Loading...
HomeMy WebLinkAboutA7164 - MATICH CORPORATION - 2018 Pavement RehabCITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: Matich Corporation P.O. Box 10 Highland, OA 92346 P (909)382-7400 F (909)382-0169 Attn: George Fonville February 7, 2019 Project No: 18-01 Project: 2018 Pavement Rehabilitation Change Order No: 02 Purchase Order: 19-0758 Account: 133-4298-50251 133-4298-50299 133-4498-50225 134-4498-50242 135-4370-55000 260-4493-50812 260-4500-59464 261-4490-50812 CHANGES IN WORK: Sunrise Way - Via Escuela to Racquet Club Rd & Francis Or to San Rafael Rd This change order provides for Extra Work at Agreed Unit Prices for the completion of additional cold-milling at a 2-inch depth, installation of AC overlay, removal and replacement of ADA curb ramps, installation of pavement markings, and the adjustment of water valves, manholes, and survey monuments. Below is a breakdown of the additional costs for this change. Price listed below is inclusive of all costs and markups. Item No.Item Description Quantity Unit Price Total 2-1 Mobilization 1 LS $36,620.00/LS $36,620.00 2-2 Water Pollution Control 1 LS $6,300.00/LS $6,300.00 2-3 Traffic Control 1 LS $21.000.00/LS $21,000.00 2-4 Cold Plane AC Pavement - 2" depth 189,053 SF $0.40/SF $75,621.20 2-5 2" AC Overlay 2,311.37 Ton $68.00/Ton $157,173.16 2-6 Striping and Signage 1 LS $28,380.00/LS $28,380.00 2-7 Adjust Water Valves 20 EA $1,000.00/EA $20,000.00 2-8 Adjust Sewer Manholes 16 EA $850.00/EA $13,600.00 2-9 Survey Monuments 5EA $1,500.00/EA $7,500.00 2-10 Remove and Replace Curb Ramps - Small 2EA $2,900.00/EA $5,800.00 2-11 Remove and Replace Curb Ramps - Large 13EA $4,800.00/EA $62,400.00 Subtotai $434,394.36 Contract Change Order No. 02 February 7, 2019 Page 2 East Palm Canyon Drive - Drainage Improvements This change order provides for Extra Work at Agreed Lump Sum Price for the completion of drainage improvements on East Palm Canyon Drive, East of Araby Rd. Work includes sawcutting, removal of existing asphalt and berm, installation of base, and installation of asphalt pavement and AC dike. Price is inclusive of all costs and markups. Item No. Item Description Quantity Unit Price Total 2-12 East Palm Canyon Drainage Improvements 1 LS $24,804.00/LS $24,804.00 Subtotal $24,804.00 Base Bid - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative B as indicated below. Item No. Item Description Quantity Unit Price Total 6 Roadway Pulverization +1,775 SF $0.20/SF $355.00 8 Pulverized Base Material +1,775 SF $0.15/SF $266.25 9 2" Cold Mill AC Pavement +9,200 SF $1.15/SF $10,580.00 10 2" Asphalt Concrete Overlay Type C2 +132.88 Ton $80.00/Ton $10,630.40 11 Asphalt Concrete Type C2 (Depth 2.5")+206.73 Ton $63.00/Ton $13,023.99 12 Asphalt Concrete Type C2 (Depth 3")-256.89 Ton $63.00/Ton ($16,184.07) 13 Remove and Reconstruct Curb Ramp Type A -1 EA $3,400.00/EA ($3,400.00) 14 Remove and Reconstruct Curb Ramp Type B -2EA $3,400.00/EA ($6,800.00) 17 Install Type E Vehicle Detection Loop -1 EA $340.00/EA ($340.00) Subtotal $8,131.57 Base Bid - Adjustment of Compensation at Agreed Lump Sum This change order provides an Adjustment of Compensation at Agreed Lump Sum for unused field orders item: Item No. Item Description Quantity Unit Price Total 19 Field Orders -1 LS $101,696.27/LS ($101,696.27) Subtotal ($101,696.27) Contract Change Order No. 02 February 7, 2019 Page 3 Additive Bid Alternate A - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative B as indicated below. Item No. Item Description Quantity Unit Price Total 6 Roadway Pulverization -382 SF $0.20/SF ($76.40) 8 Pulverized Base Material -382 SF $0.16/SF ($61.12) 9 Asphalt Concrete Type 02 (Depth 2.5")+278.73 Ton $63.00/Ton $17,559.99 10 Asphalt Concrete Type C2 (Depth 3")-1.59 Ton $64.00/Ton ($101.76) 13 Remove and Reconstruct Curb Ramp Type A +1 EA $3,400.00/EA $3,400.00 14 Remove and Reconstruct Curb Ramp Type B +2EA $3,400.00/EA $6,800.00 Subtotal $27,520.71 Additive Bid Alternate A - Adjustment of Compensation at Agreed Lump Sum This change order provides an Adjustment of Compensation at Agreed Lump Sum for unused field orders item: Item No. Item Description Quantity Unit Price Total 16 Field Orders -1 LS $28,208.18/LS ($28,208.18) Subtotal ($28,208.18) Additive Bid Alternative B - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative B as indicated below Item No. Item Description Quantity Unit Price Total B-5 Remove Existing Curb and Gutter +25 LF $46.00/LF $1,150.00 B-6 Remove Portion of Existing PCC Cross-gutter & Spandrel -2SF $20.00/SF ($40.00) B-7 Remove Portion of Existing Driveway Apron +52.5 SF $15.00/SF $787.50 B-8 Remove Sidewalk -21 SF $10.00/SF ($210.00) B-11 Construct Rolled Curb per City Std. 202 +24 LF $61.00/LF $1,464.00 B-13 Construct Portion of PCC Cross-gutter and Spandrel per City Std. 202 and 206 and per Plans -10 LF $20.00/LF ($200.00) B-14 Construct 6" Thick PCC Driveway Apron per City Std. 201 +52.5 SF $15.00/SF $787.50 B-15 Construct 4" Thick PCC Sidewalk per City Std. 210 -21 SF $15.00/EA ($315.00) B-16 Construct 8" PVC (SCH 40) Storm Drain -12 LF $325.00/LF ($3,900.00) B-19 Concrete Encasement -4.75 CY $350.00/CY ($1,662.50) B-20 Asphalt Concrete Type C2 (Adjacent to Curb, Pipe Trench and Roadway) -2.93 Tons $79.00/Ton ($231.47) B-21 