ -$ -$ 1,000,000.00$ 18-10 Downtown Safety Bollards Phase 2 260 -$ -$ -$ 500,000.00$ 608,750.00$ -$ -$ 1,108,750.00$ 18-14 Gene Autry Windwall Upgrade 134L 59,985.00$ 9,336.00$ 2,020,000.00$ -$ -$ -$ -$ 2,029,336.00$ 18-17 Police Department Impound Building 261 -$ -$ -$ 580,000.00$ -$ -$ -$ 580,000.00$ 18-17 Police Department Impound Building 260 -$ -$ -$ 580,000.00$ -$ -$ -$ 580,000.00$ 18-20 Skylight Railings 261 456,875.56$ 450,000.00$ 397,780.00$ -$ -$ -$ -$ 847,780.00$ 19-15 Storm Drain Line 20 261 -$ -$ 7,520,000.00$ -$ -$ -$ -$ 7,520,000.00$ 19-15 Storm Drain Line 20 135 467,444.00$ 340,840.00$ 810,000.00$ -$ -$ -$ -$ 1,150,840.00$ 19-18 JC Frey Building Rehabilitation 260 -$ -$ -$ 870,000.00$ -$ -$ -$ 870,000.00$ 19-23 Keyless Entry System Phase 2 260 -$ -$ 200,000.00$ 468,750.00$ -$ -$ -$ 668,750.00$ 19-24 Demuth Park ADA Access Phase 2 260 -$ -$ 600,000.00$ 1,000,000.00$ -$ -$ -$ 1,600,000.00$ 19-25 Life Safety Improvements - Fire Sprinklers and Alarms 260 -$ -$ 900,000.00$ 1,000,000.00$ -$ -$ -$ 1,900,000.00$ 19-26 Emergency Generators at City Facilities 260 -$ -$ 600,000.00$ 777,500.00$ -$ -$ -$ 1,377,500.00$ 19-27 City Water Treatment Program (HVAC) 260 -$ -$ 507,500.00$ -$ -$ -$ -$ 507,500.00$ 19-28 Recreation Fields LED Lighting Upgrades 260 94,219.00$ -$ 4,100,000.00$ -$ -$ -$ -$ 4,100,000.00$ 14
Table of Projects and AccountsProject # Project Title Fund Budgeted FY20-21 Available Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 Total20-03 Roundabout at Indian Canyon SPC Camino Parocela 260 210,300.00$ -$ 400,000.00$ 400,000.00$ 400,000.00$ 400,000.00$ -$ 1,600,000.00$ 20-03 Roundabout at Indian Canyon SPC Camino Parocela 261 -$ -$ 200,000.00$ 200,000.00$ 200,000.00$ 400,000.00$ -$ 1,000,000.00$ 20-04 Sunrise Plaza HVAC Improvements 260 -$ -$ 400,000.00$ 500,000.00$ 696,500.00$ -$ -$ 1,596,500.00$ 20-06 City Hall and Police Department Electrical Upgrades 261 480,000.00$ 480,000.00$ 100,000.00$ -$ -$ -$ -$ 580,000.00$ 20-07 Sunrise Plaza Domestic Water Line Separation 261 -$ -$ -$ 253,750.00$ -$ -$ -$ 253,750.00$ 20-08 Fleet Operations HVAC and Electrical Improvements 261 100,000.00$ 100,000.00$ 200,000.00$ 497,500.00$ -$ -$ -$ 797,500.00$ 20-10 Sunrise Plaza Door and Window Replacements 261 100,000.00$ 100,000.00$ 200,000.00$ 524,150.00$ -$ -$ -$ 824,150.00$ 20-21 Local Road Safety Plan Projects 261 -$ -$ 500,000.00$ 2,646,500.00$ 1,617,833.00$ 1,617,833.00$ 1,617,834.00$ 8,000,000.00$ 21-04 WWTP General Sitework and Pavement Replacement 420 -$ -$ 150,000.00$ 725,000.00$ 725,000.00$ -$ -$ 1,600,000.00$ 21-05 WWTP Sludge Drying Beds 420 429,898.00$ 225,254.00$ 706,000.00$ 706,000.00$ -$ -$ -$ 1,637,254.00$ 21-06 WWTP Demolition of Abandoned Equipment 420 -$ -$ 1,842,750.00$ 1,842,750.00$ -$ -$ -$ 3,685,500.00$ 21-08 WWTP Biosolids Dewatering Facility 420 4,999,959.00$ 2,029,867.00$ 2,000,000.00$ 7,000,000.00$ 7,000,000.00$ 6,313,858.00$ -$ 24,343,725.00$ 21-10 Traffic Operation Center Communication Upgrades 134L 18,184.00$ 1,158.00$ 500,000.00$ -$ -$ -$ -$ 501,158.00$ 21-16 Demuth Dog Park 152 1,448,270.00$ 1,448,270.00$ -$ 201,965.00$ -$ -$ -$ 1,650,235.00$ 21-16 Demuth Dog Park 260 -$ -$ -$ -$ -$ -$ -$ -$ 21-16 Demuth Dog Park 261 650,000.00$ 650,000.00$ -$ 1,000,235.00$ -$ -$ -$ 1,650,235.00$ 21-17 Arnico Tract Sewer - Phase 4 260 585,000.00$ -$ 200,000.00$ -$ -$ -$ -$ 200,000.00$ 22-02 Annual Slurry Seal 133 877,368.00$ -$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 3,375,000.00$ 22-02 Annual Slurry Seal 134L 206,463.00$ -$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 3,375,000.00$ 22-08 Annual Pavement Rehabilitation 260 8,998,293.00$ 3,017,493.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 33,017,493.00$ 22-14 Convention Center Exhibit Hall and Primrose Carpet Replacement 260 -$ -$ 650,000.00$ -$ -$ -$ -$ 650,000.00$ 22-15 Exhibit Hall Air Wall and Acoustical Tile Refurbish 260 -$ -$ -$ 450,000.00$ -$ -$ -$ 450,000.00$ 22-16 Convention Center Jackie Lee Houston Plaza Upgrades 260 -$ -$ 100,000.00$ -$ -$ -$ -$ 100,000.00$ 22-17 Convention Center Marquee Upgrade 260 -$ -$ -$ 160,000.00$ -$ -$ -$ 160,000.00$ 22-18 Palm Springs Convention Center Retrofit Lighting Controls 260 -$ -$ 500,000.00$ -$ -$ -$ -$ 500,000.00$ 22-19 Relocate Fire Station 1 260 -$ -$ 1,600,000.00$ 3,600,000.00$ 9,000,000.00$ 9,000,000.00$ -$ 23,200,000.00$ 22-20 Measure J Community Initiated Projects 260 -$ -$ 3,000,000.00$ 1,000,000.00$ 1,000,000.00$ 1,000,000.00$ 1,000,000.00$ 7,000,000.00$ 22-21 Pedestrian Master Plan Recommended Projects 261 -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$ 22-21 Pedestrian Master Plan Recommended Projects 134L -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$ 22-21 Pedestrian Master Plan Recommended Projects 260 -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$ 22-22 Citywide Sign and Striping Inventory and Replacement Program 133 -$ -$ 300,000.00$ -$ 300,000.00$ -$ -$ 600,000.00$ 22-23 Annual Traffic Calming Projects 133 -$ -$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 1,250,000.00$ 22-23 Annual Traffic Calming Projects 134L -$ -$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 1,250,000.00$ 22-24 Pickleball Courts 152 -$ -$ 150,000.00$ 575,000.00$ -$ -$ -$ 725,000.00$ 22-24 Pickleball Courts 260 -$ -$ 150,000.00$ 575,000.00$ -$ -$ -$ 725,000.00$ 22-25 Playground Equipment Shade Structures 137 -$ -$ 281,960.00$ -$ -$ -$ -$ 281,960.00$ 22-26 San Rafael Turf Conversion 260 -$ -$ 150,000.00$ -$ -$ -$ -$ 150,000.00$ Totals 53,125,413.12$ 37,349,039.93$ 87,311,417.00$ 75,079,680.00$ 81,383,427.00$ 78,567,035.00$ 11,967,834.00$ 371,658,432.93$ 15
5
Capital Improvement Program
Project Summary by Fund for Fiscal Year 2022-2023 (Year 1)
CP# Project Title Phase Expenditure Set Aside
Fund 133 – Gas Tax
22-02 Annual Slurry Seal Construction $675,000 -
22-22 Annual Sign & Striping Replacements Construction $300,000 -
22-23 Annual Traffic Calming Projects Design/Const $250,000 -
$1,225,000 -
Total Gas Tax Projects 2022-2023 $1,225,000
Fund 134 – Measure A - Regional
01-11 Indian Canyon Bridge Over UPRR Construction* $3,074,340 -
10-10 Vista Chino Low Water Crossing Design/RW - $282,549
12-02 South Palm Canyon at Tahquitz Creek Design/RW - $349,993
12-04 East Palm Canyon Bridge Design/RW - $125,854
* Depends on Federal Funding $3,074,340 $758,396
Fund 134 – Measure A - Local
01-11 Indian Canyon Bridge Over UPRR Construction* $1,024,780 -
06-18 S. Palm Canyon at Palm Canyon Wash Design/RW - $346,044
08-25 Ramon Road Bridge -Whitewater River Design/RW - $100,000
12-02 South Palm Canyon at Tahquitz Creek Design/RW - $116,664
12-04 East Palm Canyon Bridge Design/RW - $41,953
18-14 Gene Autry Windwall Upgrade Construction $2,020,000 -
21-10 Traffic Operations Center Construction - $500,000
22-02 Annual Slurry Seal Construction $675,000 -
22-21 Pedestrian & SR2S Master Plan Projects Design - $500,000
22-23 Annual Traffic Calming Projects Design/Const $250,000 -
* Depends on Federal Funding $3,969,780 $1,604,661
Total Measure A Projects 2022-2023 $9,407,177
Fund 135 – Drainage
19-15 Storm Drain Line 20 Construction $810,000 -
$810,000 -
Total Drainage Projects 2022-2023 $810,000
Fund 137 – Community Development Block Grant (CDBG)
22-25 Playground Equipment Shade Struct. Construction $281,960 -
$281,960 -
Total CDBG Projects 2022-2023 $281,960
6
CP# Project Title Phase Expenditure Set Aside
Fund 142 – Gas Tax SB-1 RMMA
16-18 HSIP Cycle 8 – Traffic Signal Improv. Construction* $1,088,536 -
* Depends on Caltrans approval of City’s Proj. Labor Agreement $1,088,536 -
Total Gas Tax SB-1 RMMA Projects 2022-2023 $1,088,536
Fund 152 – Quimby Act
22-24 Pickleball Courts Planning/Design $150,000 -
$150,000 -
Total Quimby Act Projects 2022-2023 $150,000
Fund 260 – Measure J
16-08 Main Library Remodel Planning - $4,138,650
18-04 Plaza Theater Planning/Design $1,000,000 -
18-06 Victoria & Ruth Hardy Park Restrooms Construction $950,000 -
18-09 Fire Tower Training Facility Construction* $750,000 -
19-23 Keyless Entry Phase 2 Planning - $200,000
19-24 Demuth Park ADA Access – Phase 2 Planning - $600,000
19-25 Life Sfty Impr – Fire Sprkls/Fire Alarms Planning - $900,000
19-26 Back Up Generators at City Facilities Planning - $600,000
19-27 City Water Treatment Program (HVAC) Planning - $507,500
19-28 Recreation Fields LED Lighting Upgrade Construction $4,100,000 -
20-03 Roundabout at Ind Canyon, South
Palm Canyon, Camino Parocela Design - $400,000
20-04 Sunrise Plaza HVAC Improvements
Chillers and Cooling Towers Planning - $400,000
21-17 Arnico Tract Sewers – Phase 4 Design - $200,000
22-08 Annual Pavement Rehabilitation Construction $6,000,000 -
22-14 Conv. Center Carpet Replacement Const. by others $650,000
22-16 Conv. Center Jackie Lee Houston Plaza Const. by others $100,000
22-18 Conv. Center Marquee Upgrades Const. by others $500,000
22-19 Relocate Fire Station #1 Planning - $1,600,000
22-20 Measure J – Community Initiated Proj. Plan/Design/Const $3,000,000 -
22-21 Pedestrian Master Plan Projects Planning/Design $500,000 -
22-24 Pickleball Courts Planning/Design $150,000 -
22-26 San Rafael Turf Conversion Plan/Design/Const $150,000 -
* Depends on Fire Station Number 1 (CP# 22-19) relocation $17,850,000 $9,546,150
Total Measure J Projects 2022-2023 $27,396,150
7
CP# Project Title Phase Expenditure Set Aside
Fund 261 – Capital Projects
01-11 Indian Canyon Bridge Over UPRR Construction* $8,142,905 -
06-18 South Palm Canyon Over Palm
Canyon Wash Design/RW - $4,600,506
10-10 Vista Chino Low Water Crossing Design/RW - $2,907,767
12-02 South Palm Canyon at Tahquitz Creek Design/RW - $3,601,843
12-04 East Palm Canyon Bridge Design/RW - $1,295,193
16-08 Main Library Remodel Planning - $4,138,650
16-18 HSIP Cycle 8 - Traffic Signals Construction** $550,000 -
18-05 HSIP Cycle 9 – Traffic Signals Construction $1,399,200 -
18-20 Skylight Railings Design $397,780
19-15 Storm Drain Line 20 Construction $7,520,000 -
20-03 Roundabout at Indian Canyon, South
Palm Canyon, Camino Parocela Design - $200,000
20-06 City Hall & Police Dept Elect. Upgrades Planning - $100,000
20-08 Fleet Ops. HVAC and Elec. Upgrades Planning - $200,000
20-10 Sunrise Plaza Door and Window
Replacements Planning - $200,000
20-21 Local Roads Safety Plan Recommended
Projects Design $500,000 -
22-21 Pedestrian Master Plan Projects Planning/Design $250,000 $250,000
$18,362,105 $17,891,739
Total Capital Projects 2022-2023 $36,253,844
* Depends on Federal Funding
**Depends on Caltrans review and approval of City Project Labor Agreement
Subtotal of Non- Enterprise Projects Year 1 - FY 2022-2023 $46,811,721 $29,800,946
Total Non-Enterprise Funded Projects 2022-2023 $76,612,667
Enterprise Fund
Fund 420 – Wastewater
01-11 Indian Canyon Bridge Over UPRR Construction* $6,000,000 -
21-04 Sitework Pavement Rehabilitation Construction $150,000 -
21-05 Sludge Drying Beds Planning/Design - $706,000
21-06 Demolish Abandoned Headworks,
Primary Clarifier, Sand Filter Planning/Design - $1,842,750
21-08 Biosolids Dewatering Facilities Planning - $2,000,000
* Depends on Federal Funding $6,150,000 $4,548,750
Total Wastewater Projects 2022-2023 $10,698,750
Subtotal of Enterprise Projects Year 1 - FY 2022-2023 $6,150,000 $4,548,750
Total Enterprise Funded Projects 2022-2023 $10,698,750
8
Total Expenditures Year 1 – FY 2022-2023 $52,961,721
Total Set Aside Year 1 – FY 2022-2023 $34,349,696
Total of All Project Funding for Year 1 – FY 2022-2023 $87,311,417
9
Capital Improvement Program
Project Summary by Fund for Fiscal Year 2023-2024 (Year 2)
CP# Project Title Budget
Fund 133 – Gas Tax
22-02 Annual Slurry Seal $ 675,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Gas Tax Projects FY 2023-2024 $ 925,000
Fund 134 – Measure A - Regional
01-11 Indian Canyon Bridge Over UPRR $ 641,820
08-25 Ramon Road Bridge Over Whitewater River $ 2,227,365
10-10 Vista Chino Low Water Crossing $ 282,549
12-02 South Palm Canyon Over Tahquitz Creek $ 349,993
12-04 East Palm Canyon Bridge $ 503,418
Total Measure A Regional Projects FY 2023-2024 $ 4,005,145
Fund 134 – Measure A - Local
01-11 Indian Canyon Bridge Over UPRR $ 213,940
08-25 Ramon Road Bridge Over Whitewater River $ 296,982
12-02 South Palm Canyon Over Tahquitz Creek $ 116,664
12-04 East Palm Canyon Bridge $ 167,806
22-02 Annual Slurry Seal $ 675,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Measure A Local Projects FY 2023-2024 $ 2,220,392
Fund 152 – Quimby Act
21-16 Demuth Dog Park $ 201,965
22-24 Pickleball Courts $ 575,000
Total Quimby Projects FY 2023-2024 $ 776,965
Fund 260 – Measure J
16-08 Main Library Remodel $ 2,921,400
18-10 Downtown Safety Bollards – Phase 2 $ 500,000
18-17 Police Department Impound Building $ 580,000
19-18 JC Frey Building Rehabilitation $ 870,000
19-23 Keyless Entry Phase 2 $ 468,750
19-24 Demuth Park ADA Access Phase 2 $ 1,000,000
19-25 Life Safety Improvements – Fire Sprinklers and Alarms $ 1,000,000
19-26 Emergency Generators at City Facilities $ 777,500
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 400,000
20-04 Sunrise Plaza HVAC Improvements – Chillers and Cooling Towers $ 500,000
22-08 Annual Pavement Rehabilitation $ 6,000,000
22-15 Convention Center Exhibit Hall Air Wall and Acoustic Tile Refurbish $ 450,000
22-17 Convention Center Marquee Upgrade $ 160,000
22-19 Relocate Fire Station #1 $ 3,600,000
10
CP# Project Title Budget
22-20 Measure J Community Initiated Projects $ 1,000,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
22-24 Pickleball Courts $ 575,000
Total Measure J Projects FY 2023-2024 $ 21,302,650
Fund 261 – Capital Projects
01-11 Indian Canyon Bridge Over UPRR $ 1,699,968
08-25 Ramon Road Bridge Over Whitewater River $ 9,829,653
10-10 Vista Chino Low Water Crossing $ 2,907,767
12-02 South Palm Canyon Over Tahquitz Creek $ 3,601,843
12-04 East Palm Canyon Bridge $ 5,180,776
16-08 Main Library Remodel $ 2,921,400
18-05 Hwy Safety Improvement Program (HSIP) Cycle 9 – Traffic Signals $ 232,236
18-17 Police Department Impound Building $ 580,000
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 200,000
20-07 Sunrise Plaza Domestic Waterline Separation $ 253,750
20-08 Fleet Operations HVAC and Electrical Upgrades $ 497,500
20-10 Sunrise Plaza Door and Window Replacements $ 524,150
20-21 Local Roads Safety Plan Recommended Projects $ 2,646,500
21-16 Demuth Dog Park $ 1,000,235
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Capital Projects FY 2023-2024 $ 32,575,778
Subtotal Non-Enterprise Project Funding for Year 2 - FY 2023-2024 $61,805,930
Enterprise Funds
Fund 420 – Wastewater
01-11 Indian Canyon Bridge Over UPRR - Sewer $ 3,000,000
21-04 WWTP General Sitework and Pavement Replacement $ 725,000
21-05 WWTP Sludge Drying Beds $ 706,000
21-06 WWTP Demolish Abandoned Headworks, Primary Clarifier, Sand Filter $ 1,842,750
21-08 WWTP Biosolids Dewatering Facilities $ 7,000,000
Total Wastewater Projects FY 2023-2024 $ 13,273,750
Subtotal of Enterprise Project Funding for Year 2 - FY 2023-2024 $ 13,273,750
Total of All Project Funding for Year 2 – FY 2023-2023 $75,079,680
11
Capital Improvement Program
Project Summary by Fund for Fiscal Year 2024-2025 (Year 3)
CP# Project Title Budget
Fund 133 – Gas Tax
22-02 Annual Slurry Seal $ 675,000
22-22 Annual Sign & Striping Replacements $ 300,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Gas Tax Projects FY 2024-2025 $ 1,225,000
Fund 134 – Measure A
08-25 Ramon Road Bridge Over Whitewater River $ 2,524,347
10-10 Vista Chino Low Water Crossing $ 4,299,605
22-02 Annual Slurry Seal $ 675,000
22-21 Pedestrian Master Plan Recommended Projects $ 500,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Measure A Projects FY 2024-2025 $ 8,248,952
