Loading...
HomeMy WebLinkAbout1GCity Council Staff Re{Jort DATE: April 8, 2021 CONSENT CALENDAR SUBJECT: ACCEPTANCE OF THE EAST PALM CANYON DRIVE PEDESTRIAN SAFETY IMPROVEMENTS, CITY PROJECT NO. 17-09 FROM: BY: SUMMARY: David H. Ready, City Manager Development Services Department Formal City Council acceptance of the East Palm Canyon Drive Pedestrian and Bicycle Safety Improvements, City Project No. 17-09 is required to document the completion of the public works improvements, and to allow the City's filing of a Notice of Completion with the Riverside County Recorder in accordance with Section 9200 of the California Civil Code. RECOMMENDATION: 1. Accept the public works improvement identified as the East Palm Canyon Drive Pedestrian Safety Improvements, City Project No. 17-09 as completed in accordance with the plans and specifications; and 2. Authorize the City Engineer to execute and file for recordation with the Riverside County Recorder a Notice of Completion for the East Palm Canyon Drive Pedestrian Safety Improvements, City Project No. 17-09. BACKGROUND: On December 19, 2018, City Council Awarded a Construction Contract in the amount of $4,259,958 to International Line Builders, Inc., (the "Contractor''), for the construction of the Palm Canyon Drive Pedestrian Safety Improvements, City Project 17-07 and the East Palm Canyon Drive Pedestrian Safety Improvements, City Project 17-09. A copy of the staff report is included as Attachment 1. ITEM NO. \ G ---- 1 City Council Staff Report April 8, 2021 --Page 2 Acceptance of CP 17-09 STAFF ANALYSIS: This contract included work related to two separate capital projects: • Palm Canyon Drive Pedestrian Safety Improvements, City Project 17-07 ("CP17-07"); • East Palm Canyon Drive Pedestrian Safety Improvements, City Project 17-09 ("CP17- 09") Prior to commencing with construction of either of these capital projects, the City was underway with construction of a third capital project: Indian Canyon Drive Two Way Conversion and Pedestrian Enhancements, City Project 17-08 ("CP17-08"). CP17-08 included traffic signal modifications that resulted in traffic congestion and other issues that the City Council requested Staff to investigate and mitigate to the extent possible. The original design for CP17-07 included many of the same traffic signal modifications and other changes that were of concern with CP17-08. On that basis, Staff provided direction to the Contractor to suspend work related to CP17-07 and a change order was issued to eliminate the work not completed with CP17-07 that resulted in a deduction of ($2,941,803) to the original contract amount. It is the intention to complete the revised design for CP17-07 this year and re-advertise for bids. The remaining funds available for CP17-07 are specific to the CVAG Bicycle/ Pedestrian Safety Grant previously awarded by CVAG to the City for CP17-07 and cannot be used for another project. The remaining project was actively constructed through 2019 and 2020 with delays and interruptions caused by the COVID-19 pandemic. The project was determined to be complete on March 9, 2021. A Notice of Completion has been prepared and is included as Attachment 2. FISCAL IMPACT: The contract amount was $4,259,958. Over the course of the project a total of 5 change orders were issued for a cumulative reduction of ($2,470,971) reducing the original contract amount to $1,788,989. The remaining balance is reserved from the CVAG Bicycle/Pedestrian Safety Grant and related Measure J local match funds required to complete CP17-07 at a later date, and cannot be used for a different capital project. 2 City Council Staff Report April 8, 2021 --Page 3 Acceptance of CP 17-09 SUBMITTED: ~ C -~i T-linn Fagg, AIC Director of Development Services City Manager Attachments: 1. Staff Report -Award CP 19-07 and 19-09 2. Notice of Completion 3 Attachment 1 4 Cit)' Council Staff ReQ.ort DATE: December 19, 2018 NEW BUSINESS SUBJECT: AWARD A CONSTRUCTION CONTRACT TO INTERNATIONAL LINE BUILDER'S, INC., A CALIFORNIA CORPORATIONt IN THE AMOUNT OF $4,259 1 958 FOR THE PALM CANYON DRIVE PEDESTRIAN IMPROVEMENTS IN DOWNTOWN 1 CITY PROJECT NO. 17-071 AND PEDESTRIAN SAFETY IMPROVEMENTS ALONG SOUTH AND EAST PALM CANYON DRIVE CORRIDOR, CITY PROJECT NO. 17-09 FROM: David H. Ready, City Manager BY: Engineering Services Department SUMMARY Award of this