AC Leveling Course (Variable Depth)-80 Tons $96.00yTon ($7,680.00) B-22 Cold mill 2" Uniform Depth (Roadway and for AC Trench Replacement) -442 SF $1.25/SF ($552.50) Subtotal ($10,602.47) Contract Change Order No. 02 February 7, 2019 Page 4 Additive Bid Alternative B - Adjustment of Compensation at Agreed Lump Sum This change order provides an Adjustment of Compensation at Agreed Lump Sum for unused field orders item: Item No. Item Description Quantity Unit Price Total B-23 Field Orders -1 LS $6,000.00/LS ($6,000.00) Subtotal ($6,000.00) Additive Bid Alternative 0 - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative C as indicated below. Item No. Item Description Quantity Unit Price Total C-4 Roadway Pulverization (Depth = 9")-16000 SF $0.50/SF ($8,000.00) C-6 Pulverized Base Material (Depth 6")+344 SF $0.27/SF $92.88 C-7 Asphalt Concrete Type 02 (Depth = 3")+ 35 Tons $68.00/Ton $2,380.00 Subtotal ($5,527.12) Additive Bid Alternative C - Adjustment of Compensation This change order provides Adjustment of Compensation for two contract items. Parking lot was removed and disposed of rather than performing pulverization, which resulted in additional export costs. Also, adjustment of compensation is provided for unused field orders. Item No. Item Description Quantity Unit Price Total C-9 Field Orders -1 LS $2,000.00/LS ($2,000.00) Subtotal ($2,000.00) Additive Bid Alternative D - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative D as indicated below. Item No. Item Description Quantity Unit Price Total D-5 Construct 6" Curb Type A3' per City Std. 200 +13 LF $36.00/LF $468.00 D-6 Construct 6" Curb Type AT per City Std. 200 -22 LF $36.00/LF ($792.00) D-7 Construct 6" Curb (Modified Type AT) per Detail 3 -11 LF $20.00/LF ($220.00) D-8 Construct Curb Return and Cross Gutter Modified as shown in Plans per City Std. 205 -27 LF $15.00/LF ($405.00) D-9 Construct 6" thick concrete +335 SF $10.00/SF $3,350.00 Contract Change Order No. 02 February 7, 2019 Page 5 D-10 Construct 4" thick concrete +252 SF $10.00/SF $2,520.00 D-11 Replace AC Pavement per City Std. 115 +136 SF $27.00/SF $3,672.00 D-12 Construct 6" PCC Concrete on top of existing concrete parking garage deck per Detail 8 -34 SF $10.00/SF ($340.00) D-13 Construct 6" PCC Driveway per City Std. 201 +151 SF $18.00/SF $2,718.00 D-15 Construct Curb Ramp Type A per City Std. 202 with Truncated Domes +1 EA $3,400.00/EA $3,400.00 Subtotal $14,371.00 Additive Bid Alternative D - Extra Work at Agreed Lump Sum This change order provides Extra Work at Agreed Lump Sum Price for additional striping at Museum Drive which was not included in the bid documents. Due to the significant changes in the striping cost, credit was given for the signing and striping per the original bid documents and a cost provided for the modified work. Price is inclusive of all costs and markups. Item No. Item Description Quantity Unit Price Total D-18 Traffic Striping, Signage and Markings - Credit for Contract -1 LS $3,700.00/LS ($3,700.00) D-18A Traffic Striping, Signage and Markings - Revised 1 LS $7,000.00/LS $7,000.00 Subtotal $3,300.00 Additive Bid Alternative D - Adjustment of Compensation at Agreed Lump Sum This change order provides an Adjustment of Compensation at Agreed Lump Sum for unused field orders item: Item No. Item Description Quantity Unit Price Total D-19 Field Orders -1 LS $1,903.81/LS ($1,960.16) Subtotal ($1,960.16) Additive Bid Alternative D - Extra Work at Contract Unit Prices This change order provides Extra Work at Contract Unit Prices for additional cold-milling and AC overlay required at Museum Drive. In order to maintain positive drainage in the concrete curb improvements, it became necessary to perform cold-milling of the existing asphalt pavement and AC overlay to re-profile the street. Below is a breakdown of the costs for this additional work. Price is inclusive of all costs and markups. Item No. Item Description Quantity Unit Price Total D-20 2" Cold Mill AC Pavement 4,000 SF $1.15/SF $4,600.00 D-21 2" Asphalt Concrete Overlay Type C2 39.51 Ton $80.00/Ton $3,160.80 Subtotal $7,760.80 Total Change Order Amount $364,288.24 Contract Change Order No. 02 February 7, 2019 Page 6 CHANGES TO CONTRACT TIME: Fifteen (15) working days are being added as a result of this change order. SOURCE OF FUNDS: Funds are available from the following account(s): SUMMARY OF COSTS: Original Contract Amount: This Change Order: Previous Change Order(s): Revised Contract Amount: $ 5,095,265.00 $ 364,288.24 $ 22,805.54 $ 5,482,358.78 Original Completion Days Added Previous Days Added: Revised Completion 110 Work Days 0 Days 0 Days 110 Work Days \S\QmiURES ON NEXT PAGE] Contract Change Order No. 02 February 7, 2019 Page 7 have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor Matich Corporation y/ko/ f Interwest Consulting Group City of Palm Springs Recommended By: Approved By: Attest By: ignature Date Printed Name and Title (^nature Printed Name and Title Marcus Fuller, City Engineer Date Date y, City Manager nthony Mejia, Z\m bate n bate Distribution: Original Conformed Godv: Contractor (1) City Clerk (1) Conformed - File Codv: Engineering Pay File (1) City Proiect File (1) Purchasing (1) Finance (1) .O^flPPROVEP BY niTY W VIAGER CITY OF PALM SPRINGS