Fund 260 – Measure J
18-10 Downtown Safety Bollards – Phase 2 $ 608,750
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 400,000
20-04 Sunrise Plaza HVAC Improvements – Chillers and Cooling Towers $ 696,500
22-08 Annual Pavement Rehabilitation $ 6,000,000
22-19 Relocate Fire Station #1 $ 9,000,000
22-20 Measure J Community Initiated Projects $ 1,050,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Measure J Projects FY 2024-2025 $ 18,205,250
Fund 261 – Capital Projects
08-25 Ramon Road Bridge Over Whitewater River $ 9,829,653
10-10 Vista Chino Low Water Crossing $ 33,831,739
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 200,000
20-21 Local Roads Safety Plan Recommended Projects $ 1,617,833
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Capital Projects FY 2024-2025 $ 45,979,225
Subtotal Non-Enterprise Project Funding for Year 3 - FY 2024-2025 $73,658,427
Enterprise Funds
Fund 420 – Wastewater
21-04 WWTP General Sitework and Pavement Replacement $ 725,000
21-08 WWTP Biosolids Dewatering Facilities $ 7,000,000
Total Wastewater Projects FY 2024-2025 $ 7,725,000
Subtotal of Enterprise Project Funding for Year 3 - FY 2024-2025 $ 7,725,000
12
Total of All Project Funding for Year 3 – FY 2024-2025 $81,383,427
Capital Improvement Program
Project Summary by Fund for Fiscal Year 2025-2026 (Year 4)
CP# Project Title Budget
Fund 133 – Gas Tax
22-02 Annual Slurry Seal $ 675,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Gas Tax Projects FY 2025-2026 $ 925,000
Fund 134 – Measure A
08-25 Ramon Road Bridge Over Whitewater River $ 2,524,347
10-10 Vista Chino Low Water Crossing $ 4,299,605
22-02 Annual Slurry Seal $ 675,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Measure A Projects FY 2025-2026 $ 8,248,952
Fund 260 – Measure J
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 400,000
22-08 Annual Pavement Rehabilitation $ 6,000,000
22-19 Relocate Fire Station #1 $ 9,000,000
22-20 Measure J Community Initiated Projects $ 1,000,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Measure J Projects FY 2025-2026 $ 16,900,000
Fund 261 – Capital Projects
08-25 Ramon Road Bridge Over Whitewater River $ 9,829,653
10-10 Vista Chino Low Water Crossing $ 33,831,739
20-03 Roundabout at Indian Canyon, South Palm Canyon, Camino Parocela $ 400,000
20-21 Local Roads Safety Plan Recommended Projects $ 1,617,833
22-21 Pedestrian Master Plan Recommended Projects $ 500,000
Total Capital Projects FY 2025-2026 $ 46,179,225
Subtotal Non-Enterprise Project Funding for Year 4 - FY 2025-2026 $72,253,177
Enterprise Funds
Fund 420 – Wastewater
21-08 WWTP Biosolids Dewatering Facilities $ 6,313,858
Total Wastewater Projects FY 2025-2026 $ 6,313,858
Subtotal of Enterprise Project Funding for Year 4 - FY 2025-2026 $ 6,313,858
Total of All Project Funding for Year 4 – FY 2025-2026 $78,567,035
13
Capital Improvement Program
Project Summary by Fund for Fiscal Year 2026-2027 (Year 5)
CP# Project Title Budget
Fund 133 – Gas Tax
22-02 Annual Slurry Seal $ 675,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Gas Tax Projects FY 2026-2027 $ 925,000
Fund 134 – Measure A
22-02 Annual Slurry Seal $ 675,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
22-23 Annual Traffic Calming Projects $ 250,000
Total Measure A Projects FY 2026-2027 $ 1,425,000
Fund 260 – Measure J
22-08 Annual Pavement Rehabilitation $ 6,000,000
22-20 Measure J Community Initiated Projects $ 1,000,000
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Measure J Projects FY 2026-2027 $ 7,500,000
Fund 261 – Capital Projects
20-21 Local Roads Safety Plan Recommended Projects $ 1,617,834
22-21 Pedestrian & Safe Routes to Schools Master Plan Recommended Projects $ 500,000
Total Capital Projects FY 2026-2027 $ 2,117,834
Subtotal Non-Enterprise Project Funding for Year 5 - FY 2026-2027 $11,967,834
Total of All Project Funding for Year 5 – FY 2026-2027 $11,967,834
Table of Projects and Accounts
Project #Project Title Fund Budgeted FY20-21 Available Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 Total
01-11 Indian Canyon Bridge Over UPRR 261 10,685,403.00$ 10,145,714.00$ 8,142,905.00$ 1,699,968.00$ -$ -$ -$ 19,988,587.00$
01-11 Indian Canyon Bridge Over UPRR 134R 3,512,908.00$ 3,246,262.00$ 3,074,340.00$ 641,820.00$ -$ -$ -$ 6,962,422.00$
01-11 Indian Canyon Bridge Over UPRR 134L 1,184,931.00$ 1,096,049.00$ 1,024,780.00$ 213,940.00$ -$ -$ -$ 2,334,769.00$
01-11 Indian Canyon Bridge Over UPRR 420 4,000,000.00$ 3,991,600.00$ 6,000,000.00$ 3,000,000.00$ -$ -$ -$ 12,991,600.00$
06-18 South Palm Canyon Bridge 261 955,308.00$ 848,594.00$ 4,600,506.00$ -$ -$ -$ -$ 5,449,100.00$
06-18 South Palm Canyon Bridge 134L 72,708.00$ 71,583.00$ 346,044.00$ -$ -$ -$ -$ 417,627.00$
06-18 South Palm Canyon Bridge 133 125,946.00$ 125,021.00$ -$ -$ -$ -$ -$ 125,021.00$
06-18 South Palm Canyon Bridge 001 290,840.00$ 149,327.00$ -$ -$ -$ -$ -$ 149,327.00$
08-25 Ramon Rd Over Whitewater River 261 555,899.00$ 449,751.00$ -$ 9,829,653.00$ 9,829,653.00$ 9,829,653.00$ -$ 29,938,710.00$
08-25 Ramon Rd Over Whitewater River 134R 404,093.00$ 295,933.00$ -$ 2,227,365.00$ 2,227,365.00$ 2,227,365.00$ -$ 6,978,028.00$
08-25 Ramon Rd Over Whitewater River 134L 172,209.00$ 139,448.00$ 100,000.00$ 296,982.00$ 296,982.00$ 296,982.00$ -$ 1,130,394.00$
10-10 Vista Chino Low Water Crossing 261 5,671,445.00$ 3,491,412.00$ 2,907,767.00$ 2,907,767.00$ 33,831,739.00$ 33,831,739.00$ -$ 76,970,424.00$
10-10 Vista Chino Low Water Crossing 134R 458,550.00$ 246,721.00$ 282,549.00$ 282,549.00$ 3,287,445.00$ 3,287,445.00$ -$ 7,386,709.00$
10-10 Vista Chino Low Water Crossing 134L 445,431.00$ 375,021.00$ -$ -$ 1,012,160.00$ 1,012,160.00$ -$ 2,399,341.00$
12-02 South Palm Canyon Over Tahquitz Creek 261 812,994.00$ 716,836.00$ 3,601,843.00$ 3,601,843.00$ -$ -$ -$ 7,920,522.00$
12-02 South Palm Canyon Over Tahquitz Creek 134R 257,750.00$ 248,399.00$ 349,993.00$ 349,993.00$ -$ -$ -$ 948,385.00$
12-02 South Palm Canyon Over Tahquitz Creek 134L 2,980.00$ -$ 116,664.00$ 116,664.00$ -$ -$ -$ 233,328.00$
12-04 E Palm Canyon Over Palm Canyon Wash 261 542,802.00$ 284,222.00$ 1,295,193.00$ 5,180,776.00$ -$ -$ -$ 6,760,191.00$
12-04 E Palm Canyon Over Palm Canyon Wash 134R 88,912.00$ 32,299.00$ 125,854.00$ 503,418.00$ -$ -$ -$ 661,571.00$
12-04 E Palm Canyon Over Palm Canyon Wash 134L 111,620.00$ 92,973.00$ 41,953.00$ 167,806.00$ -$ -$ -$ 302,732.00$
16-08 Main Library Renovation 260 -$ -$ 4,138,650.00$ 2,921,400.00$ -$ -$ -$ 7,060,050.00$
16-08 Main Library Renovation 261 -$ -$ 4,138,650.00$ 2,921,400.00$ -$ -$ -$ 7,060,050.00$
16-18 HSIP Cycle 8 Traffic Signal Modifications 261 2,199,341.00$ 2,117,242.00$ 550,000.00$ -$ -$ -$ -$ 2,667,242.00$
16-18 HSIP Cycle 8 Traffic Signal Modifications 142 117,871.00$ 116,383.00$ 1,088,536.00$ -$ -$ -$ -$ 1,204,919.00$
18-05 HSIP Cycle 9 Traffic Signal Modifications 261 71,264.56$ 14,082.93$ 1,399,200.00$ 232,236.00$ -$ -$ -$ 1,645,518.93$
18-06 Victoria and Ruth Hardy Park Restrooms Renovation 260 -$ -$ 950,000.00$ -$ -$ -$ -$ 950,000.00$
18-09 Fire Tower Training Facility 001 201,949.00$ 201,949.00$ -$ -$ -$ -$ -$ 201,949.00$
18-09 Fire Tower Training Facility 260 -$ -$ 750,000.00$ -$ -$ -$ -$ 750,000.00$
18-04 Plaza Theater 260 -$ -$ 1,000,000.00$ -$ -$ -$ -$ 1,000,000.00$
18-10 Downtown Safety Bollards Phase 2 260 -$ -$ -$ 500,000.00$ 608,750.00$ -$ -$ 1,108,750.00$
18-14 Gene Autry Windwall Upgrade 134L 59,985.00$ 9,336.00$ 2,020,000.00$ -$ -$ -$ -$ 2,029,336.00$
18-17 Police Department Impound Building 261 -$ -$ -$ 580,000.00$ -$ -$ -$ 580,000.00$
18-17 Police Department Impound Building 260 -$ -$ -$ 580,000.00$ -$ -$ -$ 580,000.00$
18-20 Skylight Railings 261 456,875.56$ 450,000.00$ 397,780.00$ -$ -$ -$ -$ 847,780.00$
19-15 Storm Drain Line 20 261 -$ -$ 7,520,000.00$ -$ -$ -$ -$ 7,520,000.00$
19-15 Storm Drain Line 20 135 467,444.00$ 340,840.00$ 810,000.00$ -$ -$ -$ -$ 1,150,840.00$
19-18 JC Frey Building Rehabilitation 260 -$ -$ -$ 870,000.00$ -$ -$ -$ 870,000.00$
19-23 Keyless Entry System Phase 2 260 -$ -$ 200,000.00$ 468,750.00$ -$ -$ -$ 668,750.00$
19-24 Demuth Park ADA Access Phase 2 260 -$ -$ 600,000.00$ 1,000,000.00$ -$ -$ -$ 1,600,000.00$
19-25 Life Safety Improvements - Fire Sprinklers and Alarms 260 -$ -$ 900,000.00$ 1,000,000.00$ -$ -$ -$ 1,900,000.00$
19-26 Emergency Generators at City Facilities 260 -$ -$ 600,000.00$ 777,500.00$ -$ -$ -$ 1,377,500.00$
19-27 City Water Treatment Program (HVAC)260 -$ -$ 507,500.00$ -$ -$ -$ -$ 507,500.00$
19-28 Recreation Fields LED Lighting Upgrades 260 94,219.00$ -$ 4,100,000.00$ -$ -$ -$ -$ 4,100,000.00$
14
Table of Projects and Accounts
Project #Project Title Fund Budgeted FY20-21 Available Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27 Total
20-03 Roundabout at Indian Canyon SPC Camino Parocela 260 210,300.00$ -$ 400,000.00$ 400,000.00$ 400,000.00$ 400,000.00$ -$ 1,600,000.00$
20-03 Roundabout at Indian Canyon SPC Camino Parocela 261 -$ -$ 200,000.00$ 200,000.00$ 200,000.00$ 400,000.00$ -$ 1,000,000.00$
20-04 Sunrise Plaza HVAC Improvements 260 -$ -$ 400,000.00$ 500,000.00$ 696,500.00$ -$ -$ 1,596,500.00$
20-06 City Hall and Police Department Electrical Upgrades 261 480,000.00$ 480,000.00$ 100,000.00$ -$ -$ -$ -$ 580,000.00$
20-07 Sunrise Plaza Domestic Water Line Separation 261 -$ -$ -$ 253,750.00$ -$ -$ -$ 253,750.00$
20-08 Fleet Operations HVAC and Electrical Improvements 261 100,000.00$ 100,000.00$ 200,000.00$ 497,500.00$ -$ -$ -$ 797,500.00$
20-10 Sunrise Plaza Door and Window Replacements 261 100,000.00$ 100,000.00$ 200,000.00$ 524,150.00$ -$ -$ -$ 824,150.00$
20-21 Local Road Safety Plan Projects 261 -$ -$ 500,000.00$ 2,646,500.00$ 1,617,833.00$ 1,617,833.00$ 1,617,834.00$ 8,000,000.00$
21-04 WWTP General Sitework and Pavement Replacement 420 -$ -$ 150,000.00$ 725,000.00$ 725,000.00$ -$ -$ 1,600,000.00$
21-05 WWTP Sludge Drying Beds 420 429,898.00$ 225,254.00$ 706,000.00$ 706,000.00$ -$ -$ -$ 1,637,254.00$
21-06 WWTP Demolition of Abandoned Equipment 420 -$ -$ 1,842,750.00$ 1,842,750.00$ -$ -$ -$ 3,685,500.00$
21-08 WWTP Biosolids Dewatering Facility 420 4,999,959.00$ 2,029,867.00$ 2,000,000.00$ 7,000,000.00$ 7,000,000.00$ 6,313,858.00$ -$ 24,343,725.00$
21-10 Traffic Operation Center Communication Upgrades 134L 18,184.00$ 1,158.00$ 500,000.00$ -$ -$ -$ -$ 501,158.00$
21-16 Demuth Dog Park 152 1,448,270.00$ 1,448,270.00$ -$ 201,965.00$ -$ -$ -$ 1,650,235.00$
21-16 Demuth Dog Park 260 -$ -$ -$ -$ -$ -$ -$ -$
21-16 Demuth Dog Park 261 650,000.00$ 650,000.00$ -$ 1,000,235.00$ -$ -$ -$ 1,650,235.00$
21-17 Arnico Tract Sewer - Phase 4 260 585,000.00$ -$ 200,000.00$ -$ -$ -$ -$ 200,000.00$
22-02 Annual Slurry Seal 133 877,368.00$ -$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 3,375,000.00$
22-02 Annual Slurry Seal 134L 206,463.00$ -$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 675,000.00$ 3,375,000.00$
22-08 Annual Pavement Rehabilitation 260 8,998,293.00$ 3,017,493.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 6,000,000.00$ 33,017,493.00$
22-14 Convention Center Exhibit Hall and Primrose Carpet Replacement 260 -$ -$ 650,000.00$ -$ -$ -$ -$ 650,000.00$
22-15 Exhibit Hall Air Wall and Acoustical Tile Refurbish 260 -$ -$ -$ 450,000.00$ -$ -$ -$ 450,000.00$
22-16 Convention Center Jackie Lee Houston Plaza Upgrades 260 -$ -$ 100,000.00$ -$ -$ -$ -$ 100,000.00$
22-17 Convention Center Marquee Upgrade 260 -$ -$ -$ 160,000.00$ -$ -$ -$ 160,000.00$
22-18 Palm Springs Convention Center Retrofit Lighting Controls 260 -$ -$ 500,000.00$ -$ -$ -$ -$ 500,000.00$
22-19 Relocate Fire Station 1 260 -$ -$ 1,600,000.00$ 3,600,000.00$ 9,000,000.00$ 9,000,000.00$ -$ 23,200,000.00$
22-20 Measure J Community Initiated Projects 260 -$ -$ 3,000,000.00$ 1,000,000.00$ 1,000,000.00$ 1,000,000.00$ 1,000,000.00$ 7,000,000.00$
22-21 Pedestrian Master Plan Recommended Projects 261 -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$
22-21 Pedestrian Master Plan Recommended Projects 134L -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$
22-21 Pedestrian Master Plan Recommended Projects 260 -$ -$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 500,000.00$ 2,500,000.00$
22-22 Citywide Sign and Striping Inventory and Replacement Program 133 -$ -$ 300,000.00$ -$ 300,000.00$ -$ -$ 600,000.00$
22-23 Annual Traffic Calming Projects 133 -$ -$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 1,250,000.00$
22-23 Annual Traffic Calming Projects 134L -$ -$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 250,000.00$ 1,250,000.00$
22-24 Pickleball Courts 152 -$ -$ 150,000.00$ 575,000.00$ -$ -$ -$ 725,000.00$
22-24 Pickleball Courts 260 -$ -$ 150,000.00$ 575,000.00$ -$ -$ -$ 725,000.00$
22-25 Playground Equipment Shade Structures 137 -$ -$ 281,960.00$ -$ -$ -$ -$ 281,960.00$
22-26 San Rafael Turf Conversion 260 -$ -$ 150,000.00$ -$ -$ -$ -$ 150,000.00$
Totals 53,125,413.12$ 37,349,039.93$ 87,311,417.00$ 75,079,680.00$ 81,383,427.00$ 78,567,035.00$ 11,967,834.00$ 371,658,432.93$
15
CityofPalmSprings,CA2021/22StrategicPlanThefollowingStrategicPlanisdesignedtoguidehighpriorityworkforthenext1Ͳ3years.Whiletheseprioritiesarecomprehensive,theyarenotexhaustive.Prioritiesarecapturedatahighconceptuallevel.Moredetailedworkplanswillbecreatedtohelpturnhighlevelprioritiesintooperationallevelplans.Mission:PalmSpringsisaninclusive,worldclasscitydedicatedtoprovidingexcellentandresponsivepublicservicestoenhancethequalityoflifeforcurrentandfuturegenerationsMajorThemes/Principles:OptimizebasicservicesandfacilitiesFocusonissuesthatmostimpactqualityoflifeNarrowprioritiestofocusonmostimportantissuesfirstPrioritiesshouldbeintegratedwhenpossibletomaximizeimpactSocialequityandsustainabilityunpinallpriorities,programs,andprojects16
1ͲQualityofLife2–EnvironmentalStewardship3–CommunityInfrastructure4–GoodGovernance1AͲImproveHomelessnessͲ BuildanavigationcenterͲ CoordinateserviceprovidersͲ Improvesecurity/maintenanceͲ Expandhomelessresponseteam2AͲAccelerateClimateActionPlanͲ BudgetfortwoadditionalFTEͲ CompleteGHGanalysisͲ Targethighvalueprojects/initiatives3AͲImproveCityFacilitiesͲ ExpandbudgetformaintenanceͲ FocusonparksandcommunityfacilitiesͲ Prioritizedeferredmaintenance4AͲEnhanceServiceLevelsͲ Evaluate/adjuststaffinglevelsͲ CreatetrainingprogramsͲ ImplementemployeeengagementopportunitiesͲ UpdateHRpolicies1BͲReduceCrimeͲ Evaluatestaffing/servicelevelsͲ ImplementneighborhoodpolicingmodelͲ FocusonviolentcrimeͲ Educateresidentsonpreventingpropertycrime2BͲConsiderNewPoliciesͲ Implement1383Ͳ DesertCommunityEnergyͲ CommercialrenewableenergystandardsͲ CommunitycompostingͲ Clarifylandconservationgoals3B–5ͲYearCapitalImprovementPlanͲ Expandwalking/bikinginfrastructureͲ IdentifyhighpriorityfacilitiesͲ FocusonparksandcommunityassetsͲ Acceleratestreetpaving4BͲImproveCommunicationsͲ ExpandcommunicationstaffͲ ImproveSpanishlanguagecommunicationsͲ Createstrategicfocus1CͲExpandHousingAffordabilityͲ CreatehousingplanͲ ExpandhousingpoliciesͲ PursuenewaffordablehousingdevelopmentsͲ ExpandstaffingͲ Buildhousingprograms2CͲDevelopInternalPolicies/PracticesͲ IntegrateSustainabilitywithotherdepartments/initiativesͲ Creategreenpurchasingpolicies3CͲCommunityDesignͲ CompleteGeneralPlanupdateͲ UpdatezoningcodeͲ Updatedesignstandards4CͲRemoveBarrierstoParticipationͲ AdjustCouncilsalaryͲ AddvehicleallowanceͲ AddresschildcareneedsͲ Createrecognitionprogram1DͲAdvanceEconomicDevelopmentͲ LobbyforwestvalleyCollegeoftheDesertCampusͲ Monitorbroadbandopportunities4DͲImproveFinancialManagementͲ ClarifybudgetprocessͲ Createassetmanagementprogram1EͲNeighborhoodIssuesͲ ReviewShortͲTermVacationRentalProgramͲ CreateSection14reparationsprogram17
DETAILED
PROJECT
INFORMATION
SHEETS
DETAILED
PROJECT
INFORMATION
SHEETS
PROJECT NO.