contract will allow the City to proceed with construction of the Palm Canyon Drive Pedestrian Improvements in Downtown, City Project No. 17-07, anti Pedestrian Safety Improvements along South and East Palm Canyon Drive Corridor! City Project No. 17-09. RECOMMENDATION: 1. Dismiss the bid protest by Calpromax Engineering, Inc. dated November 26, 2018; 2. Waive any informality (non-responsiveness), and award a construction contract (Agreement No. __ ) to International Line Builder's, Inc., a Delaware corporation, in the amount of $4,259,958 for Bid Schedules A, Band C, for the Palm Canyon Drive Pedestrian Improvements in Downtown, City Project No. 17-07, and Pedestrian Safety Improvements Along South anll East Palm Canyon Drive Corridor, City Project No. 17-09; 3. Delegate authority to the City Mana~er to approve and execute construction contract change orders up to the cumulative total of $425,996 with all change orders reported to the City Council; and 4. Authorize the City Mana~er to execute all necessary documents. fi'EM NO. _5_._~_. __ 5 City Council Staff Report December 19, 2018 --Page 2 Award Construction Contract City Projects 17-07 & 17-09 BUSINESS PRINCIPAL DISCLOSURE: According to a Statement of Information filed with the California Secretary of State, International Line Builder's Inc., is a Delaware corporation whose corporate officers are: Jeffrey Thiede (CEO), Daniel Kuntz (Secretary), and Jon Hunke (CFO). A full listing of the officers of International Line Builder's Inc., is included as Attachment 1. The parent company of International Line Builders, Inc., is MDU Construction Services, Inc., who is a subsidiary of MDU Resources Group, Inc., a multi-billion dollar company publically traded on the New York Stock Exchange since 1948 under the symbol "MDU", with 196 million publicly held shares with a value of over $5 billion. The largest shareholders are all institutional holdings, mutual funds, and other corporations. No individual holds shares with a value of over 5%. BACKGROUND Early in 2017, the ONE-PS Code Enforcement and Public Works Committee discussed possible mitigations for traffic collisions involving bicycles and pedestrians with the Engineering Services Department {Engineering). Engineering staff analyzed data from Palm Springs Police Department (PSPD) along the City's major corridors and identified a high concentration of accidents that warranted further review to improve bicyclist and pedestrian safety. ONE-PS, PSPD, and Engineering staff also coordinated with the Measure J Commission in its solicitation of community projects for potential funding with future Measure J funds. A careful in-depth evaluation of past bicycle and pedestrian accident history was done on the City's major corridors, considering the severity of the accident, time of day, day of week, existing traffic conditions. The City came up with seven priority projects that included new signals, pedestrian crosswalks, shortening crossing distances, adding pedestrian countdown heads, increased lighting at crosswalks and intersections, adding high visibility striping and making corner ramps more accessible. In the spring of 2017, the Coachella Valley Association of Governments (CVAG) released a Call for Projects for $1 O million in Measure A grant funding related to CVAG's Bicycle and Pedestrian Safety Program. In response to its Call for Projects, Engineering staff submitted grant applications for the seven priority projects focused on mitigating bicyclist and pedestrian accidents occurring on various major corridors. CVAG approved 5 of the City's grant applications, including the City's grant for Pedestrian Safety Enhancements at signalized intersections along the Downtown Palm Canyon Drive Corridor and another grant for pedestrian crosswalks and lighting enhancements along East Palm Canyon Drive to South Palm Canyon Drive. On October 4, 2017, the City Council approved a reimbursement agreement with CVAG for the Project, and authorized the issuance of a purchase order to Albert A. Webb & Associates to proceed with final design for the two projects. A map of the final project locations can be found as Attachment 2. 