CONTRACT CHANGE ORDER To: Matich Corporation P.O. Box 10 Highland. OA 92346 P (909)382-7400 F (909)382-0169 Attn: George Fonville April 10, 2019 Project No: 18-01 Project: 2018 Pavement Rehabilitation Change Order No: 03 Purchase Order: Account: 19-0758 133-4298-50251 133-4298-50299 133-4498-50225 134-4498-50242 135-4370-55000 260-4493-50812 260-4500-59464 261-4490-50812 CHANGES IN WORK: Mesquite Ave - Bike Lane Markings This change order provides for Extra Work at Agreed Unit Price for the completion of bike lane markings on Mesquite Ave between Sunrise Way and Compadre Rd. Price is inclusive of all costs and markups. Item No. Item Description Quantity Unit Price Total 3-1 Mesquite Ave Bike Lane Markings 19 EA $522.90/EA $9,935.10 Subtotal $9,935.10 Base Bid - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative B as indicated below. Item No. Item Description Quantity Unit Price Total 4 Standard Monument Type A -3 EA $1,500.00/EA ($4,500.00) 5 Standard Monument Type B -13 EA $415.00/EA ($5,395.00) 15 Adjust Water Valve to Grade - DWA Std. W111A +30 EA $1,000.00/EA $30,000.00 16 Adjust Sewer Manhole to Grade - City Std. 402 +8 EA $850.00/EA $6,800.00 Subtotal $26,905.00 Contract Change Order No. 03 April 10, 2019 Page 2 Additive Bid Alternate A - Contract Quantity Adjustments This change order provides for contract quantity adjustments for Additive Bid Alternative B as indicated below. Item No. Item Description Quantity Unit Price Total 4 Standard Monument Type A -9 EA $1,500.00/EA ($13,500.00) 5 Standard Monument Type B -10 EA $425.00/EA ($4,250.00) 13 Adjust Water Valve to Grade - DWA Std. W111A +18 EA $1,000.00/EA $18,000.00 Subtotal $250.00 Additive Bid Alternate A - Adjustment of Compensation at Agreed Lump Sum This change order provides an Adjustment of Compensation at Agreed Lump Sum for unused field orders item: Item No. Item Description Quantity Unit Price Total 16 Field Orders -1 LS $44,377.95/LS ($44,377.95) Subtotal ($44,377.95) Total Change Order Amount CHANGES TO CONTRACT TIME: Zero (0) working days are being added as a result of this change order. SOURCE OF FUNDS: Funds are available from the following account(s): ($7,287.85) Contract Change Order No. 03 April 10, 2019 Page 3 SUMMARY OF COSTS: Original Contract Amount: This Change Order: Previous Change Order(s): Revised Contract Amount: $ 5,095,265.00 $ (7,287.85) $ 387,093.78 $ 5,475,070.93 Original Completion Days Added Previous Days Added: Revised Completion 110 Work Days 0 Days 15 Days 125 Work Days [SIGNATURES ON NEXT PAGE] Contract Change Order No. 03 April 10, 2019 Page 4 1 have received a copy of this Change Order and the above AGREED PRICES are acceptable to Contractor Matich Corporation ^ y// ^/zo{ rz Interwest Consulting Group Citv of Palm Springs Recommended By: Approved By: Attest By: Signature Date ^1 ^ <l.T- C ^ printed Name and Title Siqnatiyre Date l^iXvS ^^CT7. 6roglY2^6t^<>0 Printed Name and Title Marcus Fuller, City Engineer M/A Date David H. Ready, City Manager Date Anthony MenaTICity Clerk lihfi Date Distribution: Original Conformed Copy: Contractor Citv Clerk (1) (1) Conformed - File Coov: Engineering Pay File (1) City Proiect File (1) Purchasing (1) Finance H) approved by deparment head PUBLIC INTEGRITY DISCLOSURE APPLICANT DISCLOSURE FORM 1. Name of Entity (Z ^ rP<^ 1^- A > loaJ 2. Address of Entity (Principle Place of Business) /?o • /o OA ^z.3y'<^ Local or California Address (if different than #2) 4. State where Entity is Registered with Secretary of State clA If other than California, is the Entity also registered in California? H Yes H No 5. Type of Entity ^Corporation □ Limited Liability Company □ Partnership □Trust □ Other (please specify) i. Officers, Directors, Members, Managers, Trustees, Other Fiduciaries (please specify) Note: If any response is not a natural person, please identify all officers, directors, members, managers and other fiduciaries for the member, manager, trust or other entity ^ T7 ^^Officer □Director □Member □Manager [name]^General Partner □ Limited Partner □ Other A^AT) ^^^fficer □ Director □ Member □ Manager [name]j^General Partner □ Limited Partner □ Other ^^ji^^fficer □ Director □ Member □ Manager rnamel .r[name] .^ □ General Partner □ Limited Partner /\4aAk T. CITY OF PALM SPRINGS - PUBLIC INTEGRITY DISCLOSURE APPLICANT DISCLOSURE FORM Page 1 of 2 (Revised 09 13 18) 7. Owners/Investors with a 5% beneficial interest in the Applicant Entity or a related entity EXAMPLE JANE DOE 50%, ABC COMPANY, Inc. [name of owner/investor][percentage of beneficial interest in entity and name of entity] A. [name of owner/investor][percentage of beneficial interest in entity and name of entity] B. [name of owner/investor][percentage of beneficial interest in entity and name of entity] C. [name of owner/investor][percentage of beneficial interest in entity and name of entity] D. [name of owner/investor][percentage of beneficial interest in entity and name of entity] E. [name of owner/investor][percentage of beneficial interest in entity and name of entity] 1 DECLARE UNDER PENALTY OF PERJURY UNDER THE LAWS OF THE STATE OF CALIFORNIA THAT THE FOREGOING IS TRUE AND CORRECT. Signature of Disclosing Party, Printed Name, Title Date CITY OF PALM SPRINGS - PUBLIC INTEGRITY DISCLOSURE FORM