01-11
Project Title: Indian Canyon Widening over UPRR, Federal Project Number 5282(017)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Partially Funded
Location: Indian Canyon Drive over the Union Pacific Railroad from Garnet to Train Station Road.
Project Description: Widening of the bridge over the Union Pacific Railroad tracks will correspond with the 6-lane roadway constructed
from Garnet Avenue to Interstate-10
Project Justification: This is a missing link to allow for 6-lane roadway matching what Caltrans built for the I-10/Indian Canyon
interchange.
General Plan Conformance: Circulation Element – Policy CR2.5: Construct all-weather bridge crossings along Indian Canyon Drive,
Gene Autry Trail, and Vista Chino and the Whitewater River to reduce traffic problems caused by flooding and blowsand.
Project Cost Estimate:
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261-Capital Projects $10,685.403 $10,145,714 $8,142,905 1,699,968
134-Regional Measure A $3,512,908 $3,246,262 $3,074,340 $641,820
134-Local Measure A $1,184,931 $ 1,096,049 $1,024,780 $213,940
Federal STBG $48,667 $48,667 $48,667 $48,667
Federal Earmark $17,432 $17,432 $17,432 $17,432
420-Wasterwaterfund $4,000,000 $3,991,600 $6,000,000 $3,000,000
Total: $8,774,623 $18,545,724 $18,308,124* $5,621,827*
Construction: $21,000,000
Construction Contingency (10%): $2,100,000
Right of Way $1,634,000
Engineering and/or Design: $2,000,000
Construction Management (15%): $3,150,000
South Sewer Extension (CON) $13,000,000
Total Cost Estimate: $42,884,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
01-11
Notes:
Caltrans Funding Summary: Project Cost: HBP Funds STBG Funds Earmark Measure A Sewer fund
Preliminary Engineering (PE) $ 2,000,000 $ 253,991 $31,000 $ 1,715,009
Right of Way (R/W) $ 1,634,000 $ 1,381,952 $ 252,048
Construction (CON) $26,250,000 $19,877,641 $146,000 $52,296 $10,006,359
South Sewer Extension (CON) $ 13,000,000 $0 $0 $0 $13,000,000
Total Cost Estimate: $42,884,000 $21,513,584 $177,000 $52,296 $11,973,416 $13,000,000
Outside Sources of Revenue:
• * - Used Dokken Cash Flow Projection dated 2020-0720 and adjusted to 2021-1-29 estimate (assumed start date of July 2021)
• **- $655,025 available balance to be used for SCE Utility Relocation FY 20-21
• Highway Bridge Program (HBP) only $19,877,641 available
o Preliminary Engineering (PE) Participation Rate = 80% Federal, 20% Local Match
o Right of Way (R/W) Participation Rate = 88.53% Federal, 11.47% Local Match
o Construction (CON) Participation Rate = 88.53% Federal, 11.47% Local Match
• Coachella Valley Association of Governments (CVAG) will cover Local Match at the following percentages:
o Regional Measure A 75%, City of Palm Springs 25%
• Surface Transportation Block Grant (STBG)
• Repurposed Federal Earmarks from the Cultural Center
• Sewer Line Extension to be funded by wastewater fund
PROJECT NO.
06-18
Project Title: South Palm Canyon Drive Bridge Widening, Federal Project Number NBIL(502)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: South Palm Canyon Drive from Murray Canyon to Bogert Trail
Project Description: Bridge widening includes construction of a new bridge and drainage improvements at Arenas Canyon South
drainage channel.
Project Justification: Eliminate flooded roadway with a 4 lane bridge on South Palm Canyon Drive
General Plan Conformance: Safety Element – Goal SA3: Reduce, to the greatest extent possible, the risk to life, property, and essential
facilities from flooding and other hydrological hazards within the City.
Project Cost Estimate:
Construction: $4,157,000
Construction Contingency (10%): $416,000
Administration (5%): $200,000
Engineering and/or Design (15%): $950,000
Construction Management (15%): $623,550
Total Cost Estimate: $6,346,550
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
133 Special Gas Tax $125,946 $125,021
261 Capital Projects $955,308 $848,594 $4,600,506
134 Measure A Local $72,708 $71,583 $346,044
001 General Fund 1003055-70000 $ 290,840 $ 149,327
Total: $1,444,802 $1,194,525 $4,946,550
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
06-18
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Match
Preliminary Engineering (PE) $950,000 $496,749 $453,251
Right of Way (R/W) $200,000 $101,034 $98,966
Construction (CON) $5,196,550 $4,600,506* $596,044
Other (OTH)
Total Cost Estimate: $6,346,550 $5,198,289 $1,148,261
Outside Sources of Revenue (if any):
• * Assumes Project is advertised after July 1, 2023
• Federal Funds – Highway Bridge Program
• Coachella Valley Association of Governments
PROJECT NO.
08-25
Project Title: Ramon Road over Whitewater River, 0.8 MI E/O Gene Autry Tr, Fed Project Number 5282(040)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: Ramon Road Bridge, 0.8 miles East of Gene Autry Trail.
Project Description: Widen 4-lane bridge to 6-lane bridge, seismic retrofit as necessary, scour countermeasures.
Project Justification: The existing street is six lanes on either side of the bridge. The four-lane bridge is a bottleneck. There is no
pedestrian sidewalk on the north side of the bridge.
General Plan Conformance: Circulation Element – Goal CR1: Establish and maintain an efficient, interconnected circulation system
that accommodates vehicular travel, walking, bicycling, public transit, and other forms of transportation.
Project Cost Estimate:
Construction: $29,650,000
Construction Contingency (10%): $ 2,965,000
Administration (5%): $ 3,728,000
Engineering and/or Design (15%): $ 3,865,000
Construction Management (15%): $ 4,447,000
Total Cost Estimate: $44,655,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261-Capital Projects $555,899 $449,751 $ 9,829,653 $ 9,829,653 $ 9,829,653
134-Measure A Reg $404,093 $295,933 $ 2,227,365 $ 2,227,365 $ 2,227,365
134-Measure A Loc $172,209 $139,448 $100,000 $ 296,982 $ 296,982 $ 296,982
Total: $1,132,201 $885,132 $100,000 $12,354,000 $12,354,000 $12,354,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
08-25
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Match
Preliminary Engineering (PE) $ 3,865,000 $ 2,815,652 $1,049,348
Right of Way (R/W) $ 3,728,000 $ 1,605,934 $2,122,066
Construction (CON) $37,062,000 $28,152,540 $8,909,460
Other (OTH)
Total Cost Estimate $44,655,000 $32,574,126 $12,090,874
Outside Sources of Revenue (if any):
• * Assumes Project is advertised after July 1, 2025
• Federal Funds – Highway Bridge Program
• Coachella Valley Association of Governments
• City of Cathedral City
PROJECT NO.
10-10
Project Title: Vista Chino over Whitewater River, Bridge No. 00L0052, Federal Project Number NBIL(513)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Desireable (start within 3 to 5 yrs) Partially Funded
Location: Vista Chino at Whitewater Channel
Project Description: Replace existing 4 lane roadway with a new 4 lane bridge. High cost bridge project agreement required.
Project Justification: Eliminate frequent road closures due to flooding and sand buildup on windy days.
General Plan Conformance: Circulation Element – Policy CR2.5: Construct all-weather bridge crossings along Indian Canyon Drive,
Gene Autry Trail, and Vista Chino and the Whitewater River to reduce traffic problems caused by flooding and blowsand.
Project Cost Estimate:
Construction: $56,615,000
Construction Contingency (10%): $11,323,000
Administration (5%): $8,880,000
Engineering and/or Design (15%): $9,690,000
Construction Management (15%): $8,492,000
Total Cost Estimate: $95,000,000
Funding:
Fund Account
Number
Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $5,671,445 $3,491,412 $2,907,767 $2,907,767 $ 33,831,739.50 $33,831,739.50
134 Measure A Reg $458,550 $246,721 $282,549 $282,549 $ 3,287,445.38 $ 3,287,445.38
134 Measure A Loc $445,431 $375,021 $ 1,012,160.13 $ 1,012,160.13
Total: $6,575,426 $4,113,154 $3,190,316 $3,190,316 $38,131,345 $38,131,345
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
10-10
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Match
Preliminary Engineering (PE) $9,690,000 $8,578,557 $1,111,443
Right of Way (R/W) $8,880,000 $7,861,464 $1,018,536
Construction (CON) $76,430,000 $67,663,479 $8,766,521
Other (OTH)
Total Cost Estimate: $95,000,000 $84,103,500 $10,896,500
Outside Sources of Revenue (if any):
• * Assumes Project is advertised after July 1, 2025
• Federal Funds – Highway Bridge Program
• Coachella Valley Association of Governments
PROJECT NO.
12-02
Project Title: South Palm Canyon Drive Over Tahquitz Creek Channel, Federal Project Number 5282(042)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: South Palm Canyon Drive, 0.4 miles South of Ramon Road
Project Description: Replace 4 lane bridge with a new, wider 4 lane bridge.
Project Justification: The new bridge will have proper lane widths and sidewalks for pedestrians and bicyclists.
General Plan Conformance: Circulation Element – Goal CR1: Establish and maintain an efficient, interconnected circulation system
that accommodates vehicular travel, walking, bicycling, public transit, and other forms of transportation.
Project Cost Estimate:
Construction: $6,509,600
Construction Contingency (10%): $650,960
Administration (5%): $840,000
Engineering and/or Design (15%): $1,600,000
Construction Management (15%): $976,440
Total Cost Estimate: $10,577,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $812,994 $716,836 $3,601,843 $3,601,843
134 Measure A Reg $257,750 $248,399 $349,993 $349,993
134 Measure A Local $2,980 $116,664 $116,664
Total: $1,073,724 $965,235 $4,068,500 $4,068,500
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
12-02
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Match
Preliminary Engineering (PE) $1,600,000 $1,416,480 $183,520
Right of Way (R/W) $840,000 $743,652 $96,348
Construction (CON) $8,137,000 $7,203,686 $933,314
Other (OTH)
Total Cost Estimate $10,577,000 $9,363,818 $1,213,182
Outside Sources of Revenue (if any):
• * Assumes Project is advertised after July 1, 2023
• Federal Funds – Highway Bridge Program
• Coachella Valley Association of Governments
PROJECT NO.
12-04
Project Title: E. Palm Canyon Drive over Palm Canyon Wash, Federal Project Number: 5282(041)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Bridge Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: East Palm Canyon Drive, 0.5 miles East of Farrell Drive
Project Description: Bridge rehabilitation project, to widen 4 lane bridge to add shoulders and sidewalks.
Project Justification: No shoulders and sidewalks along the bridge. Pedestrian bridge on north side, but nothing for south side.
General Plan Conformance: Circulation Element – Goal CR1: Establish and maintain an efficient, interconnected circulation system
that accommodates vehicular travel, walking, bicycling, public transit, and other forms of transportation.
Project Cost Estimate:
Construction: $5,862,000
Construction Contingency (10%): $ 581,200
Administration (5%): $ 580,000
Engineering and/or Design (15%): $1,428,000
Construction Management (15%): $ 871,800
Total Cost Estimate: $9,323,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $542,802 $284,222 $1,295,193 $5,180,776
134 Measure A Reg $88,912 $32,299 $125,854 $503,418
134 Measure A Local $111,620 $92,973 $41,953 $167,806
Total: $743,334 $409,494 $1,463,000 $5,852,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
12-04
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Match
Preliminary Engineering (PE) $1,428,000* $1,149,120 $278,880
Right of Way (R/W) $ 580,000 $442,650 $137,350
Construction (CON) $7,315,000 $6,475,969 $839,030
Other (OTH)
Total Cost Estimate: $9,323,000 $8,067,740 $1,255,261
• Assumes project to be advertised after July 1, 2024.
• *Total Includes non-participating cost
• ** Assumes offsetting budget adjustments for new R/W funds ($580K) and additional PE funds ($408K)
• 6D for additional PE funds ($408k) submitted 1-2021
• SB1-RMMA funds to be use toward traffic signal
PROJECT NO.
16-08
Project Title: Main Library Remodel
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Library Funding Status:
Project Status: On Hold Project Priority: Essential (start within 1 yr) Unfunded
Location: Palm Springs Public Library, 300 S. Sunrise Way
Project Description: Renovate the existing Main Public Library. Renovations planned to address significant building systems upgrades
along with interior renovations to support a new library service model.
Project Justification: Library is in need of updates to serve the community better.
General Plan Conformance: Land Use Element – Actions LU5.2: Allow for the development of new public educational facilities in
areas designated for residential or parks and recreational use.
Project Cost Estimate:
Construction: $9,738,000
Construction Contingency (10%): $973,800
Administration (10%): $973,800
Engineering and/or Design (15%): $1,460,700
Construction Management (10%): $973,800
Total Cost Estimate: $14,120,100
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Grant $4,138,650 $2,921,400
260 Measure J $4,138,650 $2,921,400
Total: $8,277,300 $5,842,800
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
16-08
Notes:
The City applied for a State Building Forward: Library Infrastructure Grant. The State of California Budget Act of 2021 (SB129, Chapter
69, Statutes of 2021) allocated $439 million in one-time funds to the California State Library to address life safety and critical maintenance
needs of public library facilities throughout California. This grant program “prioritizes funding for local libraries located in high poverty
areas of the state”. If funding is available, other library infrastructure projects may be considered. The maximum grant amount per library
facility is $10 million. Funds must be expended by March 31, 2026. Match Requirements - A dollar-for-dollar match is required. Applicants
may request a reduction in the required match based on certain conditions.