2 6 City Council Staff Report December 19, 2018 --Page 3 Award Construction Contract City Projects 17-07 & 17-09 The Palm Canyon Drive Pedestrian improvements in Downtown, City Project No. 11~01, was designed to address the significant number of accidents that occurred in the corridor. Figures 1 and 2 show the 17 accidents that occurred between 2006-2016 on Palm Canyon Drive in the Downtown area, and the severity of those accidents. ~ 0, ~ ~- s C.ihuill.l Rd;: . 0-. m >· .:: .,,, r-Nsi .... ;.. ... i t;::.,,ht ,$",.r .... :~ ;; ;;· :E ~ ~ ~ -~ "··:~.~ .; :~.»· :~, -~ (, t • ~ Figure 1 -Locations of Pedestrian and Bicycle Accidents on Palm Canyon Drive 2006-2016 Number of Colh~ions lJy Collision Severily IO Collision Severity Count % Collision Severity 3 • ln;ury (Oths.:f Visible) 35 .25% Figure 2 -Severity of Injuries Pedestrian and Bicycle Accidents on Palm Canyon Drive 2006-2016 The scope of City Project 17-07 includes upgrades to traffic signal equipment, including pedestrian countdown heads, accessible pedestrian signals, high visibility crosswalks, improved lighting, protected left turn phases, and other improvements at eleven intersections along Palm Canyon Drive: • Tachevah Drive/Via Lola • Tahquitz Canyon Way** • Tam a risk Road • La Plaza • Gran via Valmonte • Arenas Road *"' • Alejo Road • Baristo Road • Amado Road ** • Ramon Road • Andreas Road ** 3 7 City Council Staff Report December 19, 2018 --Page 4 Award Construction Contract City Projects 17-07 & 17-09 ** Note -Amado Road, Andreas Road, Tahquitz Canyon Way, and Arenas Road intersections will have a new "Pedestrian Scramble" -an all pedestrian crossing where pedestrians will have total access a nd may cross diagonally across the intersection, as shown in the photograph below. A scr a m b le cro ssuig at t he b :;y lnters ect,c,n ~t Hot!ywr:0d a nd r frghla n d . Phot t""1 via L..t.. Greo : Str:::.-:-t.::;, Curb extensions (pop-outs) are also included at the following locations: • Amado Road -all four corners • Tahquitz Canyon Way -NE corner • Baristo Road -SW and SE corners • Ramon Road The Pedestrian Safety Improvements along South and East Palm Canyon Drive Corridor City Project No 17-09, was designed to address the significant number of accidents that occurred in the corridor. Figures 3 and 4 show the 9 accidents that occurred between 2006-2016 on South Palm Canyon Drive and East Palm Canyon Drive, and the severity of those accidents. 4 8 City Council Staff Report December 19, 2018 --Page 5 Award Construction Contract City Projects 17-07 & 17-09 ... .. i 11' '<lo E f' ~li'f1 f:.;..i\t<fti Or . Ql~t> Cµ N ii ~ C • 3 o 7i Oreo C,1 5 o::-:.-{',,, ~ .. " Figure 3 -Locations of Pedestrian and Bicycle Accidents on S Palm Canyon Drive and E Palm Canyon Drive 2006-2016 Numb,;>t of Vicums by V1ctm1 Ot>{Jr,::e of 11,JUIY v :wm Dezree ol 1njury (Oliflt Victim Degree of Injury Figure 4 -Severity of Injuries Pedestrian and Bicycle Accidents on S Palm Canyon Drive and E Palm Canyon Drive 2006-2016 The scope of City Project 17-09 includes installation of new pedestrian crosswalks with rectangular rapid flashing beacons with in-pavement flashing lights, and street lights, at the following locations along S. Palm Canyon Dr. and E. Palm Canyon Dr.: • Sonora Road • Avenida Palmera • Deep Well Road • Sagebrush Road City Project 17-09 also includes a traffic signal upgrade at S. Palm Canyon Dr. / E. Palm Canyon Dr. Finally, City Project 17-09 includes installation of a new electrical and street lighting system through the "curve" from S. Palm Canyon Dr. to E. Palm Canyon Dr., which includes 12 new street lights to improve sight distance and visibility for pedestrians, bicyclists and vehicles at night. 5 9 City Council Staff Report December 19, 2018 --Page 6 Award Construction Contract City P rejects 17 -07 & 17-09 On October 17, 2018, the City Council approved the plans, specifications and estimate; and authorized staff to advertise and solicit bids for Palm Canyon Drive Pedestrian Improvements in Downtown, City Project No. 17-07, and Pedestrian Safety Improvements along South and East Palm Canyon Drive Corridor, City Project No. 17-09, (the "Project"). STAFF ANALYSIS: On October 20, 2018 and October 27, 2018, staff advertised the Project for bids in the Desert Sun, submitted the Notice Inviting Bids to plan rooms 1 , and provided the contract documents free of charge to prospective bidders. On November 20, 2018 at 3:00 p.m., the Procurement and Contracting Division received four (4) bids from the following contractors listed in