APPLICANT DISCLOSURE FORM Page 2 of 2 (Revised 09 13.18) LIBERTY MUTUAL SURETY PO Box11053 Orange, CA 92856-9926 Date of Request: 9/12/2022 004649 Contract Bond Libel ' Mutual. Status Query Ift SURETY CITY OF PALM SPRINGS Office: Los Angeles 3200 EAST TAHQUITZ CANYON WAY Phone: 800-763-9268 PALM SPRINGS, CA 92262 Fax: 855-318-1836 Email: StatusQuery@LibertyMutual.com In order to allow us to monitor the progress of our contractor, please complete and return this form. Your response will not prejudice your rights or affect our liability under our bond(s) referred to below. We enclose a prepaid return envelope for your use. Bond Number: 024254502 Contract Price: $5,758,200.00 Inception Date: 07/26/2021 Cross Reference Bond Number: Contract Description: 2021 Pavement Rehabilitation City Project No. 21-01. Our Bond On Behalf Of: MATICH CORPORATION Bond Executed In The Following Company: Liberty Mutual Insurance Company 1. HAS CONTRACT BEEN COMPLETED? 2. IF COMPLETED PLEASE STATE: a. Date of acceptance b. Total amount of completed contract 3. IF NOT COMPLETED PLEASE STATE: a. Probable completion date b. Amount paid contractor to date c. Amount withheld as retained percentage 4. HAS WORK PROGRESSED SATISFACTORILY? 5. ARE THERE ANY UNSATISFIED CLAIMS OR LIENS ON FILE? Signed (� V Tim Mikolajewski President - Liberty Mutual Surety Dated: RECEIVED Signed Name SEP 2 0 2022 Title Phone: Fax: Office of the City Clerk ` '7 File #: 1235 [CA](PUBLIC][COPY:EST] I Customer: City of Palm Springs Recording Requested by and Return to: 1 P.O. #: Matich Corporation I Project: Project# 24-01 DIR# 514093 1 Rec ID: 5E63CD66-705D-4734-A730-741097235240 P.O. Box 10 1 Job #: 49VYO 52700951885081 Highland, CA 92346-1010 1 Cert No.: CALIFORNIA PRELIMINARY NOTICE - PUBLIC WORKS (TfII6 IOTIG is GZV88 PORS T W G11ZF(80ZZa CIVIL C SS 8034(B), 8IO2, 8106-8118, 8200 et seq., 8612, 9300 et Seq.) >> TO THE PUBLIC ENTITY OR REPUTED City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs, CA 92262 USA >> TO DIRECT OR REPUTED CONTRACTOR Matich Corporation P.O. Box 10 Highland, CA 92346-1010 USA >> TO LENDER, SURETY OR BONDING CO. OR >> REPUTED LENDER, SURETY, BONDING CO. Alliant Insurance Services, Inc. Construction Services Group 18100 Von Karmen, loth Floor Irvine, CA 92612 USA Acct/Bond# 024273001 The following is a general description of the labor, service, equipment or materials furnished or to be furnished by the undersigned: Asphalt Materials 6 Delivery 2. The estimated amount of the work provided or to be provided is $8,799,456.00 3. The name of the person or entity who furnished that labor, service, equipment or materials is: Matich Corporation P.O. Box 10 Highland, CA 92346-1010 Relationship to Parties: General 4. The name of the person or entity who contracted for purchase of that labor, service, equipment or material is: City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs, CA 92262 USA 5. The description of the jobsite is: Project# 24-01 DIR# 514093 2024 Pavement Rehabilitation Various Locations throughout the City of Palm Springs, CA USA County of Riverside REQUEST FOR COPY OF PAYMENT BOND AND NAME OF SURETY COMPANY TO CONTRACTING BODY: City of Palm Springs or State Comptroller The undersigned Claimant hereby declares that he has supplied or will supply labor or materials as described above, that payment has not yet been made therefore; and that he hereby requests that the contracting body furnish a certified copy of the Payment Bond, if any, to the Claimant, at the address listed above, and the current address of the contracting public entity. NOTICE TO PROPERTY OWNER OR PUBLIC ENTITY I declare that I am authorized to file this claim on behalf of the Claimant. I have read the foregoing document and know the contents thereof; the same is true of my own knowledge. I declare under penalty of perjury that the foregoing is true and correct. Executed at Highland, California on 03/27/2024 for MA' CH CORPORA ION, Prepared by: Teri Wiley, it ager one: () 82-7400 Fax: (909) 382-0191 PROOF OF SERVICi BY MAIL AFFIDAVIT I declare that I served the Preliminary Notice, and any related documents, by certified or registered mail, postage prepaid, or other certified delivery, addressed to the above named parties, at the addresses listed abovp, on 03/27/2024. I declare under penalty of perjury that the foregoing is,tr and c rect. Execu= d at Highland, California on 03/27/2024. Prepared by: Peggy Brunswic r Assistant RECEIVED APR 0 3 2024 OFFICE OF THE CITY CLERK Dated: 05/16/24 II�II��IIIIIII�II�II MEC AY 2RECEIVED CALIFORNIA PRELIMINARY NOTICE OFFICE OF THE CITY CLERK lis is not a Lien. Civil Code Sections 8200, et seq., 9300, et seq. Reputed Owner or Public Entity 05/16/24 CA170875 CITY OF PALM SPRINGS 3200 E TAHQUITZ CANYON WAY PALM SPRINGS CA 92262 Reputed Construction Lender or Lessee OWNER FINANCED Reputed Direct Contractor MATICH CORPORATION PO BOX 10 HIGHLAND CA 92346 NOTICE TO PROPERTY OWNER EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances. This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units. 