LIFE SAFETY PROJECTS COST ESTIMATE
Furnish and Install Fire Sprinkler System $200,000
Fire Alarm System Control Panel $15,000
Emergency Egress Hardware (doors with panic hardware for all exterior doors) $251,000
Emergency Egress Light, Power Systems (emergency lights, emergency exit signs, strobes) $156,000
Ceiling Finishes - Acoustic Tile T-bar system, needs to be replaced for new sprinklers $340,000
Air Filtration System $15,000
Security System - CCTV and Burgler Alarm System $130,000
Emegency Backup Generator $250,000
Skylights - Railings and fall protection anchor points $100,000
Subtotal Life Safety Projects $1,457,000
CRITICAL MAINTENANCE AND CRITICAL INFRASTRUCTURE PROJECTS
HVAC Replacement - Chiller and Cooling Tower replacement $430,000
HVAC Replacement - Distribution System - Exhaust system $90,000
HVAC Replacement - Distribution System - Central AHU Unit only $392,000
HVAC Replacement - Distribution System - Chilled Water Distribution Pipes $400,000
HVAC Replacement - Distribution System - Hydronic Heating Distribution Pipes $390,000
HVAC Replacement - Distribution System - ductwork $1,500,000
HVAC Terminal and Package Units - Split DX w/Air Cooled Remote Condenser $30,000
PROJECT NO.
16-08
Electrical Service $1,400,000
Seismic Retrofit $400,000
Inclusive Access - ADA $814,000
Roof Replacement $600,000
Window replacements $450,000
Replace water lines - includes associated plumbing $400,000
Subtotal Critical Maintenance Critical Infrastructure Projects $7,296,000
NON-CRITICAL BUT ELIGIBLE PROJECTS
Painting $120,000
Replace Signage, ADA tactile, larger fonts for visually impaired, $15,000
Replace non-emergency lighting $300,000
Replace Carpet and/or floors $100,000
Replace interior doors and locks $450,000
Subtotal Non-Critical but Eligible Projects $985,000
Subtotal All Projects $9,738,000
10% Project Contingency $973,800
10% Project Administration $973,800
15% Design Consultants $1,460,700
10% Construction Management $973,800
Total Projects $14,120,100
Activity Month/Year Started Month/Year Completed
Hire Consultant for Architectural Services. Jul-22 Sep-22
Hire Consultant for Seismic Evaluation of the Building Jul-22 Sep-22
Design Fire Sprinkler System, HVAC, MEP (Mechanical, Electrical, Plumbing), CCTV
Security System, Structural Engineer Oct-22 Jul-23
PROJECT NO.
16-08
Put project out to bid Aug-23 Sep-23
Award Construction Contract Oct-23 Oct-23
Construction Nov-23 Jul-25
Project Closeout Jul-25 Dec-25
PROJECT NO.
16-18
Project Title: HSIP Cycle 8 Traffic Signal Modifications Federal Project Number 5282(047)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Expand Walking/Biking Infrastructure
Type: Traffic Signals Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Funded
Location: 14 intersections in the City. N Palm Canyon/San Rafael, N Indian Canyon/San Rafael, N Indian Canyon/Vista Chino, E
Vista Chino/Sunrise, E Vista Chino/Gene Autry Trail, E Vista Chino, Clubhouse View, N Indian Canyon/Tachevah, S Palm
Canyon/Ramon, Ramon/Farrell, Ramon/Vella-Kirk Douglas, Ramon/Gene Autry Trail, Ramon/San Luis Ray Dr, S Palm
Canyon/Mesquite, Dinah Shore/Gene Autry Trail.
Project Description: Modify the traffic signals at 14 intersections.
Project Justification: Modify the traffic signals at 14 intersections for improved visibility, install advanced dilemma zone detection for
high speed approaches, and add protected left-turn phasing.
General Plan Conformance: Circulation Element – Actions CR2.2: Upgrade and maintain traffic signal-interconnect systems to
efficiently coordinate and control traffic flow on arterial streets, including the installation or removal of separate left-turn phasing
where warranted. Traffic signal timing should adequately provide for safe pedestrian crossing.
Project Cost Estimate:
Construction: $3,100,000
Construction Contingency (10%): $ 310,000
Administration (5%): $ 155,000
Engineering and/or Design (15%): $ 479,700
Construction Management (15%): $ 287,800
Total Cost Estimate: $4,350,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $2,199,341 $2,117,242 $550,000
142 SB1 $117,871 $116,383 $1,088,536
Total: $2,317,212 $2,233,625 $1,638,536
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
16-18
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Funds
Preliminary Engineering (PE) $479,700 $479,700 $0
Right of Way (R/W)
Construction (CON) $3,870,800 $2,206,900 $1,663,900
Other (OTH)
Total Cost Estimate: $4,350,500 $2,686,600 $1,663,900
PROJECT NO.
18-04
Project Title: Plaza Theater
Council Priority: Community Infrastructure (3A) Improve City Facilities
Type: Building/Facility Department: Engineering Services Funding Status:
Project Status: New Project Priority: Desireable (start within 3 to 5 yrs) Partially Funded
Location: Plaza Theater
Project Description: Renovate Historical Building
Project Justification: Aging City infrastructure - funding by donations
General Plan Conformance: Land Use Element – Policy LU10.8: Maintain the Plaza Theatre for use as a multipurpose community
performing arts center for film festivals, premieres, and live stage productions, while preserving its historical value.
Project Cost Estimate:
Construction: $10,000,000
Construction Contingency (10%): $ 1,000,000
Administration (5%): $ 500,000
Engineering and/or Design (10%): $ 1,000,000
Construction Management (15%): $ 1,500,000
Total Cost Estimate: $13,500,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $1,000,000
Donations $12,500,000
Total: $13,500,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-04
Notes: Cost is based on a 2018 report from Gensler.
PROJECT NO.
18-05
Project Title: HSIP9 Traffic Signal Modifications at 9 Intersections Federal Project Number 5282(049)
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Expand Walking/Biking Infrastructure
Type: Traffic Signals Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: Located at 9 intersections throughout the City: Tahquitz Canyon Way / Calle Encilia, E. Palm Canyon Drive / Araby Drive,
Ramon Road / Avenida Caballeros, Ramon Road / Compadre Road, Farrell Drive/Via Escuela, Sunrise Way / Tachevah Drive,
Farrell Drive / Alejo Road, Indian Canyon Drive / 20th Avenue, Sunrise Way / Alejo Road
Project Description: Improve traffic signals at 9 intersections with the latest in traffic safety equipment, including the installation of
advanced dilemma zone detection and upgrading of ADA curb ramps
Project Justification: The Advanced Dilemma Zone Detection will reduce rear end collisions associated with unsafe stopping and
broadside collisions. The proposed pedestrian countdown signal heads could reduce pedestrian and bicycle collisions at the
intersections.
General Plan Conformance: Circulation Element – Actions CR2.2: Upgrade and maintain traffic signal-interconnect systems to efficiently
coordinate and control traffic flow on arterial streets, including the installation or removal of separate left-turn phasing where
warranted. Traffic signal timing should adequately provide for safe pedestrian crossing.
Project Cost Estimate:
Construction: $1,058,000
Construction Contingency (10%): $ 158,700
Administration (5%):
Engineering and/or Design (15%): $ 303,500
Construction Management (15%): $ 182,500
Total Cost Estimate: $1,702,700
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $71,264 $14,083 $1,399,200 $232,236
Total: $71,264 $14,083 $1,399,200 $232,236
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-05
Notes:
Caltrans Funding Summary: Project Cost: Federal Funds Local Cost:
Preliminary Engineering (PE) $ 303,500 $ 303,500 $0
Right of Way (R/W) $0 $0 $0
Construction (CON) $1,399,200 $1,399,200 $0
Other (OTH)
Total Cost Estimate: $1,702,700 $1,702,000 $0
PROJECT NO.
18-06
Project Title: Park Restroom Victoria and Ruth Hardy
Council Priority: Community Infrastructure (3A) Improve City Facilities Focus on Parks and Community Assets
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Unfunded
Location: Victoria, Ruth Hardy Parks.
Project Description: This project will upgrade the plumbing and electrical facilities inside City owned parks. Based on Engineering
and Architectural review, the project may reconstruct the restroom rather than upgrade. Alternatively, we will review the ability to
construct new restrooms at these locations.
Project Justification: Current restrooms are in need of renovation.
General Plan Conformance: Recreation, Open Space & Conservation Element – Policy RC2.5: Ensure that parks and recreational
facilities are fully accessible to people of all ages and abilities, including people with disabilities.
Project Cost Estimate:
Construction: $703,500
Construction Contingency (10%): $70,350
Administration (5%): $35,175
Engineering and/or Design (15%): $35,175
Construction Management (15%): $105,800
Total Cost Estimate: $950,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $950,000
Total: $950,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-06
Notes:
City Council approved $1,600,000 for park restroom improvements as a part of the budget for FY19-20. Of that $150,000 needs to go to
Sunrise Park Restrooms CP19-13 ($50,000 from CDBG).
Restrooms at Demuth Park is part of CP19-24 Demuth Park ADA Upgrades Phase 2; there are 4 restroom locations. Approved
$175,552 in CDBG funds (July 9, 2020 Staff Report Item 2A) for the restrooms near the Pickleball Courts/Playground area.
On September 24, 2020 (Video Item 5C), as a part of the PowerPoint slide for the budget update they recommended for direction to
appropriate $250,000 of Quimby Funds for the restrooms at JOJDHUC.
Sunrise Park Restrooms are being done with project 19-13, Demuth Park restrooms are being done with project 19-24.
PROJECT NO.
18-09
Project Title: Fire Tower Training Facility
Council Priority:
Type: Building/Facility Department: Fire Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: 3000 E. Alejo Rd. behind the Fire Department Training Center
Project Description: Design of a Fire Tower Training Facility at a Palm Springs International Airport property adjacent to the existing
training facility.
Project Justification: Currently there is nowhere in the City of Palm Springs to train new and existing staff. The FD has been traveling
far distances for such training and the availability of those locations are limited.
General Plan Conformance: Safety Element – Policy SA7.7: Maintain adequate fire training facilities, equipment, and programs for
firefighting and inspection personnel and educational programs for the general public, including fire safety and prevention and
emergency medical information.
Project Cost Estimate:
Construction: $655,000
Construction Contingency (10%): $65,500
Administration (5%): $65,500
Engineering and/or Design (15%): $98,250
Construction Management (15%): $98,500
Total Cost Estimate: $950,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
001 General Fund $201,949
260 Measure J $750,000
Total: $201,949 $750,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-09
Notes:
Outside Sources of Revenue:
The Fire Department has secured funding of $76,000 donated from the Agua Caliente Band of Cahuilla Indians, $20,000 donated from
the Matthew Dragicevich Charitable Trust, and up to $154,000 can be acquired through a California Firefighter Joint Apprenticeship
Committee (Cal-JAC) reimbursement.
PROJECT NO.
18-10
Project Title: Downtown Safety Bollards – Phase 2
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Expand Walking/Biking Infrastructure
Type: Other Department: Engineering Services Funding Status:
Project Status: New Project Priority: Desireable (start within 3 to 5 yrs) Unfunded
Location: Downtown Palm Springs around VillageFest. At Andreas, Taquitz Canyon, Baristo and Arenas
Project Description: Phase 2 to install permanent retractable bollards on South Palm Canyon at Andreas, Tahquitz, Baristo, & Arenas
Project Justification: This project will replace the water filled k-rails used every Thursday night for Village Fest, with permanent
retractable bollards. This provides a physical separation between vehicles and pedestrians, and will protect the public health and
safety of all those who attend Village Fest. This second phase expands the location of new security bollard installations from the
original installation.
General Plan Conformance: Community Design Element – Policy CD30.2: Integrate streetscape improvements, landscaping, and
signage that uniquely identify the Downtown area as the principal commercial activity center of the City.
Project Cost Estimate:
Construction: $750,000
Construction Contingency (10%): $75,000
Administration (5%): $37,500
Engineering and/or Design (15%): $112,500
Construction Management (15%): $112,500
Total Cost Estimate: $1,087,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $500,000 $608,750
Total: $500,000 $608,750
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-10
Notes:
PROJECT NO.
18-14
Project Title: Gene Autry Windwall Upgrade
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Unfunded
Location: On Gene Autry Trail, approximately 900 feet south of Salvia Road (starting point)
Project Description: Design of a permanent CMU Windwall structure with a concrete barrier and cable median.
Project Justification: Sand typically builds up several feet on the west side of the bridge, leading to constant lane closures.
General Plan Conformance: Air Quality Element – Policy AQ2.3: Reduce the transport of blowsand adjacent to paved roadways and
residential areas through the use of chemically stabilizing soil surfaces or snow fence windbreaks. Chemical stabilizing
measures should only be used in areas where they will not impact endangered habitats or species.
Project Cost Estimate:
Construction: $1,500,000
Construction Contingency (10%): $150,000
Administration (5%): $60,000
Engineering and/or Design (15%): $110,000
Construction Management (15%): $200,000
Total Cost Estimate: $2,020,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
134 Measure A $59,985 $9,336 $2,020,000
Total: $59,985 $9,336 $2,020,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-14
Notes:
PROJECT NO.
18-17
Project Title: Police Department Impound Building
Council Priority:
Type: Building/Facility Department: Police Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: At City Yard
Project Description: This project will construct an enclosed and secure structure to hold impounded vehicles.
Project Justification: The PS Police Department needs an enclosed and secure structure to hold impounded vehicles. The structure
would need to be protected from the elements and able to secure vehicles for evidentiary integrity. The current fenced in
impound lot is exposed to the elements and protected only by a chain link fence.
General Plan Conformance: Safety Element – Policy SA7.1: Maintain adequate resources to enable the Police Department to meet
response-time standards, keep pace with growth, and provide high levels of service.
Project Cost Estimate:
Construction: $800,000
Construction Contingency (10%): $80,000
Administration (5%): $40,000
Engineering and/or Design (15%): $120,000
Construction Management (15%): $120,000
Total Cost Estimate: $1,160,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Fund $580,000
260 Measure J $580,000
Total: $1,160,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-17
Notes:
PROJECT NO.
18-20
Project Title: Skylight Railings
Council Priority: Community Infrastructure (3A) Improve City Facilities
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: On Hold Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: Palm Springs Public Library, Fire Station #1, Fire Station #2, Fire Station #4, Demuth Community Center, Animal Shelter,
Police Department (Jail), Fleet Operations Building.
Project Description: Retrofit identified skylights to include safety railings.
Project Justification: Protect existing skylights on the roofs of eight public buildings.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses.
Project Cost Estimate:
Construction: $600,000
Construction Contingency (10%): $60,000
Administration (5%): $30,000
Engineering and/or Design (15%): $67,780
Construction Management (15%): $90,000
Total Cost Estimate: $847,780
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects 456,876 450,000 397,780
Total: 456,876 450,000 397,780
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
18-20
Notes:
PROJECT NO.
19-15
Project Title: Storm Drain Line 20
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Identify High-Priority Facilities
Type: Drainage Department: Engineering Services Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: (East-West Line) Ramon Road from El Cielo to Farrell Drive, (North-South Line) Farrell Drive from Ramon Road to Tahquitz
Canyon Way.
Project Description: Construct reinforced concrete pipe (RCP) storm drain main line, catch basins, connector pipes, and
appurtenances.
Project Justification: Routine flooding in the area. This will connect to an existing storm drain for Line 20 built by Riverside County
Flood Control.
General Plan Conformance: Circulation Element – Policy CR10.4: Continue and expand existing programs for the upgrade of storm
drainage systems where they are deficient, using public or private funds.
Project Cost Estimate:
Construction: $6,000,000
Construction Contingency (10%): $600,000
Administration (5%): $325,945
Engineering and/or Design (15%): $301,050
Construction Management (15%): $900,000
Total Cost Estimate: $8,126,995
Funding:
Fund Account
Number
Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital (RCFC funds) $7,520,000
135 Drainage North Zone 1353105-80000 $244,407 $167,284 $330,000
135 Drainage Central Zone 1353110-80000 $53,607 $43,540 $250,000
135 Drainage South Zone 1353115-80000 $169,429 $130,016 $230,000
Total: $467,444 $340,840 $8,330,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-15
Notes:
PROJECT NO.
19-18
Project Title: JC Frey Building Rehabilitation
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Library Funding Status:
Project Status: On Hold Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: 1911 E. Baristo Road
Project Description: This project will install useable restrooms, replace HVAC and install the fire sprinklers and fire alarms.
Project Justification: The existing Main Library has an archival room and storage area that they would like to convert into meeting
space. This requires the archive equipment and files to be moved to the JC Frey Building.
General Plan Conformance: Recreation, Open Space & Conservation Element – Policy RC2.5: Ensure that parks and recreational
facilities are fully accessible to people of all ages and abilities, including people with disabilities.
Project Cost Estimate:
Construction: $600,000
Construction Contingency (10%): $60,000
Administration (5%): $30,000
Engineering and/or Design (15%): $90,000
Construction Management (15%): $90,000
Total Cost Estimate: $870,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $870,000
Total: $870,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-18
Notes:
PROJECT NO.
19-23
Project Title: Keyless Entry System Phase 2
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Fire Stations and Animal Shelter
Project Description: This project will replace the access control system with a new non-proprietary system hardware that is
expandable to other City facilities, including integration with intrusion detection and video surveillance. Phase 1 included City
Hall, City Yard & Fleet and the Police Department.
Project Justification: The City’s existing access control system (card reader) is more than 10 years old and comprised of a proprietary
system hardware with limited capability for future expansion. The system is no longer supported by the vendor.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses
Project Cost Estimate:
Construction: $475,000
Construction Contingency (10%): $47,500
Administration (5%): $23,750
Engineering and/or Design (15%): $71,250
Construction Management (15%): $71,250
Total Cost Estimate: $668,750
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $200,000 $468,750
Total: $200,000 $468,750
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-23
Notes:
PROJECT NO.
19-24
Project Title: Demuth Park ADA Access – Phase 2
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Focus on Parks and Community Assets
Type: Parks Department: Engineering Services Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Demuth Park
Project Description: Phase 2 will address the accessibility deficiencies at restrooms, concession buildings, drinking fountains, outdoor
bleachers, playground, railings, tables, and benches at Demuth Park.
Project Justification: An accessibility survey was prepared for Demuth Park which identified basic accessibility deficiencies and
adjustments needed to bring restrooms and buildings into compliance.