Table 1: Company Location Bid Amount International Line Builder's, Inc. Riverside, CA $4,259,958.00 Calpromax Engineering, Inc. Placentia, CA $4,707,997.00 DBX, Inc. Temecula, CA $4,852,091.00 PTM General EnQineerinQ Services, Inc. Riverside, CA $4,994,978.40 Table 1 The low bid of $4,259,958 is approximately 5.4% below the engineer's estimate of $4,850,000. The complete bid summary is included as Attachment 3. Bid Protest During the bid opening staff determined that the bid submitted by International Line Builder's, Inc., ("ILB") did not include the bid summary pricing page that identifies the total sum of each of the separate Bid Schedules A+B+C. At the bid opening, staff was unable to read aloud the total bid amount submitted by ILB, therefore, Calpromax Engineering, Inc., ("Calpromax"), was announced as the apparent low bidder, subject to the City's further review of all bids submitted for a determination of responsiveness. Following staff's review, the total bid price for ILB was determined by adding the respective sub-totals identified on each Bid Schedule sheet in its bid, identifying ILB as the apparent low bidder. In consultation with the City Attorney, a determination was made that ILB's failure to submit the bid summary pricing page was not a material defect in ILB's bid as the City could determine the total bid price, and that ILB is the low bidder. 1 A Plan Room is a "library" where construction professionals may view bidding documents (blueprints and specifications) for projects seeking price estimates for specific construction products or services. There are 9 various plan rooms in southern California where the City submits its bid documents to ensure all contractors within the area are aware of the bid solicitation. 6 10 City Council Staff Report December 19, 2018 --Page 7 Award Construction Contract City Projects 17-07 & 17-09 On November 21, 2018, staff advised all of the bidders of the City's determination to find ILB as the apparent low bidder. On November 26, 2018, Calpromax, the second lowest bidder filed a bid protest, a copy is included as Attachment 4. In accordance with Chapter 7.08.030 of the Palm Springs Municipal Code, the City Engineer evaluated Calpromax's bid protest and responded by letter dated November 29, 2018, included as Attachment 5. As noted in the City's response to Calpromax's bid protest, the argument that ILB's failure to submit one of the "core" bid forms of the bid package was fatal to ILB's responsiveness to the bid was not persuasive, and ILB's oversight in the missing bid summary pricing page amounted to a minor irregularity that was-not consequential to the bid. The City responded by stating: California courts have historically upheld municipal discretion to waive bidding irregularities in low bids when those irregularities are inconsequential, i.e, they do not affect the amount of the bid or afford the bidder an unfair advantage over other bidders See e.g. Bay Cities Paving & Grading, Inc. v. City of San Leandro 223 Cal. App. 4th 1181 (2014) and Ghilotti Construction Co., v. City of Richmond (1996) 45 Cal. App. 4th 897,904. Further, the California Legislature adopted public bidding laws and requirements for the benefit of the public and public-agencies, and not for the financial benefit or gain of any particular bidder. As cited in Ghilotti, referring to Judson Pacific- Murphy Corp. v. Durkee [(1956) 144 Cal. App. 2d 337, 383]: It certainly would amount to a disservice to the public if a losing bidder were to be permitted to comb through the bid proposal or license application of the low bidder after the fact [and] cancel the low bid on minor technicalities, with the hope of securing acceptance of his, a higher bid. Such construction would be adverse to the best interests of the public and contrary to public policy. The City has thoroughly reviewed the bid submitted by ILB and found the rest of ILB's bid submittal to be complete. With no other bid irregularities which would otherwise be considered material to the bid, it is our intention to award the contract to ILB. This determination has been made in accordance with Paragraph N-3(a) "Award of Contract" of the Notice Inviting Bids for this project, which states: The City reserves the right after opening bids to reject any or all bids, to waive any informality (non-responsiveness) in a bid, or