1 - You are hereby notified that MILLER EQUIPMENT COMPANY INC P O BOX 2956 LANCASTER CA 93539 2 - Has furnished or will furnish labor,services, equipment, or materials of the following general description: EQUIPMENT RENTAL / EARTHWORK / GRADING 3 - An estimate of the total price of the labor, services, equipment, or materials $200,000.00 4 - The building, structure or other work of improvement is located at: #24-008 2024 PAVEMENT REHABILITATION VARIOUS LOC. THROUGHOUT THE CITY OF PALM SPRINGS, CA COUNTY OF RIVERSIDE PALM SPRINGS CA 92262 (RIVERSIDE CO) 5- The party to or for whom the work is provided. MATICH CORPORATION PO BOX 10 HIGHLAND CA 92346 The relationship to the party(ies) giving this notice is: Subcontractor 6 - Name and addresG of Trust Funds to which Supplemental Fringe Benefits are payable (if applicable): Operating Engineers Trust Construction Laborers Trust 7 - Federal Public Work Jobsite Title 40 USC Sec. 270A-270E. Contract # Bond Co: Authorized Agent "t1 1-800-366-5660 ���•••/// This undersigned declares as follows: I am over the age of 18 and employed by Construction Notice Services. Inc., whose business address is 9520 Padgett Street,#208, San Diego. CA 92126. 1 am employed in the County of San Diego, where this mailing occurs, and not a party to this action. On the date shown below.in the City of San Diego. I served within California Preliminary Notice, sealed and deposited in the mail in the manner prescribed by law, by first class registered or certified mail. postage fully prepaid, to the person(s) at the address shown thereon. Signature: Date: 05/16/24 :r- _ - e . . ^ K4artinK4ariettaisproud tobeproviding sen�ceson Martin Marietta is on your job. Weare using Leve|set to set this job up for job! payn�entsuccess. \A/evvou|dlike toshare vv�hyou the yourinformation we have about your project. 32'2024-HMA Vorous|ocabuns Palm Springs, California 92262 Bond Number (if knmwn): Our Project Contribution �R.E1JN-1fNARYN'01(("1 AGGREGATES and/or CEMENT and/or READY MIX and/or ASPHALT and/or MAGNESIA PRODUCTS Work Starts / Material First Furnished 4/25/2024 Work Finishes / Material Last Furnished 5/6/2024 RECEIVED OFFICE OF THE CITY CLERK About Us Martin Marietta 4123Park|ukeAvenue Raleigh, North Carolina 27612 Referemce0N4MSQDPW7N There you will beable to: Contact Info Monica Lekas ° Send and receive messages about this document Martin Marietta ° Fix orprovide additional details Agent Phone: (8SD)944'671S Emai|:monica]ekas@martinmar\etta.com WA ����U��`� ' ~������" 9307110011701168140106 a We were hired by r Fill LEVEISET Subcontractor EBS GENERAL ENGINEERING INC 1345 QUARRY ST STE 101 CORONA, California 92879 Property Owner/ Public Entity City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs, California 92262 INGeneral Contractor Matich Corporation 1596 Harry Shepard Blvd San Bernardino, California 92408 Surety/Bonding Co. J Alliant Insurance Services, Inc. - Construction Services Group - Bond No.: 024273001 18100 Von Karman, 10th Floor Irvine, California 92612 Want more information on this project? Visit levelset.com/talk and enter RJN4MSQDPW7N Additional Info Property Description About the .lob Estimate of the total price of the labor, services, equipment or material furnished or to be furnished $10,000.00 NOTICE TO PROPERTY OWNER / PUBLIC ENTITY EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances. This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units. IMPORTANT: INFORMATION REQUEST PURSUANT TO §9550 et seq. If the public entity commissioning work and/or the surety are not identified in this notice, or if either are incorrectly identified, please accept this notice as a formal request to the direct contractor pursuant to §9550 et seq to deliver (i) The name and address of the public entity commissioning the work; and /or (ii) The name and address of the surety, if any; as the case may be; Further, if the direct contractor is not identified or is misidentified, please consider this a formal request to provide that information to Martin Marietta. Any information provided to Martin Marietta may be provided by visiting levelset.com/talk and entering RJN4MSQDPW7Nor by sending to the following address: Martin Marietta 4123 Parklake Avenue Raleigh, North Carolina 27612 Martin Marietta Signed by Monica Lekas Its duly authorized and disclosed agent Signed on May 19, 2024 Employee Trust Funds (and Laborers) If applicable, and pursuant to §8208 (b) of the California Civil Code, the following is a list of the Employee Trust Funds (described in subdivision (b) of Section 8024) and/or laborers to which payments are due. Want more information on this project? Visit levelset.com/talk and enter _ E V E L S E T RJN4MSQDPW7N e Mail Center PRESORT PO Box 9023 First -Class Mail Temecula, CA 92589-9023 U.S. Postage and Fees Paid W SO 9307 1100 1170 1168 1401 06 20240520-214 �I��'III'��"I'II�II�III�III�1��11�11'Il�l�'I���II��IIIIII'I�'I'1 City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs, CA 92262 CM CM as Martin Marietta is proud to be providing services on Martin Marietta is on your job. We are using Levelset to set this job up for your job! payment success. We would like to share with you the information we have about your project. 