General Plan Conformance: Recreation, Open Space & Conservation Element – Policy RC2.5: Ensure that parks and recreational
facilities are fully accessible to people of all ages and abilities, including people with disabilities.
Project Cost Estimate:
Construction: $1,103,450
Construction Contingency (10%): $110,345
Administration (5%): 55,171
Engineering and/or Design (15%): 165,517
Construction Management (15%): 165,517
Total Cost Estimate: $1,600,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $600,000 $1,000,000
Total: $600,000 $1,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-24
Notes:
PROJECT NO.
19-25
Project Title: Life Safety Improvements (Fire Sprinklers/Fire Alarms)
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Library Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Library, Leisure Center, Pavilion, Corporate Yard and Fleet Operations buildings.
Project Description: This project will install upgraded fire sprinkler system in City owned facilities to comply with current life safety
standards. Upgrades include fire sprinkler systems in the Library, Leisure Center, Pavilion, Corporate Yard and Fleet Operations
facilities. (Demuth Community Center is being done as 19-14). This project will also include but not limited to, fire alarm panels,
smoke detectors, pull stations, emergency exit lighting, strobes, and audible notification devices.
Project Justification: Upgrades fire sprinkler system in City owned facilities to comply with current life safety standards.
General Plan Conformance: Safety Element – Policy SA4.7 Encourage owners of nonsprinklered properties, especially midrise
structures and high-occupancy structures, to retrofit their buildings and include internal fire sprinklers.
Project Cost Estimate:
Construction: $1,310,350
Construction Contingency (10%): $131,035
Administration (5%): $65,511
Engineering and/or Design (15%): $196,552
Construction Management (15%): $196,552
Total Cost Estimate: $1,900,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $900,000 $1,000,000
Total: $900,000 $1,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-25
Notes:
If City receives a grant for CP#16-08, then the portion for the library will be incorporated into the design/construction of 16-08.
PROJECT NO.
19-26
Project Title: Back Up Generators at City Facilities
Council Priority: Community Infrastructure (3A) Improve City Facilities Focus on Parks and Community Assets
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Funded
Location: Animal Shelter, Leisure Center, Pavilion, and Library.
Project Description: Purchase and install back up emergency generators for various facilities.
Project Justification: These generators provide electricity during power outages. The Library is designated as a cooling center for
Riverside County
General Plan Conformance: Safety Element – Goal SA8: Reduce the risk to life, property, and essential facilities through emergency
preparedness and public awareness.
Project Cost Estimate:
Construction: $950,000
Construction Contingency (10%): $95,000
Administration (5%): $47,500
Engineering and/or Design (15%): $142,500
Construction Management (15%): $142,500
Total Cost Estimate: $1,377,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $600,000 $777,500
Total: $600,000 $777,500
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-26
Notes:
PROJECT NO.
19-27
Project Title: City Water Treatment Program (HVAC)
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Partially Funded
Location:
Project Description: This project will install automatic monitoring and control devices in all cooling towers that are a part of the air
conditioning and ventilation systems in City facilities to ensure the City remains compliant with certain public health and safety
regulations.
Project Justification: The City requires a comprehensive water treatment program to monitor levels of water quality and remove any
potential water borne agents or chemicals that can negatively impact health or mechanical equipment.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses.
Project Cost Estimate:
Construction: $350,000
Construction Contingency (10%): $35,000
Administration (5%): $17,500
Engineering and/or Design (15%): $52,500
Construction Management (15%): $52,500
Total Cost Estimate: $507,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $507,500
Total: $507,500
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-27
Notes:
PROJECT NO.
19-28
Project Title: Recreation Fields LED Lighting Upgrades
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Focus on Parks and Community Assets
Type: Parks Department: Recreation Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Partially Funded
Location: Park ballfields. Demuth Park, Sunrise Park
Project Description: The lights at the various park ballfields were installed in the 1950s and 1960s and utilized outdated and energy
inefficient metal halide light fixtures that are no longer manufactured. This project will replace the metal halide light fixtures with
energy efficient LED light fixtures and replace the wiring system.
Project Justification: City staff purchased all available light fixtures and is not expected to find any more replacements. Recently the
wiring for the system has failed. Attempts to fix it determined that the original wires were direct burial without any conduits.
General Plan Conformance: Recreation, Open Space & Conservation Element – Goal RC2: Ensure that parks are safe, well
maintained, and provide a pleasant experience for residents and visitors.
Project Cost Estimate:
Construction: $3,649,319
Construction Contingency (10%): $364,932
Administration: $89,968
Engineering and/or Design:
Construction Management: $90,000
Total Cost Estimate: $4,194,219
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $94,219 $4,100,000
Total: $94,219 $4,100,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
19-28
Notes:
PROJECT NO.
20-03
Project Title: Roundabout at S. Indian Canyon Drive and S. Palm Canyon Drive
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Desireable (start within 3 to 5 yrs) Partially Funded
Location: Intersection of S. Indian Canyon Drive, S. Palm Canyon Drive and Camino Parocela
Project Description: Construct a new roundabout at the five-legged intersection.
Project Justification: As a part of the Indian Canyon Two-Way conversion study, the City Council requested the project look at a traffic
signal vs. a roundabout at this intersection. The roundabout was the preferred design alternative from a traffic safety perspective
and to reduce traffic accidents. The cost to build the roundabout exceeded budget projections and was not included in the Indian
Canyon Project.
General Plan Conformance: Circulation Element – Policy CR1.1: Develop a system of roadways that provides travel choices and
reduces traffic congestion.
Project Cost Estimate:
Construction: $2,000,000
Construction Contingency (10%): $200,000
Administration (5%): $100,000
Engineering and/or Design (Actual): $236,174
Construction Management (15%): $300,000
Total Cost Estimate: $2,836,174
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $210,300 0 $400,000 $400,000 $400,000 $400,000
261 Capital Projects $200,000 $200,000 $200,000 $400,000
Total: $210,300 0 $600,000 $600,000 $600,000 $800,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-03
Notes:
PROJECT NO.
20-04
Project Title: Sunrise Plaza HVAC Improvements
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Unfunded
Location: Pavilion and Leisure Center
Project Description: Replace chillers and cooling towers with an all-in-one packaged unit, including connecting to the City’s
Environmental Control Management System (ECMS)
Project Justification: Existing units not in working condition.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses
Project Cost Estimate:
Construction: $1,170,000
Construction Contingency (10%): $117,000
Administration (5%): $58,500
Engineering and/or Design (15%): $175,500
Construction Management (15%): $175,500
Total Cost Estimate: $1,696,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $400,000 $500,000 $696,500
261 Capital $100,000 $100,000
Total: $100,000 $100,000 $400,000 $500,000 $696,500
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-04
Notes:
PROJECT NO.
20-06
Project Title: City Hall and Police Department Electrical Upgrades
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Engineering Services Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: City Hall located at 3200 E. Tahquitz Canyon Way, Palm Springs Police Department located at 200 S. Civic Drive.
Project Description: The main electrical transformer servicing City Hall, originally installed in 1965, has served its useful life and requires
replacement. This project will install upgrades to existing electrical components and add electrical service panel in each building.
Project Justification: City Hall and the Police Department has outgrown the electrical capabilities of the existing building. In addition, as
technology advances, there is an increased need for data. Storage of that data requires servers and temperature controls to
prevent them from overheating. An additional service meter is required to expand and meet current and future electrical demands.
These upgrades were not included in the recently completed Police Department Remodel Project.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses
Project Cost Estimate:
Construction: $362,069
Construction Contingency (10%): $36,207
Administration (5%): $18,014
Engineering and/or Design (15%): $54,310
Construction Management (15%): $54,310
Total Cost Estimate: $525,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $480,000 $480,000 $100,000
Total: $480,000 $480,000 $100,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-06
Notes:
PROJECT NO.
20-07
Project Title: Sunrise Plaza Domestic Water Line Separation
Council Priority: Community Infrastructure (3A) Improve City Facilities Focus on Parks and Community Assets
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Sunrise Park
Project Description: Separate the domestic water lines from the irrigation water lines and add isolation valves at each facility.
Project Justification: Existing water lines for the facilities throughout Sunrise Park are all connected to one main water point of
connection. Maintenance repairs at one facility requiring water interruption then cause all of Sunrise Plaza facilities to be without
water. Repairs to irrigation lines are fairly common and extremely inconvenient to Parks and Recreation, and Library staff and
their program attendees to be without water during these repairs. The addition of isolation valves at each facility will allow staff to
minimize the impacts to affected facility. Also having the irrigation system separated would open the possibility to having Sunrise
Park use recycled water for irrigation in the future.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses
Project Cost Estimate:
Construction: $175,000
Construction Contingency (10%): $17,500
Administration (5%): $8,750
Engineering and/or Design (15%): $26,250
Construction Management (15%): $26,250
Total Cost Estimate: $253,750
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $253,750
Total: $253,750
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-07
Notes:
PROJECT NO.
20-08
Project Title: Fleet Operations HVAC and Electrical Improvements
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: Fleet Operations – 459 N. Civic Drive, Palm Springs, CA 92262
Project Description: Replace the existing ducting where necessary, evaporative cooling systems and install energy efficient climate
control units. Add an electrical service meter to accommodate the needs for Facilities & Maintenance, Office of Special
Programs, and City Fleet. Perform an air-balancing test to determine the correct ducting required for the building.
Project Justification: Staff has outgrown the existing electrical service to the City Yard and Fleet buildings. The addition of hybrid and
electrical vehicles requires more charging stations and more electricity than the current service meter can provide. The City Yard
electrical system requires renewal of the main electrical service, distribution equipment transformer, distribution equipment,
panel and feeders, and the electrically operated transfer switch. In connection with the additional electrical service meter the
emergency generator will need to be upgraded to meet the increased electrical load.
General Plan Conformance: Circulation Element – Goal CR10: Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses
Project Cost Estimate:
Construction: $550,000
Construction Contingency (10%): $55,000
Administration (5%): $27,500
Engineering and/or Design (15%): $82,500
Construction Management (15%): $82,500
Total Cost Estimate: $797,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $100,000 $100,000 $200,000 $497,500
Total: $100,000 $100,000 $200,000 $497,500
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-08
Notes:
PROJECT NO.
20-10
Project Title: Sunrise Plaza Door and Window Replacements
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: Sunrise Park – Leisure Center and Pavilion
Project Description: Replace all doors and hardware with life safety compliant doors. Replace all windows with vandalism proof,
tinted, energy efficient windows.
Project Justification: Windows and doors are at the end of its useful life and in need of replacement.
General Plan Conformance: Recreation, Open Space & Conservation Element – Policy RC2.5: Ensure that parks and recreational
facilities are fully accessible to people of all ages and abilities, including people with disabilities.
Project Cost Estimate:
Construction: $560,000
Construction Contingency (10%): $56,000
Administration (5%): $28,000
Engineering and/or Design (15%): $84,000
Construction Management (15%): $84,000
Total Cost Estimate: $824,150
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $100,000 $100,000 $200,000 $524,150
Total: $100,000 $100,000 $200,000 $524,150
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-10
Notes:
PROJECT NO.
20-21
Project Title: Local Roads Safety Plan Recommended Projects
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Expand Walking/Biking Infrastructure
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Unfunded
Location: Various locations, see Notes.
Project Description: Install new traffic signals at unsignalized intersections, install larger stop-signs and update regulatory/warning signs
in vicinity of a selected intersection, install directional median islands to restrict/allow left-turns at an intersection. Projects
numbered 5, 6, and 7.
Project Justification: A local road safety plan (LRSP) provides the framework for identifying, analyzing, and prioritizing roadway safety
improvements on City streets. Following engineering analysis, stakeholder outreach, review of crash, traffic and roadway data, the
LRSP was developed to reduce fatalities, injuries and crashes. Countermeasures were developed and turned into recommended
projects. Ninety percent (90%) of costs (not including project administration) may be reimbursable by Caltrans Highway Safety
Improvement Program (HSIP).
General Plan Conformance: Circulation Element – Goal CR1: Establish and maintain an efficient interconnected circulation system that
accommodates vehicular travel, walking, bicycling, public transit, and other forms of transportation
Project Cost Estimate:
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $500,000 $2,646,500 $1,617,833 $1,617,833 $1,617,834
Total: $500,000 $2,646,500 $1,617,833 $1,617,833 $1,617,834
Construction: $5,547,500
Construction Contingency (10%): $545,000
Administration (5%): $272,500
Engineering and/or Design (15%): $817,500
Construction Management (15%): $817,500
Total Cost Estimate: $8,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
20-21
Notes:
FY 23-24 Projects ($3,146,500)
LSRP Project No. 5 – New Traffic Signal at N. Indian Canyon and Via Escuela.
This project will install a new traffic signal at the intersection of N. Indian Canyon and Via Escuela. This would include signal poles,
equipment, controllers, detectors, signage and striping. This will also include the replacement of corner ramps and installing crosswalks
with pedestrian countdown heads. Estimated project cost is $359,700 for construction.
LSRP Project No. 6 – Upgrade Pedestrian Crosswalk at N. Indian Canyon and Granvia Valmonte
This project will improve the existing non-signalized crosswalk, with larger stop signs for the side streets, update the warning and
regulatory signs, and replace the pavement striping and markings on the street.
LSRP Project No. 7 – Install raised median at E. Palm Canyon and Broadmoor Dr/Palm Hills Rd
This project will install a raised median with directional median openings to allow left-turns into the smaller side streets. Since this location
is on SR-111, coordination with Caltrans will be required.
PROJECT NO.
21-04
Project Title: WWTP General Sitework and Pavement Replacement
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Utility Department: Engineering Services Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: Wastewater Treatment Plant, 4375 E. Mesquite Ave, Palm Springs, CA 92264
Project Description: The project includes the reconstruction of approximately 3,200 feet of primary roadways used for plant circulation
for trucks subject to heavy loading and moving equipment around the plant. It also includes the reconstruction of minor
roadways that provide access around the percolation ponds and perimeter of the WWTP.
Project Justification: The original existing interior roadways at the WWTP are still being used to this day. The heavy loads of trucks
and the day-to-day operations of the plant have deteriorated some of the roads to dirt. Some of the roads were repaved as a
part of the WWTP Upgrades Project completed in 2019, but due to limited budget only a small portion was completed.
General Plan Conformance: Circulation Element – Goal CR10. Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses.
Project Cost Estimate:
Construction: $1,120,000
Construction Contingency (10%): $112,000
Administration (5%): $56,000
Engineering and/or Design (15%): $144,000
Construction Management (15%): $168,000
Total Cost Estimate: $1,600,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
420 Wastewater $150,000 $725,000 $725,000
Total: $150,000 $725,000 $725,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-04
Notes:
Engineering Design cost per Carollo proposal dated November 20, 2020. Rates are valid for the initial 3-years, which takes us through
the end of July 2023.
PROJECT NO.
21-05
Project Title: WWTP Sludge Drying Beds
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Utility Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Wastewater Treatment Plant, 4375 E. Mesquite Ave, Palm Springs, CA 92264
Project Description: Rehabilitate Sludge Drying Beds 16-18 and 19-25. Remove all existing asphalt and deteriorated improvements,
reconstruct new concrete sludge beds and related improvements.
Project Justification: The existing sludge drying beds are deteriorating and have come to its end of useful life. It needs to be
reconstructed. This project was included as a priority project in the comprehensive Capital Rehabilitation and Repair Plan (CRRP)
for the City’s Wastewater Treatment Plant.
General Plan Conformance: Circulation Element – Policy CR10.1: Require utility improvements where existing systems are deficient.
Project Cost Estimate:
Construction: $1,100,000
Construction Contingency (10%): $110,000
Administration (5%): $55,000
Engineering and/or Design (15%): $202,200
Construction Management (15%): $165,000
Total Cost Estimate: $1,632,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
420 Wastewater $429,898 $225,254 $706,000 $706,000
Total: $429,898 $225,254 $706,000 $706,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-05
Notes:
Engineering Design cost per Carollo proposal dated November 20, 2020. Rates valid for the initial 3 years, which will take us through the
end of July 2023
PROJECT NO.
21-06
Project Title: WWTP Demolition of Abandoned Headworks, Primary Clarifier, Sand Filter
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Utility Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: Wastewater Treatment Plant, 4375 E. Mesquite Ave, Palm Springs, CA 92264
Project Description: : This project will demolish the abandoned headworks aerated grit chambers and mechanical bar screens, as well
as the primary clarifiers area, and sand filter area.
Project Justification: Due to the recent upgrades completed in 2019, the facilities will be abated and demolished to make way for other
planned projects at the WWTP. This will also remove abandoned equipment that is in relatively close proximity to the park. This
project is identified as a priority project in the comprehensive Capital Rehabilitation and Repair Plan (CRRP) for the City’s
Wastewater Treatment Plant.
General Plan Conformance: Circulation Element – Goal CR10. Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses.
Project Cost Estimate:
Construction: $2,635,000
Construction Contingency (10%): $263,500
Administration (5%): $131,750
Engineering and/or Design (15%): $260,000
Construction Management (15%): $395,250
Total Cost Estimate: $3,685,500
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
420 Wastewater $1,842,750 $1,842,750
Total: $1,842,750 $1,842,750
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-06
Notes:
Engineering Design cost per Carole proposal dated November 20, 2020. Rates valid for the initial 3 years, which will take us through the
end of July 2023.
In February 2010, Carollo Engineers (Carollo) completed a “Capital Rehabilitation and Repair Plan” (CRRP) that defined priority findings
and recommendations for the WWTP. Years later, Stantec developed a “Technical Memorandum – 1 2019 Capital Rehabilitation and
Repair Plan” (TM1) that further developed and updated Carollo’s work, including a long-term financial plan and schedule to prioritize,
fund, and complete desired projects at the WWTP. There are several previously abandoned facilities identified in TM1 planned for
demolition, including the mechanical bar screen, aerated grit chambers, and grit washer (collectively, the “headworks”), primary clarifiers,
sand filters, and chlorine contactor. After visiting with Veolia’s Doug Loar, the WWTP’s Plant Operations Manager, we learned the chlorine
contactor is utilized for recycled water storage and therefore will not be demolished as part of this project.
PROJECT NO.
21-08
Project Title: WWTP Biosolids Dewatering Facility Projects
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Utility Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Funded
Location: Wastewater Treatment Plant, 4375 E. Mesquite Ave, Palm Springs, CA 92264
Project Description: Addition of another odor control scrubber to handle new dewatering facility. Construct new dewatering facility with
two installed dewatering centrifuges. Construct a sidestream treatment system to remove ammonia centrate/filtrate produced by
the dewatering process.