to make award to the lowest responsible bidder, on the basis of the total sum of base Bid Schedules A, B, and C, and reject all other bids, as it may best serve the interest of the City. 7 11 City Council Staff Report December 19, 2018 --Page 8 Award Construction Contract City Projects 17-07 & 17-09 Calpromax failed to submit an appeal of the City Engineer's decision to the City Manager by the December 6, 2018, deadline. Staff recommends the City Council waive any informality in ILB's bid, and award a construction contract to ILB for Bid Schedules A, B and C. Public Works Contractor Registration Law (SB 854) Under California Labor Code Section 1771.1, as amended by Senate Bill (SB) 854 (2014), unless registered with the State of California Department of Industrial Relations (DIR), a contractor may not bid, nor be listed as a subcontractor, for any bid proposal submitted for public works projects on or after March 1, 2015. Similarly, a public entity cannot award a public works contract to a non-registered contractor, effective April 1, 2015. Staff has reviewed the DIR's contractor registration database, and has confirmed that ILB is registered with the DIR, and is appropriately licensed. Staff has determined that ILB submitted the lowest responsive bid. Staff reviewed the bid, references, and contractor's license, and found ILB to be properly licensed and qualified. A construction contract with ILB for the subject Project is included as Attachment 6. Local Business Preference Compliance Section 7.09.030 of the Palm Springs Municipal Code, "Local Business Preference Program," requires prime contractors to use good faith efforts to sub-contract the supply of materials and equipment to local business enterprises and to sub-contract services to businesses whose work force resides within the Coachella Valley. ILB is not considered a local business; however, they have demonstrated sufficient evidence of good faith efforts to sub-contract the supply of materials and equipment to local businesses. ENVIRONMENTAL IMPACT: Section 21084 of the California Public Resources Code requires Guidelines for Implementation of the California Environmental Quality Act (11 CEQA 11 ). The Guidelines are required to include a list of classes of projects which have been determined not to have a significant effect on the environment and which are exempt from the provisions of CEQA. In response to that mandate, the Secretary for Resources identified classes of projects that do not have a significant effect on the environment, and are declared to be categorically exempt from the requirement for the preparation of environmental documents. In accordance with Section 15301 "Existing Facilities," Class 1 projects consist of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public structures, facilities, mechanical equipment or topographical features involving negligible or no expansion of use beyond that existing at the time of the lead agency's determination. Therefore, in accordance with Section 15301 (c), staff has determined that the Palm Canyon Drive Pedestrian Improvements in Downtown, City Project No. 17-07, and East Palm Canyon/South Palm Canyon Drive Pedestrian Improvements, City Project No. 17-09, is considered categorically exempt from CEQA 8 12 City Council Staff Report December 19, 2018 --Page 9 Award Construction Contract City Projects 17-07 & 17-09 and a Notice of Exemption has been prepared and filed with the Riverside County Clerk, included as Attachment 7. FISCAL IMPACT: The City was awarded grants from CVAG for 5 different capital projects related to pedestrian and bicycle safety (the "CVAG Safety Projects"). The total cost of these five projects was estimated at $9.1 m with CVAG providing funding in the amount of $6.2m requiring a local match of $2.9m. The City Council has previously awarded contracts to construct 3 of the 5 CVAG Safety Projects, this is the final 2 CVAG Safety Projects which are being bundled together as one capital project for construction. The CVAG reimbursement agreement provides a not-to-exceed amount of $1,989,000 in Regional Measure A funding for the Palm Canyon Drive Pedestrian Improvements in Downtown, City Project No. 17-07. The reimbursement agreement also provides a not-to exceed amount of $1,255,500 in Regional Measure A funding for the Pedestrian Safety Improvements along