2024 PAVEMENT REHAB PROJECT Various locaitons Palm Springs, California 92262 Bond Number (if known): Our Project Contribution I4 AGGREGATES and/or CEMENT and/or READY MIX and/or l �fr i "' '� ° ASPHALT and/or MAGNESIA PRODUCTS Work Starts / Material First Furnished 4/25/2024 Work Finishes / Material Last Furnished 5/6/2024 RECEIVED MAY 2 8 2024 OFFICE OF THE CITY CLERK About Us Martin Marietta 4123 Parklake Avenue Raleigh, North Carolina 27612 levelset.com/talk Reference RJN4MSQDPW7N Contact Info There you will be able to: Monica Lekas • Send and receive messages about this document Martin Marietta • Fix or provide additional details Agent Phone: (858) 944-6715 Email: monica.lekas@martinmarietta.com EVELSET W - 9307110011701167969975 Subcontractor EBS GENERAL ENGINEERING INC 1345 QUARRY ST STE 101 CORONA, California 92879 Property Owner/ Public Entity City of Palm Springs 3200 E. Tahquitz Canyon Way Palm Springs, California 92262 Our Vendors (tf applicable) General Contractor Matich Corporation 1596 Harry Shepard Blvd San Bernardino, California 92408 Want more information on this project? Visit levelset.com/talk and enter 1 a;L E V E L s E T RJN4MSQDPW7N Additional Info Property Description About the Job Estimate of the total price of the labor, services, equipment or material furnished or to be furnished $10,000.00 NOTICE TO PROPERTY OWNER / PUBLIC ENTITY EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances. This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units. IMPORTANT: INFORMATION REQUEST PURSUANT TO §9550 et seq. If the public entity commissioning work and/or the surety are not identified in this notice, or if either are incorrectly identified, please accept this notice as a formal request to the direct contractor pursuant to §9550 et seq to deliver (i) The name and address of the public entity commissioning the work; and /or (ii) The name and address of the surety, if any; as the case may be; Further, if the direct contractor is not identified or is misidentified, please consider this a formal request to provide that information to Martin Marietta. Any information provided to Martin Marietta may be provided by visiting levelset.com/talk and entering RJN4MSQDPW7Nor by sending to the following address: Martin Marietta 4123 Parklake Avenue Raleigh, North Carolina 27612 Martin Marietta Signed by Monica Lekas Its duly authorized and disclosed agent Signed on May 16, 2024 Employee Trust Funds (and Laborers) If applicable, and pursuant to §8208 (b) of the California Civil Code, the following is a list of the Employee Trust Funds (described in subdivision (b) of Section 8024) and/or laborers to which payments are due. is _EVELSET Want more information on this project? Visit levelset.com/talk and enter RJN4MSQDPW7N A-7/6V CALIFORNIA PRELIMINARY NOTICE _] *****PLEASE ISSUE JOINT CHECKS***** NOTICE IS HEREBY GIVEN that: ROBERTSON'S 200 S MAIN ST CORONA CA 92882 (951)685-2200 Has or will Furnish labor, services, equipment, or materials, generally described as: READY MIX CONCRETE, ROCK & SAND To be furnished or furnished for the building, structure or the work of improvement described as follows: SALVIA RD & GENE AUTRY TR PALM SPRINGS J.C.N. # 245028 Tract No. J:24-008 Lot No.2024 PAVEMENT REHABILITATION Cert Num: 21232804 Name of Person or Firm who contracted for purchase of the labor, services, equipment, or materials is: EBS GENERAL ENGINEERING I 1345 QUARRY STREET SUITE 101 CORONA CA 92879 An estimate of the total price of said labor, services, equipment or materials is: 6, 073. 64 NOTICE TO PROPERTY OWNER EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, If the person or firm that has given you this notice is not paid In full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that Is appropriate under the circumstances. This notice Is required by law to be served by the undersigned as a statement of your legal rights. This notice is not Intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mall. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice If you are a residential homeowner of a dwelling containing four or fewer units. OWNER OR REPUTED OWNER OR PUBLIC AGENCY CITY OF PALM SRINGS 3200 E TAHQUITZ CANYON WAY PALM SPRINGS CA 92262 LENDER OR REPUTED LENDER DIRECT OR REPUTED DIRECT CONTRACTOR MATICH CORPORATION PO BOX 10 HIGHLAND CA 92346 SUBCONTRACTOR with whom claimant has contracted ALSO NOTIFIED TENANT OR BONDING AGENT RECEIVED JUN 0 4 2024 OFFICE OF THE CITY CLERK TRUST FUNDS TO WHICH SUPPLEMENTAL FRINGE BENEFITS ARE PAYABLE Proof of Service This undersigned declares as follows: I am over the age of 18, and employed by Robertson's, whose business address is 200 South Main Street, Suite 200, Corona, California 92882. I am employed in the County of Riverside, where this mailing occurs, and not a party to this action. On the date shown below, in the City of Corona, I served the within California Preliminary Notice, sealed and deposited in the mail in the manner prescribed by law, by first class registered or certified mail, postage fully prepaid, to the person(s) at the addresses shown thereon. IC Name: 05/30/2024 Date: ROBERTSON'S w-2f US POSTAGE°�.Pr�EYBOWES P.O. BOX 360000RONA, CA 92878-3600 ' $ 005.040 ZIP 92882 �' ••. 02 1fN 0001399944 MAY 30 2024 7108 1176 8852 1232 8048 IMPORTANT. CALIFORNIA PRELIMINARY NOTICE CITY OF PALM SRINGS 3200 E TAHQUITZ CANYON WAY PALM SPRINGS CA 92262 :..........•.;,,...