Project Justification: During wet and winter months, the drying beds lack the capacity to handle all of the plant’s sludge. Centrifuge
dewatering provides substantial sludge processing capacity within a relatively small footprint and their enclosed configuration
alleviate odor concerns. A sidestream treatment system will also be needed to remove ammonia centrate/filtrate produced by the
dewatering process, and the liquid can go back to the headworks.
General Plan Conformance: Circulation Element – Policy CR10.1: Require utility improvements where existing systems are deficient.
Project Cost Estimate:
Construction: $18,000,000
Construction Contingency (10%): $1,800,000
Administration (5%): $394,000
Engineering and/or Design (15%): $2,969,858
Construction Management (15%): $1,150,000
Total Cost Estimate: $24,313,858
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
420 Wastewater $4,999,959 $2,029,867 $2,000,000 $7,000,000 $7,000,000 $6,313,858
Total: $4,999,959 $2,029,867 $2,000,000 $7,000,000 $7,000,000 $6,313,858
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-08
Notes:
Engineering Design cost per Carollo proposal dated November 20, 2020. Rates valid for the initial 3 years, which will take us through the
end of July 2023. The Biosolids Dewatering Facility Projects combine three related projects, because to build the dewatering facility, you
would need odor control and a sidestream treatment process.
Odor Control Improvements Project: *assumes a 20% cost savings in base construction costs.
Stand Alone Project *Combined w/ other projects
Construction: $6,900,000 $5,520,000
Construction Contingency (10%): $690,000 $552,000
Administration (5%): $345,000 $276,000
Engineering and/or Design: $995,000 $995,000
Construction Management (15%): $1,035,000 $828,000
Total Cost Estimate: $9,965,000 $8,171,000
Δ = $1,794,000
Dewatering Facility Project:
Stand Alone Project *Combined w/ other projects
Construction: $11,000,000 $8,800,000
Construction Contingency (10%): $1,100,000 $880,000
Administration (5%): $550,000 $440,000
Engineering and/or Design: $1,700,000 $1,700,000
Construction Management (15%): $1,650,000 $1,320,000
Total Cost Estimate: $16,000,000 $13,140,000
Δ = $2,860,000
Sidestream Treatment Project:
Stand Alone Project *Combined w/ other projects
Construction: $5,500,000 $4,400,000
Construction Contingency (10%): $550,000 $440,000
Administration (5%): $275,000 $220,000
Engineering and/or Design: $961,000 $961,000
Construction Management (15%): $825,000 $660,000
Total Cost Estimate: $8,111,000 $6,681,000
Δ = $1,430,000
Estimated total cost savings by combining all 3 projects: $6,084,000
PROJECT NO.
21-10
Project Title: Traffic Operations Center Communications Upgrades
Council Priority: Community Infrastructure (3A) Improve City Facilities Prioritize Deferred Maintenance
Type: Traffic Signals Department: Engineering Services Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Unfunded
Location: City Hall and Citywide
Project Description: Replace radios, switches, modems, and controllers for some of the signalized intersections and communication
towers. Update software and hardware as appropriate.
Project Justification: Our traffic engineering consultant completed their evaluation of the existing system. The problems are basically
communications issues. Years of deferred maintenance, not upgrading the computer software, and the loss/lack of key staff to
oversee the traffic signal has resulted in an immediate need to fix these issues.
General Plan Conformance: Circulation Element – Policy CR1.1: Develop a system of roadways that provides travel choices and
reduces traffic congestion.
Project Cost Estimate:
Construction: $400,000
Construction Contingency $21,000
Administration (5%): $20,000
Engineering and/or Design $30,000
Construction Management: $29,000
Total Cost Estimate: $500,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
134 Measure A $18,184 $1,158 $500,000
Total: $18,184 $1,158 $500,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-10
Notes:
PROJECT NO.
21-16
Project Title: Demuth Dog Park
Council Priority: Community Infrastructure (3A) Improve City Facilities Focus on Parks and Community Assets
Type: Parks Department: Recreation Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Partially Funded
Location: Demuth Park, near Fields 7-8.
Project Description: Construct a new small and large dog park at Demuth Park, with a paved parking lot that will support the new small
and large dog parks.
Project Justification: Following the use of temporary dog park locations, dog park users and stakeholders were vocal about their desire
for additional permanent dog parks being established within the City, offering similar amenities and features, as in the City Hall
dog park. Staff has submitted this project for a Land and Water Conservation Fund Grant, and was recommended favorably by
the State Department of Park and Recreation’s Office of Grants and Local Services to the US National Parks Service for approval.
The City awaits confirmation of the grant which will fund 50% of the cost, with a 50% local match.
General Plan Conformance: Recreation, Open Space & Conservation Element – Goal RC1. Provide sufficient park, trail and
recreational facilities that meet the diverse needs of residents and visitors.
Project Cost Estimate:
Construction: $2,610,000
Construction Contingency (10%):
Administration (5%): $90,470
Engineering and/or Design (15%): $400,000
Construction Management (15%): $200,000
Total Cost Estimate: $3,300,470
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
152 Quimby $1,448,270 $1,448,270 $201,965
260 Measure J
261 Capital Projects $650,000 $650,000 $1,000,235
Total: $2,098,270 $2,098,270 $1,202,200
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-16
Notes:
On August 5, 2020, the California Department of Parks and Recreation – Office of Grants and Local Services advised Staff that the
Demuth Dog Park Project was recommended for funding to the National Parks Service. The LWCF grant is made available with federal
funds allocated by the National Parks Service to California, and a limited number of projects are selected for funding statewide.
The City’s application for LWCF grant funding has been reviewed favorably by the California Department of Parks and Recreation – Office
of Grants and Local Services, and award of the grant to the City is pending National Parks Service approval which is only subject to the
state’s completion of the federal environmental cultural study of the project site. The state has requested that the City confirm availability
of local funds for the 50% match of $1,650,235.
On March 22, 2022, the interim Director of Parks and Recreation received word that grant applications are still being reviewed at the
federal level.
PROJECT NO.
21-17
Project Title: Arnico Tract Sewer - Phase 4
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Utility Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Partially Funded
Location: Arnico Street between E. Via Escuela and Jason Court.
Project Description: Install sewer main and sewer laterals in Arinco Street
Project Justification: The residential neighborhood of 87 homes located south of Via Escuela between Whitewater Club Drive and Gene
Autry Trail was previously identified in a moderate-to-low income census tract area making public improvements in that
neighborhood eligible for funding through the City's Community Development Block Grant (CDBG) Program. Over several years,
the City Council funded installation of sewer improvements in phases in this neighborhood with CDBG funds. However, after the
2010 Census, this residential area was no longer identified in an eligible income area allowing for use of CDBG funds, leaving the
last phase of homes on Arnico Street without connections to the City’s sewers and relying on septic tanks.
General Plan Conformance: Circulation Element – Goal CR10. Provide adequate and safe utility systems and facilities to support the
City’s existing and proposed land uses.
Project Cost Estimate:
Construction: $535,000
Construction Contingency (10%): $53,500
Administration (5%): $26,750
Engineering and/or Design (15%): $90,500
Construction Management (15%): $80,250
Total Cost Estimate: $785,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $585,000 $200,000
Total: $585,000 $200,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
21-17
Notes:
PROJECT NO.
22-02
Project Title: Annual Slurry Seal
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Accelerate Street Paving
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Funded
Location: Citywide
Project Description: Annual slurry seal of various City streets
Project Justification: Maintenance of existing streets to prevent from deteriorating into high-cost repairs.
General Plan Conformance: Circulation Element – Policy CR1.2. Preserve and extend the City’s fine grid of streets to the greatest
extent possible. Where possible, allow the grid of streets to curve and meander to slow traffic and to create more interesting
streetscapes.
Project Cost Estimate:
Construction: $1,000,000
Construction Contingency (10%): $100,000
Administration (5%): $50,000
Engineering and/or Design (5%): $50,000
Construction Management (15%): $150,000
Total Cost Estimate: $1,350,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
133 Special Gas Tax 877,368 $675,000 $675,000 $675,000 $675,000 $675,000
134 Measure A Local 206,463 $675,000 $675,000 $675,000 $675,000 $675,000
Total: $1,350,000 $1,350,000 $1,350,000 $1,350,000 $1,350,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-02
Notes:
PROJECT NO.
22-08
Project Title: Annual Pavement Rehabilitation
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Accelerate Street Paving
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Partially Funded
Location: Citywide
Project Description: Reconstruction and/or overlay of deteriorated street segments in the City.
Project Justification: This project will cut down the backlog of deferred maintenance of City streets. This will fix cracked, broken and
damaged streets.
General Plan Conformance: Circulation Element – Policy CR1.2. Preserve and extend the City’s fine grid of streets to the greatest
extent possible. Where possible, allow the grid of streets to curve and meander to slow traffic and to create more interesting
streetscapes.
Project Cost Estimate:
Construction: $6,000,000
Construction Contingency (10%): $600,000
Administration (5%): $300,000
Engineering and/or Design (5%):
Construction Management (5%): $300,000
Total Cost Estimate: $7,200,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $8,998,293 $3,017,493 $6,000,000 $6,000,000 $6,000,000 $6,000,000 $6,000,000
Total: $8,998,293 $3,017,493 $6,000,000 $6,000,000 $6,000,000 $6,000,000 $6,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-08
Notes:
PROJECT NO.
22-14
Project Title: Convention Center Exhibit Hall and Primrose Carpet Replacement
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: 277 N. Avenida Caballeros, Exhibit Hall and Primrose
Project Description: Replace 112,561 SF of carpet.
Project Justification: Exhibit Hall carpet tiles are no longer available. The current carpet is over 20 years old, and we have exhausted
available stock. The new carpet will provide better sound quality and ensure replacement tiles for future repairs. The new carpet
will improve aesthetics and the convention center can use the new carpet as a selling tool for marketing the facility.
General Plan Conformance: Community Design Element – Goal CD12. Create active, vibrant, and attractive gathering places
Project Cost Estimate:
Construction: $650,000
Construction Contingency (10%):
Administration (5%):
Engineering and/or Design (15%):
Construction Management (15%):
Total Cost Estimate: $650,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $650,000
Total: $650,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-14
Notes:
PROJECT NO.
22-15
Project Title: Exhibit Hall Air Wall and Acoustical Tile Refurbish
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: 277 N. Avenida Caballeros
Project Description: Replace air wall covering in Oasis Exhibit Hall. 322 panels faces at 24'-7" x 4'-0".
Project Justification: Covering are aged, faded, and damaged. The 3 airwalls are the original hardware and covering that were installed
in 1987.
General Plan Conformance: Community Design Element – Goal CD12. Create active, vibrant, and attractive gathering places
Project Cost Estimate:
Construction: $450,000
Construction Contingency (10%):
Administration (5%):
Engineering and/or Design (15%):
Construction Management (15%):
Total Cost Estimate: $450,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $450,000
Total: $450,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-15
Notes:
PROJECT NO.
22-16
Project Title: Convention Center Jackie Lee Houston Plaza Upgrades
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Convention Center Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: 277 N. Avenida Caballeros, Jackie Lee Houston Plaza
Project Description: Install new shade structures, increase concrete pad for event space, and improve landscaping.
Project Justification: Upgrades will provide a larger outdoor event space for the convention center and local events.
General Plan Conformance: Community Design Element – Goal CD12. Create active, vibrant, and attractive gathering places
Project Cost Estimate:
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $100,000
Total: $100,000
Construction: $80,000
Construction Contingency (10%):
Administration (5%):
Engineering and/or Design (15%): $20,000
Construction Management (15%):
Total Cost Estimate: $100,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-16
Notes:
PROJECT NO.
22-17
Project Title: Convention Center Marquee Upgrade
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: 277 N. Avenida Caballeros, east and west of the building
Project Description: Replace existing message signs with new digital message signs.
Project Justification: Replacement parts will soon be no longer available.
General Plan Conformance: Community Design Element – Policy CD1.1: Use public landscaping, banners, and signage along
streets, sidewalks, and property frontages and in public spaces to strengthen the City’s identiy.
Project Cost Estimate:
Construction: $160,000
Construction Contingency (10%):
Administration (5%):
Engineering and/or Design (15%):
Construction Management (15%):
Total Cost Estimate: $160,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $160,000
Total: $160,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-17
Notes:
PROJECT NO.
22-18
Project Title: Palm Springs Convention Center Retrofit Lighting Controls
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Unfunded
Location: 277 N. Avenida Caballeros
Project Description: Replace all HID indirect flood lighting fixtures with new LEDs (non-dimming) and controls. Replace all fluorescent
fixtures with LED fixtures. All color temperatures to be neutral white -4,000 Kelvin. All hallway fixtures to be non-dimming. All lights
in Mesquite and Smoketree rooms to be dimmable by zone. Project to include associated wall controllers for each partitioned area.
Project to include one (1) System Management Station Computer Touchscreen with Custom LiteTalk Software.
Project Justification: The PSCC had 4 separate lighting controls. Two of them are obsolete with no replacement parts.
General Plan Conformance: Community Design Element – Goal CD12. Create active, vibrant, and attractive gathering places
Project Cost Estimate:
Construction: $500,000
Construction Contingency (10%):
Administration (5%):
Engineering and/or Design (15%):
Construction Management (15%):
Total Cost Estimate: $500,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $500,000
Total: $500,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-18
Notes:
PROJECT NO.
22-19
Project Title: Relocate Fire Station 1
Council Priority: Community Infrastructure (3A) Improve City Facilities Identify High-Priority Facilities
Type: Building/Facility Department: Fire Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Partially Funded
Location: SW Corner Lot S Avenida Caballeros and E Tahquitz Canyon Way
Project Description: Construct Fire Station including Administrative Offices, Emergency Operations Center and Training Tower
Project Justification: See Notes
General Plan Conformance: Ensure adequate firefighting resources are available to meet the demands of new development, including
the construction of midrise structures, by ensuring that: Response times do not exceed desired levels of service; fire-flow engine
requirements are consistent with Insurance Service Office (ISO) recommendations; and, the heights of truck ladders and other
equipment are sufficient to protect multiple types of structures.
Project Cost Estimate:
Construction: $16,000,000
Construction Contingency (10%): $1,600,000
Administration (5%): $800.000
Engineering and/or Design (15%): $2,400,000
Construction Management (15%): $2,400,000
Total Cost Estimate: $23,200,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $1,600,000 $3,600,000 $9,000,000 $9,000,000
Total: $1,600,000 $3,600,000 $9,000,000 $9,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-19
Notes: Fire Station #1 located on Indian Canyon Drive was built in 1957, sixty-five years ago. The fire station does not meet safety
standards implemented in construction of new fire stations. The station cannot accommodate gender separation for sleeping and
restroom accommodations. The station infrastructure is failing and will be very expensive to repair. The station does not have a
decontamination area to utilize for decontamination after structure fires or exposure to medical pathogens. The station has no physical
fitness area, the weights and cardio equipment are outdoors. The station does not have an area to maintain small power tools and
other equipment. The station cannot house a ladder truck which is critical to timely downtown emergency response to large structures.
Due to the historic nature of the building and the lack of adequate expansion area on a limited lot size, remodeling the station is not an
option.
The City hired a firm in 2005 to perform a Standard of Cover study. Relocation of fire station #1 to the current proposed site was
recommended in that study. In 2021 the International Association of Firefighters performed a Standard of Cover study at no cost to the
City and the recommendation was to relocate fire station #1 to the current proposed site and relocate the ladder truck from fire station
#2 to be housed with the fire engine from station #1. The study utilized GIS data and identified a 5,000 % improvement in response
times by relocating the fire station and ladder truck to the proposed location. Improved response times results in improved outcomes. The
Standard of Cover Studies can be provided upon request for those that do not already have a copy.
The City currently does not have an Emergency Operations Center (EOC). This project includes an EOC. The EOC will also be utilized
as a training classroom facility for all City departments in addition to EOC training for the 35 City staff assigned to report to the EOC
during a disaster.
The fire department currently does not have a training tower. The department must travel thirty minutes outside of the City to the Roy
Wilson training facility for mandatory evolution training. This makes it impossible to orchestrate multi-company training as the City
would be depleted of response resources and rely on mutual aid from other fire departments. The fire department would be able to do
in house driver operator training. Hold new hire recruit academies in house in lieu of utilizing either the Roy Wilson training facility or the
Ben Clark training facility in Riverside. The department will also be able to perform active shooter and other training with the Palm
Springs Police Department.
This Capital Project is 27 years overdue and should be placed as the City’s top priority to improve public safety to the community.
PROJECT NO.
22-20
Project Title: Measure J Community Initiated Projects
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Building/Facility Department: Maintenance & Facilities Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Funded
Location: Various locations in the City, see notes
Project Description: Construction of projects submitted by the community and recommended by the Measure J Commission.
Project Justification: Measure J Community Initiated Projects. Following a wide community outreach for projects to consider, the
Measure J Commission evaluated projects based on the
General Plan Conformance: Recreation, Open Space & Conservation Element – Goal RC1. Provide sufficient park, trail and
recreational facilities that meet the diverse needs of residents and visitors.
Project Cost Estimate: (per year)
Construction: $2,068,950
Construction Contingency (10%): $206,895
Administration (5%): $103,455
Engineering and/or Design (15%): $310,350
Construction Management (15%): $310,350
Total Cost Estimate: $3,000,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $3,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
Total: $3,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-20
Notes:
Application Amount Est. Const. Cost Total w/ Overhead
1. Drainage at the Boys and Girls Club $50,000 $50,000 $72,500
2. Shade Structure over the playground at Victoria Park $40,000 $40,000 $58,000
3. Fencing between the Pool and Pavilion $60,000 $60,000 $87,000
4. Repair Existing Exercise Equipment at Wellness Park $22,580 $22,580 $32,625
5. Add 4 New Pieces of Exercise Equipment at Desert Highland Park $49,323 $49,500 $71,775
6. Hiking Trail Maintenance and Trailhead Signage $100,000 $100,000 $145,000
7. Shade Structures at the Animal Shelter $90,000 $90,000 $130,500
8. Demuth Dog Park Upgrades to address immediate needs $250,000 $250,000 $362,500
9. Resurface the Walking Path at Desert Highland Park $50,000 $50,000 $72,500
10. Swim Center Locker Rooms $100,000 $100,000 $145,000
11. Palm Canyon Theater Maintenance Repairs (8 projects) $193,500 $193,500 $280,575
12. Visitor Center Up Lighting $30,000 $30,000 $30,000
13. Wellness Centers at Local Schools (4 schools) $100,000 $100,000 $100,000
14. School Gardens at Local Schools (4 schools) $80,000 $80,000 $80,000
$1,215,403 $1,215,580 $1,667,975
Please note that some of the submitted projects from the community, may have been recommended for other funding sources.