South and East Palm Canyon Drive Corridor City Project No 17-09, for a combined total not-to-exceed grant amount of $3,244,500. Pursuant to the terms of the CVAG Reimbursement Agreement, the City is required to be "in construction" by December 2018; in consultation with CVAG staff, staff was advised that the City's award of a construction contract would be considered compliance with the terms of the agreement. Previously, on October 21, 2015, the City Council approved the Measure J Commission's 3-year program of Community Projects, establishing funding for 46 various projects as follows: Fiscal Year (FY) 2015/16-$1,028,000; FY 2016/17-$965,000; and FY 2017/18 -$1,202,000; for a total of $3.195m over 3 years. Some of this funding has been used for various projects completed, however, a majority of the various Community Projects were assembled by the Engineering Department into a single capital project (the Measure J Community Projects -Sidewalk Gap Closure Improvements, City project No. 15-31 ["CP 15-31"]). The City solicited bids and scheduled award of a contract in the amount of $1,838,900.50 for this project at the April 4, 2018, City Council meeting. At that time the Council tabled the item until further discussion on capital project funding occurred as part of the 2018/19 fiscal year budget. · At the June 6, 2018, City Council meeting, the Council directed staff to seek other sources of funding for CP 15-31. Subsequently, at the June 20, 2018, City Council meeting, the Council rejected the bids received for CP 15-31 and authorized staff to submit an application through the Active Transportation Program Cycle 4 ("ATP4") funding cycle for it. Staff submitted the ATP4 grant application in July 2018; the state intends to announce grant recipients by December 31, 2018. On the basis of these actions, on the expectation of the City receiving the ATP4 grant funds, the balance of the Community Projects funding 9 13 City Council Staff Report December19,2018-Page10 Award Construction Contract City Projects 17-07 & 17-09 previously budgeted in FY 2015/16, FY 2016/17, and FY 2017/18 approximately $2.15m and is available for other capital projects. On December 6, 2018, the Measure J Commission was given an update on the Project and alternatives for providing the local match required. At that time, the Measure J Commission voted unanimously to recommend to Council to reallocate the remaining funds of $2.15m for the original 3-year Community Projects funding as the City's local match for these 2 CV AG Safety Projects2 • Staff recommends the Council approve allocation of the remaining $2.2m in Measure J Community Projects funding for the local match to the CVAG funding for the Project. The final cost estimate and funds available for the Project are identified in the following Table 2: Table of Project Costs Amount CVAG Bicycle/Pedestrian Safety Grants $3,244,500 Measure J Funds -Prior Fiscal Year · $200,000 Measure J Funds -(Community Projects Balance) $2,154,730 DesiQn ($400,420) Project Administration (thru 9/28/18) · ($48,527) Project Administration (Estimated) ($25,000) Construction Management/I ns~!3_9tion (Estimateq) _ . ($350,000) Construction Contract ($4,259;958) . ·-·----. . ··----···---~--. --· .. Contingency( 1 0% )JEstimated) ------··-··-·· . ·--·· .. .. ····-_($425,996)· Balance Remaining: $89,329 Table 2 With the City Council's approval (as recommended by the Measure J Commission) to allocate the remaining $2.1 Sm in Measure J Community Projects funding (previously budgeted in FY 2015/16, FY 2016/17, and FY 2017/18), there are sufficient funds to award the contract. 2 At the October 4, 2017, City Council meeting, as part of the Council's action to approve the various CVAG Reimbursement Agreements for the Safety Projects, Council did take action to "Reserve the amount of $2,000,000 from the Measure J Fund in the 2018/19 Fiscal Year for the Measure J Community Projects (Traffic Hot Spots 2.0 Program) to be used for the required CVAG local match for the 2017 Bicycle and Pedestrian Safety Program· projects." The recommendation to utilize the remaining funds from the original Measure J Community Projects funding would eliminate the requirement to allocate $2m from the FY18/19 Measure J budget as the local match for the Project. 