•...;..:: :-'•:-:•:�. i 1f� ff�� f�f:l+e�f�:l:ffi�)i��it��fii'1'I�i 1111�}tfitlrl�f�� 32512 245028 Al 10 CALIFORNIA PRELIMINARY NOTICE This is not a lien. This is not a reflection on the integrity of any contractor or subcontractor, but the notice prescribed in California Civil Code Sections 8102, 8200, et seq., 9300, et seq. TO OWNER OR REPUTED OWNERS)/PUBLIC ENTITY CITY OF PALM SPRINGS 3200 E. TAHQUITZ CANYON WAY PALM SPRINGS, CA 92262 TO DIRECT CONTRACTOR MATICH CORPORATION P.O. BOX 10 HIGHLAND, CA 92346 TO LENDER/SURETY ALLIANT INSURANCE SERVICES, INC. 18100 VON KARMAN, 10TH FL IRVINE, CA 92612 BOND #024273001 NOTICE TO PROPERTY OWNER 1. The following is a general description of the labor, service, equipment or materials furnished or to be furnished: UTILITIES ADJUSTING 2. Estimated Price: $800,000.00 3. The name of the person who furnished that labor, service, equipment or materials is: EBS UTILITIES ADJUSTING, INC. 1345 QUARRY ST. SUITE 101 CORONA, CA 92879 951-279-6869 JOB NO. 245028 4. Date labor, service, equipment or materials first furnished: 4/24/2024 5. The name of the person who contracted for purchase of that labor, service, equipment or material is: MATICH CORPORATION JOB NO. 24-008 P.O. BOX 10 HIGHLAND, CA 92346 6. The description of the jobsite is: #24-012024 PAVEMENT REHABILITATION VARIOUS LOCATIONS, PALM SPRINGS, CA EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances. This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you mist within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given ycu th;s notice. The notice must be cant by registered or certified mail. Faaure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a'dwelling containing four or fewer units. Dated: May 29, 2024 By: I Courtney Dixon Authorized Agent For: EBS Utilities Adjusting Inc. PROOF OF NOTICE DECLARATION I declare that I served a copy of the above Preliminary Notice, and any related documents, by (as required by law) first-class, certified or registered mail, postage prepaid, addressed to the above named parties, at the addresses listed above, on5/29/2024. I declare under penalty of perjury that the foregoing is true and correct. Executed at Corona, CA on 5/29/2024. �1 RECEIVED J U N 0 3 2024 OFFICE OF THE CITY CLERK By Courtney Dixon Accounting Manager < a� lr� �.'f-.�:: i' j4�, ���''��.��.` �. ! ��� ..`l.t _ of � -, ,i+_ -i _� MAY 13 2024 /4--71 Io y Customer: MATICH CORPORATION File No: 4476 1 CA I PUBLICS Other Lender OFFICE OF THE CITY CITY PROJECT 24-01 Notice Requested by and Return To: Rec. ID: 266574 WESTERN RENTALS 14635 VALLEY BLVD. FONTANA, CA 92335 1 Job No: 24-008 CALIFORNIA PRELIMINARY NOTICE - PUBLIC WORKS (THIS NOTICE IS GIVEN PURSUANT TO CALIFORNIA CIVIL CODE §§ 8034(b), 8102, 9300 et seq.) TO: DIRECT CONTRACTOR TO: PUBLIC ENTITY (see California Civil Code § 8018) (see California Civil Code §§ 8036, 9302) MATICH CORPORATION CITY OF PALM SPRINGS P.O. BOX 10. 3200 E. TAHQUITZ CANYON WAY Highland, CA 92346 Palm Springs, CA 92262 TO: CONSTRUCTION SURETY/ LENDER TO: CUSTOMER (see California Civil Code § 8006, 8506, 8530-8538) MATICH CORPORATION N/A P.O. BOX 10. Highland, CA 92346 JOINT CHECK REQUESTED SEE ADDITIONAL LEGAL PARTIES: EXHIBIT D Please take notice that WESTERN RENTALS, 14635 VALLEY BLVD., FONTANA, CA 92335, Phone: (909) 822-8008, Fax: (909) 822.4850 has furnished or has agreed to furnish the following kind of equipment, labor, materials or services: HEAVY EQUIPMENT RENTALS. Relationship to the parties of the one giving this notice (subcontractor, supplier, describe if otherwise): Supplier The person to or for whom the same was done or furnished is: MATICH CORPORATION, P.O. BOX 10., Highland, CA 92346, Phone: (909) 382-7400, Fax: (909) 382-0113, which was performed in connection with the CITY PROJECT 24-01, VARIOUS LOCATIONS THROUGHOUT THE CITY OF PALM SPRINGS, CA COUNTY OF RIVERSIDE, SALVIA R & N GENE AUTRY TRAIL, Palm Springs, CA 92262 in the County of Riverside. The public entity for the above described work of improvement is CITY OF PALM SPRINGS, 3200 E. TAHQUITZ CANYON WAY, Palm Springs, CA 92262. The estimated value of all labor, services, equipment and materials to be furnished by Claimant is $20,000.00. The equipment, labor, materials or services was provided or will be provided beginning on April 29, 2024. PROOF OF SERVICE DECLARATION (CALFORNIA CIVIL CODE § § 8100-8118) I, JASMINE PALOMARES, declare that I served copies of the above CALIFORNIA PRELIMINARY NOTICE - PUBLIC WORKS, (check appropriate box): ❑ By personally delivering copies to (names(s) and title(s) of person served) at (address), on (date), at (time). By Registered or Certified Mail, Express Mail or Overnight Delivery by an express service carrier, addressed to each of the parties at the address shown above on May 8, 2024. By leaving the notice and mailing a copy in the manner provided in § 415.20 of the California Code of Civil Procedure for service of Summons and Complaint in a Civil Action. I certify under penalty of erjury that the foregoing is true and correct. Signed at FONTANA, CA on May 8, 2024, By: JASMINE PALOMARES, ACCOUNTS RECEIVABLES Prepared by: WESTERN RENTALS, 14635 VALLEY BLVD., FONTANA, CA 92335, Phone: (909) 822-8008, Fax: (909) 822-4850 v� Exhibit D - List of Additional Parties Owner: CITY OF PALM SPRINGS, 3200 E. TAHQUITZ CANYON WAY, Palm Springs, CA 