Projects not yet vetted by Engineering team. These projects were recommended by the Measure J
Commission for funding based on the Community Initiated Project applications received in December 2021.
PROJECT NO.
22-21
Project Title: Pedestrian Master Plan Recommended Projects
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Identify High-Priority Facilities
Type: Other Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Various locations throughout the City, see notes for Phase 1 Projects.
Project Description: Based on a December 2021 Pedestrian Plan report, funded through the Southern California Associate of
Governments (SCAG), various locations throughout the City were identified for pedestrian safety improvements. The reported
identified a total of 37 locations needing improvements. Since it is not feasible to address all 37 locations within one fiscal year,
The City will use a phased approached, picking one or two locations per District. Phase 1 Projects will consist of installing new
crosswalk, ramps, rapid flashing beacon system, medians, lane reductions via pop-out curbs, bikes lanes and refreshing faded
lane lines.
Project Justification: The Pedestrian Master Plan considered community feedback from residents, schools, police department, as well
as analyzed pedestrian/ bicyclist accident data to identify hotspots.
General Plan Conformance: Circulation Element – Goal CR7. Create a pedestrian experience that is attractive to both residents and
visitors.
Project Cost Estimate:
Construction: $1,035,000
Construction Contingency (10%): $103,500
Administration (5%): $51,000
Engineering and/or Design (15%): $155,250
Construction Management (15%): $155,250
Total Cost Estimate: $1,500,00
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
261 Capital Projects $500,000 $500,000 $500,000 $500,000 $500,000
134 Measure A $500,000 $500,000 $500,000 $500,000 $500,000
260 Measure J $500,000 $500,000 $500,000 $500,000 $500,000
Total: $1,500,000 $1,500,000 $1,500,000 $1,500,000 $1,500,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-21
Notes: Phase I Locations
• District 1, Project D1-02, San Rafael Drive, between Indian Canyon Drive & Virginia Road
o Install a sidewalk on the southside of San Rafael Drive, between Puerta Del Sol & Indian Canyon. Install a standard
pedestrian crossing at the intersection of Puerta Del Sol and San Rafael Drive. Install a rectangular rapid flashing beacon
system (RRFB) at the intersection of McCarthy Road and San Rafael Drive, along with applicable regulatory/warning signs,
curb extension, refuge island, and crosswalk lighting.
• District 2, Project D2-02, Racquet Club Road, between Indian Canyon Drive & Sunrise Way
o Change the lane configuration of Racquet Club Road from four travel lanes to two travel lanes with an occasional turn lane,
with parking on both sides and bicycle lanes once road segment is classified appropriately in the pending General Circulation
Plan (GCP). In the meantime, Engineering will pick from the approved list of projects in District 2.
• District 3, Project D3-03, Ramon Road, between Sunrise Way & Avenida Caballeros
o Program a lead pedestrian interval on existing timing sheets, installed protected left turns, construct a mid-block crossing
along Ramon Road
• District 4, Project D4-06, Ramon Road, between Sunrise Way & Compadre Road
o Program a lead pedestrian interval on existing timing sheets, installed protected left turns, install additional overhead
regulatory signage, enhanced crosswalk via ladder style and school zone colors, refresh lane markers within a 200-ft radius
of the intersection, install concrete medians, install curb extension.
• District 5, Project D5-02, S Palm Canyon, between Belardo Road & Acanto Drive
o Convert S Palm Canyon from four travel lanes with intermittent street parking to two travel lanes, a center turn lane, two
buffered bicycle lanes, and a parking lane that will be located between the buffered bike lane and the traffic lane. A
pedestrian crossing will also be installed near Lykken Trail head.
PROJECT NO.
22-22
Project Title: Citywide Sign and Striping Inventory and Replacement Program
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Citywide
Project Description: Citywide assessment and inventory of lane markings, roadside regulatory signs, and roadside warning signs
Project Justification: Federal mandate that signs be converted to meet retro-reflectivity standards. Lane marking assessment to
determine areas to re-paint or replace bot-dots with painted lane lines.
General Plan Conformance: Circulation Element – Goal CR1: Establish and maintain an efficient interconnected circulation system
that accommodates vehicular travel, walking, bicycling, public transit, and other forms of transportation.
Project Cost Estimate:
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
133 Special Gas Tax $300,000 $300,000
Total: $300,000 $300,000
Construction: $206,500
Construction Contingency (10%): $20,650
Administration (5%): $10,350
Engineering and/or Design (15%): $31,250
Construction Management (15%): $31,250
Total Cost Estimate: $300,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-22
Notes:
PROJECT NO.
22-23
Project Title: Annual Traffic Calming Projects
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Identify High-Priority Facilities
Type: Streets & Highways Department: Engineering Services Funding Status:
Project Status: In Progress Project Priority: Essential (start within 1 yr) Partially Funded
Location: Various locations throughout the City.
Project Description: Installation of traffic calming devices such as speed cushions, chicanes, and enhanced pedestrian crosswalk
systems.
Project Justification: The City’s Traffic Calming Program is a systematic process in which a community can request mitigation measures
to calm traffic in their neighborhood. Engineering conducts field surveys, collects traffic data, and verifies if warrants are met which
all have a cost. If warrants are met, and the traffic concern cannot be mitigated by signage or police enforcement, then more
expensive methods are considered. Only traffic calming projects that meet warrants and have 2/3 approval from the community
they are installed.
General Plan Conformance: Circulation Element – Policy CR1.6. Implement roadway traffic-calming mechanisms as identified in the
City’s Neighborhood Traffic Calming Program to protect residential neighborhoods from the intrusion of cut-through traffic in areas
that have demonstrated traffic patterns.
Project Cost Estimate:
Construction: $345,000
Construction Contingency (10%): $34,500
Administration (5%): $17,000
Engineering and/or Design (15%): $51,750
Construction Management (15%): $51,750
Total Cost Estimate: $500,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
133 Gas Tax $250,000 $250,000 $250,000 $250,000 $250,000
134 Measure A $250,000 $250,000 $250,000 $250,000 $250,000
Total: $500,000 $500,000 $500,000 $500,000 $500,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-23
Notes:
PROJECT NO.
22-24
Project Title: Pickleball Courts
Council Priority: Community Infrastructure (3B) 5-Year Capital Improvement Plan Focus on Parks and Community Assets
Type: Parks Department: Recreation Funding Status:
Project Status: New Project Priority: Necessary (start within 1 to 3 yrs) Unfunded
Location: Unknown - Community input is necessary.
Project Description: 12 new pickleball courts.
Project Justification: Project requested through Measure J community initiated projects outreach. High demand by pickleball
community.
General Plan Conformance: Recreation, Open Space & Conservation Element – Goal RC1: Provide sufficient park, trail and
recreational facilities that meet the diverse needs of residents and visitors.
Project Cost Estimate:
Construction: $1,000,000
Construction Contingency (10%): $100,000
Administration (5%): $50,000
Engineering and/or Design (15%): $150,000
Construction Management (15%): $150,000
Total Cost Estimate: $1,450,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
152 Quimby $150,000 $575,000
260 Measure J $150,000 $575,000
Total: $300,000 $1,150,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-24
Notes:
PROJECT NO.
22-25
Project Title: Playground Equipment Shade Structures
Council Priority: Community Infrastructure (3A) Improve City Facilities Focus on Parks and Community Assets
Type: Parks Department: Recreation Funding Status:
Project Status: New Project Priority: Essential (start within 1 yr) Funded
Location: Demuth Park and Baristo Park
Project Description: Construct shade structures over the 2 playgrounds at Demuth Park and the playground at Baristo Park
Project Justification: Intense summer heat, makes playground equipment hot to the touch and unusable by children for large parts of
the day. Shade structures will provide some relief and allow for children to play outdoors. The Community Development Block
Grant (CDBG) program can fund projects like this when located in a low/moderate income area of the City.
General Plan Conformance: Recreation, Open Space & Conservation Element – Goal RC1. Provide sufficient park, trail and
recreational facilities that meet the diverse needs of residents and visitors.
Project Cost Estimate:
Construction: $245,960
Construction Contingency (10%): $25,000
Administration (5%): $11,000
Engineering and/or Design
Construction Management
Total Cost Estimate: $281,960
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
137 CDBG $281,960
Total: $281,960
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-25
Notes:
PROJECT NO.
22-26
Project Title: San Rafael Drive Turf Conversion
Council Priority: Environmental Stewardship
Type: Drainage Department: Engineering Services Funding Status:
Project Status: New Project Priority: Desireable (start within 3 to 5 yrs) Unfunded
Location: North parkway on San Rafael near Sunrise Way
Project Description: Remove turf and convert to desert scape ---
Project not yet vetted by Engineering team recommended by Measure J for funding based on community-
initiated project applications.
Project Justification: California Water Restrictions
General Plan Conformance: Housing Element HS4.4 – Encourage the conservation of water resources through the incorporation of
native landscaping and noninvasive species that are specially adapted to the desert climate.
Project Cost Estimate:
Construction: $103,448
Construction Contingency (10%): $10,345
Administration (5%): $5,172
Engineering and/or Design (15%): $15,517
Construction Management (15%): $15,518
Total Cost Estimate: $150,000
Funding:
Fund Account Number Budgeted
FY 21-22
Available
Balance FY 22-23 FY 23-24 FY 24-25 FY 25-26 FY 26-27
260 Measure J $150,000
Total: $150,000
5 YEAR CAPITAL IMPROVEMENT PROGRAM
CITY OF PALM SPRINGS
PROJECT NO.
22-26
Notes: Information below provided by applicant in the community-initiated projects application.
APPENDIX
Summary Description of Funds Used on Capital Projects
Fund 001: Org 1003055: Object 70000: (was Fund 123 Special Development Fund) – This fund
was established to collect developer impact fees paid for new residential development projects
located in the Canyon South Specific Plan area (south of Murray Canyon Drive). Several
residential developments paid impact fees relating to Affordable Housing, Drainage, Fire
Station/Equipment, and Bridges/Roads. These funds are budgeted and appropriated for use on
capital projects relating to the uses identified.
Fund 124: CSA 152 –The Riverside County Economic Development Agency assumed control of
the County Service Area’s (CSAs) in July 2002. Each parcel in the City is assessed a $9.50 BAU for
County Services. CSA 152 is authorized to provide street sweeping services to communities that
are required for compliance with National Pollutant Discharge Elimination System (NPDES)
standards. This program is to reduce pollutants from entering the various storm channels and
washes throughout the community.
Fund 132: Parking Capital Programs – A General Fund supported bond issue and minor
miscellaneous funds. Parking revenue provided funding for various City parking lots and
downtown parking structure built during FY 01-02 and FY 02-03.
Fund 133: Special Gas Tax Improvements – Projects under this fund cover street maintenance
and street improvements only. The revenue is received from the State of California SB1 funds
from a special half percent (½ %) sales tax.
Fund 134: Measure A Improvements – Projects under this fund cover street maintenance and
street improvements only. The revenue is received from the State of California from a special
1.2% sales tax.
Fund 135: Drainage – Revenue is received from fees assessed on new construction projects for
the purpose of building and maintain a drainage and flood control system within the City.
Fund 136: Emergency Response – this fund handles all emergency calls and directs police and fire
services to emergency locations.
Fund 137: Community Development Block Grant (CDBG) – The CDBG program administers
funding for programs and projects approved by City Council and funded by federal grants. Funds
must only be used in eligible Census blocks.
Fund 138 Sustainability – The sustainability program serves as a resource, catalyst and an
advocate for environmental sustainability in the City of Palm Springs and throughout the
Coachella Valley.
Fund 141: Landscape, Lighting, and Parkway Maintenance – This fund accounts for the
Landscape, Lighting and Parkway Maintenance Districts within the City of Palm Springs.
Fund 142: SB-1 RMRA: Road Maintenance and Rehabilitation – Senate Bill 1 (SB-1), identified as
the “Road Repair and Accountability Act of 2017” will increase local street and road funds
allocated through the Highway Users Tax Account, allocating funds from new taxes through the
Road Maintenance and Rehabilitation Account (RMRA). In accordance with the State’s new
guidelines, a new and separate revenue stream through increased Gas Tax will be provided to
the City, upon approval by the California Transportation Commission (CTC) of a project listing
identifying the City’s use of the new Gas Tax (RMRA) revenue.
Fund 143: CFD Canyon View – This fund accounts for revenues and related costs pertaining to
special taxes levied in a community facilities district (CFD) within the City.
Fund 149: Air Quality Management Fund – This fund accounts for revenues received from the
County for enacting air quality improvement polices.
Fund 150: Public Arts – This fund was established to account for revenue and expenditures
related to fees collected on new construction for the purpose of procuring art for public benefit.
Fund 151: Library Endowment – The Library Trust Fund supports capital needs for the Libraries.
Funds are received from private donations only.
Fund 152: Quimby Park & Recreation – Revenue is received from new development projects for
Public Open Space or Quimby Fees to fund parks and recreation projects that qualify under the
Quimby Act. The goal of the Quimby Act is to require developers to help mitigate the impacts of
property improvements, and gives authority for passage of land dedication ordinances only to
cities and counties. The fees must be paid and land conveyed directly to the local public agencies
that provide park and recreation services community-wide.
Fund 160: Special Projects – This fund includes accounts related to private development projects.
This includes, legal fees, EIR reviews, Planning studies, special building inspection, traffic
mitigation at intersections, landscaping inspections, and donations to community, Police and
Fire.
Fund 260: Measure J Capital – On November 8, 2011, Palm Springs voters approved Measure J, a
dedicated local revenue measure in the form of a 1% local sales tax increase to maintain local
community services and economically revitalize our Downtown.
Fund 261: Capital Projects – Projects identified under this fund cover general City improvements
and receive funding from a transfer-in from the General Fund, Utility Users Tax, Technology
Enhancement Fees, Developer Fees, and various Grants.
Funds 310 - 328: Assessment Districts – This fund accounts for expenditures related to approved
Assessment Districts.
Fund 405: Airport Customer Facility Fund – This account is for building a consolidated rental car
facility at the Palm Springs International Airport.
Fund 416: Airport Capital Projects (6501) Special Capital Projects – Funding for the Palm Springs
International Airport is used for capital projects related to the airport. Revenue is received from
an airline landing fee surcharge. This includes equipment purchases, crack filling, furniture,
fixtures, and equipment for the new hold rooms, public parking control gates, roadway signage
and terminal furniture replacement.
Fund 416: Airport Capital Project (6601) Federal Grants – Revenue is received from Federal
Grants (FAA) and used to rehabilitate and remodel the Palm Springs International Airport.
Fund 416: Airport Capital Project (6700) Passenger Facility Charges Local Funds – Revenue that is
collected from airline travelers paid on their ticket price. Fees goes toward upkeep and
maintenance of airport and is setup and capped according to US Federal law.
Fund 420: Wastewater Treatment – Revenue for this fund is not subsidized by general operating
revenues of the City and is fully privatized. The treatment plant operations were privatized in
September 1999, and are managed with a contract between the City of Palm Springs and Veolia
Water North America – West, LLC.
Fund 550: Energy – The Energy Fund accounts for costs related to the two-cogeneration plants
owned by the City of Palm Springs, as well as investigating new energy sources. Costs are
recovered through user fees charged to departments on a monthly basis.