10 14 City Council Staff Report December 19, 2018 --Page 11 Award Construction Contract City Projects 17-07 & 17-09 Sufficient funds are budgeted and available to award the construction contract in the total amount of $4,259,958 from the following accounts: City Proiect 17-07 (Bid Schedule A); $2,941,803 Regional Measure A Fund, Account 134-4497-50348; $1,750,000 Measure J Fund, Account 260-4494-50348; $1,191,803 City Proiect 17-09 (Bid Schedules 8 & C); $1,318,155 Regional Measure A Fund, Account 134-4497-50350; $988,616.25 Measure J Fund, Account 260-4494-50350; $329,538.75 SUBMITTED: ~ Marcus L. Fuller, MPA, PE, PLS ~~~~-- Assistant City Manager City Manager Attachments: 1 . I LB Office rs 2. Map of Locations 3. Bid Summary 4. Bid Protest -Calpromax 5. Bid Protest Response -City 6. Construction Contract 7. CEQA Notice of Exemption 11 15 Attachment 2 16 Recording Requested By: City of Palm Springs When Recorded Mail To: Name Anthony J. Mejia, City Clerk Street Address 3200 E. Tahquitz Canyon Way City& State Palm Springs, CA 92262 SPACE ABOVE THIS LINE FOR RECORDERS USE NOTICE OF COMPLETION (CA Civil Code§§ 8180-8190, 8100-8118, 9200-9208) NOTICE IS HEREBY GIVEN THAT: 1. The undersigned is an owner of an interest of estate in the hereinafter described real property, the nature of which interest or estate is: _F_ee _____________________________ (e.g. fee, leasehold, joint tenancy, etc.) 2. The full name and address of the undersigned owner or reputed owner and of all co-owners or reputed co-owners are: Name Street and No. City State City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs CA 92262 3. The name and address of the direct contractor for the work of improvement as a whole is: International Line Builders, Inc. 4. This notice is given for (check one): r2I Completion of the work of improvement as a whole. • Completion of a contract for a particular portion of the work of improvement (per CA Civ. Code § 8186). 5. If this notice is given only of completion of a contract for a particular portion of the work of improvement (as provided in CA Civ. Code § 8186), the name and address of the direct contractor under that contract is: Not Applicable 6. The name and address of the construction lender, if any, is: Not Applicable 7. On the 9th day of March , 203.!_, there was completed upon the herein described property a work of improvement as a whole ( or a particular portion of the work of improvement as provided in CA Civ. Code § 8186) a general description of the work provided: City Project 17-09, East Palm Canyon Drive Pedestrian Enhancements 8. The real property herein referred to is situated in the City of _P_al_m_S_pr_in_gs ______ , County of _R_iv_er_si_de ______ _ State of California, and is described as follows: Construction of street lighting systems, lighted crosswalks, Concrete Ramps and Walkways, Traffic Signal Modifications, Striping and Signage 9. The street address of said property is: East Palm Canyon Drive and South Palm Canyon Drive between the intersections of Sunrise Way and Mesquite Ave. 10. If this Notice of Completion is signed by the owner's successor in interest, the name and address of the successor's transferor is: Not applicable I certify (or declare) under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Date: ______________ _ By: _________________ _ Signature of Owner or Owner's Authorized Agent Joel Montalvo/City Engineer City of Palm Springs Page 1 of2 17 VERIFICATION I, Joel Montalvo , state: I am the City Engineer ~ ("Owner", "President", "Authorized Agent'', "Partner", etc.) of the Owner identified in the foregoing Notice of Completion. I have read said Notice of Completion and know the contents thereof; the same is true of my own knowledge. I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct. Executed on ___________ (date), at Palm Springs (City), s;A__ (State). Signature of Owner or Owner's Authorized Agent Joel Montalvo, City Engineer City of Palm Springs PROOF OF SERVICE DECLARATION STATE OF CALIFORNIA COUNTY OF ___________ _ On ______________ , ___ (date), before me, ________________ , Notary Public (name and title of officer) personally appeared _______________ who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument. I certify under PENAL TY OF PURJURY under the laws of the State of California that the foregoing paragraph is true and correct. Witness my hand and official seal. Page 2 of2 Signature 18