92262 Project: CITY PROJECT 24-01, VARIOUS LOCATIONS THROUGHOUT THE CITY OF PALM SPRINGS, CA COUNTY OF RIVERSIDE, SALVIA R & N GENE AUTRY TRAIL, Palm Springs, CA 92262 in the County of Riverside The following is a complete list, to the best of our knowledge, of all additional or secondary parties with an interest in the aforementioned project: ADDITIONAL LENDER, SURETY OR BONDING COMPANY ALLIANT INSURANCE SERVICE, INC-CONSTRUCTION SERVICE GROUP CONSTRUCTION SERVICES GROUP 18100 VON KARMAN, 10TH FLOOR Irvine, CA, 92612 Bond Number: 024273001 Al I(oq File: 14436044 (CA PV) Customer: EBS UTILITIES ADJUSTING INC Notice Requested by: Customer #: / S & J Supply Co., Inc. Job Name: 2024 PAVEMENT REHAB DIR # 514093 13105 Florence Ave. Job# / PO#: 111511 Santa Fe Springs, CA 90670 562-944-7433 Cert #: 9314 8898 8030 0074 6707 06 APN #: PRELINIINARY NOTICE This is not a lien. This is not a reflection on the integrity of any contractor or subcontractor, but the notice prescribed in California Civil Code Sections 8102, 8200, et seq., 9300, et seq. TO OWNER OR REPUTED OWNER(S)/PUBLIC ENTITY CITY OF PALM SPRINGS 3200 E. TAHQUITZ CANYON WAY PALM SPRINGS, CA 92262 TO DIRECT CONTRACTOR MATICH CORPORATION P.O. BOX 10 HIGHLAND, CA 92-346 909-382-7400 TO LENDER/SURETY ALLIANT INSURANCE SERVICES 18100 VON KARMAN AVE LOTH FL IRVINE, CA 92612 Bond/Loan # 024273001 Joint Check Requested The following is a general description of the labor, service, equipment or materials furnished or to be furnished: MATERIAL SUPPLIER Estimated Price: $25,000.00 The name of the person who furnished that labor, service, equipment or materials is: S & J Supply Co., Inc. 13105 Florence Ave. Santa Fe Springs, CA 90670 5629447433 Date labor, service, equipment or materials first furnished: 5/20/2024 The name of the person who contracted for purchase of that labor, service, equipment or material is: EBS UTILITIES ADJUSTING INC 1345 QUARRY STREET STE101, CORONA, CA 92879 The description of the jobsite is: 2024 PAVEMENT REHAB DIR # 514093 #11151 MULTIPLE LOCATIONS, PALM SPRINGS, CA 92262 NOTICE TO PROPERTY OWNER EVEN THOUGH YOU HAVE PAID YOUR CONTRACTOR IN FULL, if the person or firm that has given you this notice is not paid in full for labor, service, equipment, or material provided or to be provided to your construction project, a lien may be placed on your property. Foreclosure of the lien may lead to loss of all or part of your property. You may wish to protect yourself against this by (1) requiring your contractor to provide a signed release by the person or firm that has given you this notice before making payment to your contractor, or (2) any other method that is appropriate under the circumstances. This notice is required by law to be served by the undersigned as a statement of your legal rights. This notice is not intended to reflect upon the financial condition of the contractor or the person employed by you on the construction project. If you record a notice of cessation or completion of your construction project, you must within 10 days after recording, send a copy of the notice of completion to your contractor and the person or firm that has given you this notice. The notice must be sent by registered or certified mail. Failure to send the notice will extend the deadline to record a claim of lien. You are not required to send the notice if you are a residential homeowner of a dwelling containing four or fewer units. Dated: 6/5/2024 MON � �06� PROOF OF NOTICE DECLARATION Laura Pavey / CRF Solutions Authorized Agent For: S & J Supply Co., Inc. I declare that I served a copy of the above Preliminary Notice, and any related documents, by (as required by law) first-class, certified or registered mail, postage prepaid, addressed to the above named parties, at the addresses listed above, on 6/5/2024. I declare under penalty of perjury that the foregoing is true and correct. Executed at Simi Valley, CA on 6/5/2024. RECEIVED By: Laura Pavey / Lien Administrator JUN 17 2024 OFFICE OF THE CITY CLERK r141 � 11 v I S 11)" , Ili , Construction Notice Department P.O. Box 1389 Simi Valley, CA 93062 Address Service Requested 6/5/2024 CITY OF PALM SPRINGS SJS562 14436044 3200 E. TAHQUITZ CANYON WAY PALM SPRINGS, CA 92262 IMPORTANT NOTICE PLEASE READ CAREFULLY Enclosed you wlimn a notice that is being sent to you on behalf of S & J Supply Co., Inc. in regards to the construction project known as 2024 PAVEMENT REHAB DIR # 514093 11151 and located at MULTIPLE LOCATIONS, PALM SPRINGS, CA 92262. It is important to note that this notice is not a lien nor a claim on a bond. This is a routine procedure to comply with certain state requirements that may exist and should not reflect in any way on the integrity or credit standing of any of the known interested parties associated with this job. Our records indicate the following parties are associated with this job: OWNER: CITY OF PALM SPRINGS PALM SPRINGS, CA GENERAL/DIRECT/ORIGINAL CONTRACTOR: MATICH CORPORATION HIGHLAND, CA LENDER/SURETY: ALLIANT INSURANCE SERVICES IRVINE, CA If any of this information is incorrect, or you are not associated with this job, please contact us immediately at myjobinfo@crfsolutions.com Please use this number, 14436044 in your email subject line. Thank you, CRF Solutions 0