City Project Numbers CP # Project Name 00‐01 Gene Autry Trail Median 00‐05 Tahquitz Canyon Traffic Signal Interconnect 00‐10 Indian Widening at Garnet 00‐14 Indian I‐10 Interchange 00‐15 Demuth, Baristo, & Victoria park Playground Improvements 00‐20 Palm Canyon Theatre Fire Damage 00‐21 Indian Canyon & Tachevah Drive Improvements 00‐24 Hazard Elimination Program 00‐26 Pavement Management Study 00‐29 Library Parking Lot Improvements 00‐31 Crossley Tract Phase 4 00‐35 Indian Canyon 2‐Way Modification 00‐36 Tahquitz Canyon Walkway Lighting 00‐37 Various Traffic Signal Modifications 01‐02 LED Lamps 01‐04 Gene Autry Trail Bridge Widening 01‐09 Henry Frank Parking Lot 01‐11 Indian Canyon Bridge Widening over Union Pacific Rail Road 01‐11A Indian Interim Road Widening 01‐14 Sunrise Interconnect 01‐15 Sunny Dunes Road Improvement 01‐16 Desert Moon Building Demolition 01‐17 City Hall Parking Lot and Dog Park 01‐18 Speed Survey 01‐19 Tramview Road Sewer System and Street Improvements 01‐20 Flood Gates 01‐22 Loop Replacements 01‐25 Indian Canyon Widening 01‐27 Downtown Parking Structure 02‐01 ARHM Overlay 02‐03 Gene Autry Trail Widening 02‐04 Sunrise Ramon Street Improvements 02‐05 Gene Autry I‐10 Interchange CP # Project Name 02‐07 WWTP Boundary Survey 02‐09 Racquet Club Sidewalk 02‐10 Tachevah Flashing Crosswalk 02‐11 Traffic Calming 02‐16 400 Avenida Cerca Demolition 02‐17 Racquet Club – Caballeros Traffic Signal 02‐23 Skate Park 02‐24 E. Palm Canyon – Araby Drive Traffic Signal Modification 02‐25 Sunrise way – Sunny Dunes Traffic Signal Installation 02‐26 Heritage District – Uptown Decorative Lighting Project 02‐27 Convention Center Expansion 03‐01 Traffic Data Collection 03‐02 Frey‐Jaycee Building ADA Improvements Project 03‐05 Desert Fashion Plaza Street Improvements 03‐08 Ramon Road Sidewalk 03‐09 Visitor Center Sewer Line Extension 03‐13 Calle Amigos Street Improvements 03‐15 Annual Slurry Seal 03‐16 Benchmarks 03‐18 S. Palm Canyon – Sunny Dunes Median Construction 04‐01 ARHM Overlay 04‐03 Ramon – Vella Road Widening 04‐04 Downtown Light Repainting 04‐05 JOJ DHUC Expansion 04‐06 Bridge Repairs 04‐09 Farrell Drive Sidewalk 04‐11 Camino Amapola – Camino Primrose Street Improvements 05‐03 S. Palm Canyon Widening 05‐06 1889 Cerritos Demolition 05‐07 Protective Permissive Signal Conversion 05‐08 Avenida Caballeros Shoulder Paving 05‐09 Demuth Parking Lot Stabilization
City Project Numbers CP # Project Name 05‐13 STP Pavement Rehabilitation 05‐14 Desert Hotel Demolition 05‐18 Golf Club Drive Culvert Reconstruction 05‐20 Storm Drain Lines 6A, 8, 20C, 20 CA 05‐21 Ramon Road Widening 05‐25 Village Fest Bollards 05‐26 Vista Chino Flood Gates 06‐03 Gene Autry Trail Gateway Landscaping 06‐05 EVP Retrofit 06‐06 Vista Chino – Sunrise Improvements 06‐12 Indian – Tamarisk Signal Installation 06‐14 Citywide Speed Surveys 06‐16 Farrell Drive Sidewalk 06‐17 Patencio – Araby Drainage 06‐18 S. Palm Canyon 4‐Lane Bridge HBRR 06‐21 Traffic Volume Counts 07‐01 EVP Retrofit 07‐03 Bogert Trail Bridge Rehabilitation 07‐06 WWTP Percolation Ponds 07‐07 WWTP Reclaimed Water Pump Station 07‐09 City Hall – Parking 07‐10 Civic Drive Street Improvements 07‐12 Sunrise – Alejo Signal Modification 07‐13 PSHS – Baristo Signal Intersection 07‐14 Sunrise – Mesquite Signal Modification 07‐15 Storm Drain Line 22 Extension 07‐16 Araby Drainage Improvements 07‐17 ARHM Overlay 07‐18 Annual Slurry Seal 07‐24 Animal Shelter 07‐26 Downtown Alley and Trash Enclosure Enhancements 07‐27 WWTP Sewer Master Plan Update CP # Project Name 08‐03 WWTP Digester Gas Treatment System 08‐04 Traffic Management Center 08‐05 San Lorenzo Shoulder Paving 08‐06 Safe Routes to Schools 08‐08 Sewer Manhole Adjustments 08‐09 WWTP Primary Digester 08‐10 Federal Safe Routes to Schools 08‐11 WWTP Security Perimeter Fence 08‐12 SB821 Farrell SW 08‐13 SB821 Ramon SW 08‐14 Light Poles Removal 08‐17 Indian Canyon – Vista Chino Traffic Signal Modification 08‐18 Jackie Lee Houston Plaza 08‐19 New ABOP Facility 08‐20 Tahquitz Median Landscape Design 08‐23 Stadium Re‐Roofing 08‐25 Ramon Bridge Widening 08‐26 Tahquitz Creek Levee Certifiation 08‐27 Annual Slurry Seal 08‐28 ARHM Overlay 09‐02 WWTP Gravity Thickener Upgrade 09‐03 WWTP Electrical System Upgrade 09‐04 Agua Caliente Cultural Museum Road Improvement 09‐05 Energy Management Project – Chevron 09‐06 Port Lawrence Temporary Parking Lot 09‐07 Safe Routes to School Cycle 8 09‐10 Ramon Road Drainage Improvements 09‐10A Ramon Road Drainage – Revised 09‐11 Vista Chino at Farrell Street Improvements 09‐13 Annual Slurry Seal 10‐01 FOG Availability Assessment 10‐02 Tract 13257 Sewer Improvements 10‐03 City Hall Emergency Generator Replacement
City Project Numbers CP # Project Name 10‐04 Library Roof and Lighting Replacement 10‐06 Vista Chino Widening – N. Palm Canyon to Gene Autry 10‐07 Traffic Signal Improvements 10‐08 Annual Overlay 10‐09 Annual Slurry Seal 10‐10 Vista Chino at Whitewater River Low Water Crossing Bridge 11‐02 Araby Bridge at Palm Canyon Wash 11‐03 Demuth Community Garden 11‐05 Annual Slurry Seal 11‐06 Annual Overlay 11‐07 Palm Canyon and Baristo Traffic Striping 11‐09 Fire Station #1 Generator Replacement 12‐01 Mesquite Avenue Improvements 12‐02 S. Palm Canyon Bridge at Tahquitz Creek 12‐03 WWTP – Sewer System Repairs 12‐04 E. Palm Canyon Bridge Rehabilitation 12‐06 Skate Park Modular Building 12‐07 Arnico Tract Sewer Improvements Phase II 12‐08 Bicycle Lanes 12‐09 Pool Heater Installation 12‐10 Speed Survey 13‐01 Frances Stevens Park Landscaping 13‐02 Annual Slurry Seal 13‐03 Welwood Murray Library 13‐04 Annual Overlay 13‐06 Sidewalk Replacement in Parks Citywide 13‐08 Ruth Hardy Park – Parking Lot Repairs 13‐09 Palm Tree Removal & Replacement 13‐10 Uptown Crosswalks 13‐12 DHUC Parking Lot 13‐13 Indian Canyon 2‐Way Conversion 13‐14 Skate Park Façade Improvements CP # Project Name 13‐15 WWTP – Trickling Filter Arm 13‐17 WWTP – Performance Review 13‐19 WWTP – Priority 1 – Digester Dome 13‐20 WWTP – Priority 1 – Sludge Centrifuge 13‐21 WWTP – Priority 1 – Primary Effluent Pump Station 13‐22 WWTP – Priority 1 – New Headworks 13‐23 WWTP – Priority 1 – Circular Clarifiers and Sludge Pump 13‐24 WWTP – Priority 1 – Facility Plan 13‐25 Sunrise at Ralphs Signal Installation 13‐26 Arnico Tract Sewer – Phase 3 13‐27 Andreas Road Two‐Way Conversion 13‐28 Cathedral Canyon Crosswalk 13‐29 Airport Backup Generator 13‐30 Baristo Sidewalk and Ramps 13‐31 Entry Way Signs 13‐32 NMTP – Biking Issues 13‐33 Tahquitz Medians – El Cielo to Sunrise 13‐34 Police Station Parking Lot 13‐35 Pavement Management System 14‐01 Demuth East Parking Lot Repairs 14‐02 Ramon Road Rehab – Sunrise to Compadre 14‐03 Annual Slurry Seal – Measure A 14‐04 Asphalt Overlay & Reconstruction 14‐05 Indian at San Rafael Realign Striping 14‐06 Demuth Park Gym Floor Replacement 14‐09 Convention Center Temporary Parking Lot 14‐10 Sewer System Repairs 2014‐2015 14‐11 WWTP – Lift Station Communications Upgrade 14‐12 WWTP – Trickling Filter Arm Replacements 14‐13 Gene Autry at Vista Chino 2nd Left Turn Lane 14‐14 City Bicycle Lane Project 14‐15 JOJ DHUC Air Conditioning 14‐16 Tahquitz Creek Triangle Parcel 14‐17 Fire Station #2 HVAC Chiller Replacement
City Project Numbers CP # Project Name 14‐18 JOJ DHUC Light Poles 14‐19 Ruth Hardy – Demuth Park Security Lighting 14‐20 Palm Canyon Electrical Infrastructure 14‐21 Palm Canyon Irrigation Replacement 14‐22 Visitor’s Center Landscape Upgrade 14‐23 Keyless Entry System Phase 1 14‐24 City Hall Security Design 15‐01 Pavement Rehabilitation Project 15‐02 Annual Slurry Seal 15‐03 Citywide Solar Project 15‐04 City Hall Landscape Conversion 15‐05 Police Department Upgrades 15‐06 City Council Chamber Upgrades 15‐07 Downtown Park 15‐08 Fire Station No. 2 Replace Apparatus Door 15‐09 Emergency Alerting System – All Fire Stations 15‐10 Fire Station No. 3 – Oil‐Water Separator 15‐11 Arenas Road Street Improvements at Whispering Palms 15‐12 Senior Center Shade Structure 15‐13 9‐11 Memorial 15‐14 WWTP Upgrades 15‐15 Demuth Park 15‐16 Cornelia White House Exterior Repairs 15‐17 San Rafael Widening 15‐18 ADA Sidewalks and Curb Ramps FY 15‐16 15‐19 McGruder Chevrolet Demolition 15‐20 Indian Canyon Drive Whitewater Bridge 15‐21 Tahquitz & Civic Traffic Signal 15‐22 Airport Landscape Conversion 15‐23 SB 821Missing Link Sidewalks 15‐24 Airport TSA Security Door 15‐25 Fire Station No. 4 Rehabilitation 15‐26 WWTP Biogas to Energy Project 15‐27 Library Shade Structure CP # Project Name 15‐29 Palm Canyon Bollards for Village Fest. La Plaza Bollards 15‐30 Priority One Tree Removal and Replacement 15‐31 Community Projects FY15‐16 (Hotspots) 15‐32 Highway Safety Improvement Program (HSIP)‐Cycle 7 16‐01 Pavement Rehabilitation 16‐02 Welwood Library ADA Access Improvements 16‐03 Dog Park Improvements 16‐04 Evaluation of All City Facilitites 16‐05 Roof Replacement 16‐06 Swim Center Replaster 16‐07 HVAC Chiller, Cooling Towers Main, Wifi Controls 16‐08 Library Infrastructure – Phase I – Design 16‐09 ADA Curb Ramps (2015 via Gas Tax) 16‐10 North Indian Canyon Widening (19th to Dillion) 16‐11 Chino Cone Preserve (Cable Fencing) 16‐12 Storm Drain Improvements (Santa Cruz and Sonora) 16‐13 N. Palm Canyon Drive Crosswalks 16‐14 Calle Pal Fierro Sewer Line Replacement 16‐15 Indian – I‐10 Sewer Extension 16‐16 In‐Ground Lighted Crosswalks 16‐18 Hwy Safety Imp Program (HSIP)‐Cycle 8 Traffic Signals 16‐19 Hwy Safety Imp Prog (HSIP)‐Cycle 8 Gene Autry‐Salvia Beacon 17‐01 Pavement Rehabilitation 17‐02 2017 Annual Slurry Seal 17‐03 Traffic Signal Installation at Vista Chino @ Via Miraleste 17‐04 Dunn Road Property Restoration 17‐05 Traffic Signal Installation at Palm Canyon @ Via Escuela 17‐06 WWTP Sewer Repairs 17‐07 North Palm Canyon Pedestrian Enhancements 17‐08 Indian Canyon Two‐Way and Pedestrian Enhancements 17‐09 S. Palm Canyon & E. Palm Canyon Pedestrian Enhancements 17‐10 Solar Swing Slide Gate Operators for Fire Stations #1 & #3 17‐11 2017 ADA Curb Ramps & Library Sidewalk
City Project Numbers CP # Project Name 17‐12 WWTP – Technical Studies 17‐13 Pasatiempo & Farrell Drainage Improvements (added to 1801) 17‐14 Convention Center Parking Lot, Phase II 18‐01 2018 Pavement Rehabilitation (FY18‐19) 18‐02 2018 Annual Slurry Seal (FY18‐19) 18‐03 Walkability Plan 18‐04 Plaza Theater Renovations 18‐05 Highway Safety Improvement Program (HSIP) Cycle 9 18‐06 Park Restrooms Renovations 18‐07 Indian Canyon and Camino Parocela Roundabout 18‐08 Parking Garage Comm Cell and Radio Transceivers, Repeaters 18‐09 Fire Training Facility 18‐10 Downtown Palm Canyon – Event Bollards 18‐11 Pilot Parking Program 18‐12 Sign Inventory Program 18‐13 PMP Study Update 18‐14 North Gene Autry Wind Wall Upgrade 18‐15 Ramon Road Nuisance Water Retention Basin 18‐16 Co‐Generation Plant Cooling Units 18‐17 PD Vehicle Impound Building 18‐18 Bogert Trail Sewage Lift Station 18‐19 WWTP CIP and Rate Study 18‐20 Skylight Railings 19‐01 2019 Pavement Rehabilitation 19‐02 2019 Annual Slurry Seal 19‐03 2019 CDBG ADA Ramps 19‐04 Fire Station #1, #3, #5 Remodel Expansion 19‐05 Downtown Parking Height Restricting Bar 19‐06 Pickleball Courts at Sunrise Park 19‐07 Storm Repairs 021419 Farrell & Indian Canyon 19‐08 Storm Repairs 021419 El Cielo & Araby 19‐09 Storm Repairs 021419 Traffic Control 19‐10 SB821 Sunny Dunes Sidewalks CP # Project Name 19‐11 Electric Vehicle Charging Stations 19‐12 Sewer Collection System Repairs 19‐13 Sunrise Park Restroom Remodel 19‐14 Demuth Park Fire Sprinklers 19‐15 Storm Drain Line 20 19‐16 Police Department 911 – CAD‐RMS System 19‐17 2019 Citywide Speed Survey 19‐18 JC Frey Building Improvements 19‐19 City Yard Roof Replacement 19‐20 Groundwater Monitoring Well Construction and Decom 19‐21 City Yard HVAC Chillers 19‐22 Airport Terminal Modifications 19‐23 Keyless Entry Phase 2 19‐24 Demuth ADA Access Phase 2 19‐25 Life Safety Improvements 19‐26 Emergency Generators 19‐27 Citywide HVAC Water Treatment Program 19‐28 Recreation Fields LED Lighting Upgrade 19‐29 Animal Shelter Repairs 19‐30 Citywide Enterprise Resource Planer (ERP) System 19‐31 WWTP Effluent TN and TDS Whitepaper 19‐32 NPFAS Site Investigation 19‐33 Reconfigured Consolidated Rental Car Facility (CONRAC) 19‐34 Airport Passenger Bridges 19‐35 Laser Leveling of Ballfields 19‐36 Traffic Management Center and Signal Timing Optimization 20‐01 Annual Pavement Rehabilitation 20‐02 Annual Slurry Seal 20‐03 Roundabout at Intersection of S Indian Canyon & S Palm Cyn 20‐04 Sunrise Plaza HVAC Improvements 20‐06 City Hall and Police Department Electrical Upgrades 20‐07 Sunrise Plaza Domestic Water Line Separation 20‐08 Fleet Operations HVAC and Electrical Improvements 20‐09 Demuth Community Center Window Replacement
City Project Numbers CP # Project Name 20‐10 Sunrise Plaza Door and Window Replacement 20‐11 Tennis Court and Pickleball Court Resurfacing 20‐12 Victoria Park Turf Conversion 20‐13 Section 14 Diagonal Parking Plan 20‐14 WWTP Fire Sprinkler & Alarm System Upgrades 20‐15 WWTP Biosolids Handling Area 20‐16 Highway 111 Guardrail 20‐17 Sewer Manhole Rehabilitation 20‐18 Avenida Palos Verdes Sewer Rehabilitation 20‐19 Desert Highland Traffic Signal Improvements‐Rosa Parks/Indian 20‐20 2020 Sewer Collection System Repairs 20‐21 Local Road Safety Plan (LRSP) 20‐22 City Hall and Police Department Cooling Towers 20‐23 WWTP Digester No. 2 Cleaning Project 20‐24 Traffic Calming FY20/21 20‐25 WWTP Digester No. 2 and Gas Flare Improvement Project 20‐26 Gym Floor Replacement at JOJDHUC 20‐27 Pavilion Shade and Acoustic Curtains 20‐28 Shade Structures at Parks 20‐29 Playground Surfacing 20‐30 Demuth Park Restroom Remodel 20‐31 Desert Highland Park Restroom 20‐32 Highway Safety Improvement Program (HSIP) Cycle 10 20‐33 San Rafael & Ave Caballeros TSI 21‐01 Annual Pavement Rehabilitation 21‐02 Annual Slurry Seal 21‐03 Annual Sign Replacement Program 21‐04 WWTP General Sitework and Paving 21‐05 WWTP Sludge Drying Beds 21‐06 WWTP Various Demolition 21‐07 WWTP Filtrate Pump Station 21‐08 WWTP Biosolids Dewatering Facility Projects 21‐09 Tova Hotel Demolition 21‐10 Traffic Operations Center Communication Upgrades CP # Project Name 21‐11 WWTP Block Wall 21‐12 SB 821 Bicycle and Pedestrian Facilities Project 21‐13 Airport Demonstration Garden 21‐14 Airport Regional Concourse Gate 16 Taxiway Repair 21‐15 WWTP Fiber Optic Line 21‐16 Demuth Dog Park 21‐17 Arnico Tract Sewer – Phase 4 21‐18 2021 Sewer Repairs 21‐19 Airport LED Video Ribbon 21‐21 Airport Control Room EMF Survey 21‐22 Desert Highland Ballfield Project 21‐24 Organics Analysis 21‐25 Traffic Plan Review 21‐26 Airport Storage Spaces 21‐27 Airport Taxiway Rehabilitation 21‐28 Airport Shared Use 21‐29 Airport Wildlife Hazard Assessment 21‐30 Airport Hot Spots Study 21‐31 Airport Parking Surveying and Striping 21‐32 Swim Center Shade Structures 21‐33 Airport Miscellaneous Stormwater Concrete Improvements 22‐02 Annual Slurry Seal 22‐04 Rim Road Improvement Project 22‐05 Navigation Center 22‐08 Annual Pavement Rehabilitation 22‐13 WWTP Odor Control Study 22‐14 Convention Center Carpet Replacement 22‐15 Convention Center Exhibit Hall Air Wall and Acoustic Tile Refurb 22‐16 Convection Center Jackie Lee Houston Plaza 22‐17 Convention Center Marquee Upgrade 22‐18 Convention Center Retrofit Lighting Controls 22‐19 Fire Station #1 Capital Project 22‐20 Measure J Community Initiated Projects 22‐21 Pedestrian Safe Routes to Schools Projects
City Project Numbers CP # Project Name 22‐22 Annual Sign and Striping Replacements 22‐23 Annual Traffic Calming Projects 22‐24 Pickleball Courts 22‐25 Shade Structures – Demuth and Baristo Playgrounds 22‐26 San Rafael Turf Conversion 22‐27 Racquet Club Drive Road Diet 22‐28 Victoria Park Gazebo 22‐29 Sonora/Farrell and Sonora/El Cielo Enhanced Crosswalks